48.101 General
Source: FAR 48.101 on acquisition.gov
FAR 48.101 establishes value engineering as a tool for contractors to propose or be required to implement cost-saving measures, with specific rules for voluntary and mandatory participation and savings sharing.
Overview
- FAR 48.101 outlines the general principles and approaches of value engineering in government contracts. Value engineering is a formal process that allows contractors to propose cost-saving methods or requires them to implement a value engineering program, aiming to reduce acquisition, operation, or support costs without compromising essential functions.
Key Rules
- Voluntary Value Engineering (Incentive Approach)
- Contractors may voluntarily submit Value Engineering Change Proposals (VECPs) using their own resources. If accepted, the contractor shares in the resulting savings and is reimbursed for allowable development and implementation costs. This approach should not increase government costs unless savings are realized.
- Mandatory Value Engineering Program
- The government may require a contractor to establish a value engineering program as a separately priced contract item. The contractor must perform value engineering as specified in the contract. Savings sharing is at a lower rate than the voluntary approach, and architect-engineer contracts are excluded from sharing. The goal is to focus contractor efforts on areas with significant savings potential.
Responsibilities
- Contracting Officers: Must determine whether to include voluntary or mandatory value engineering requirements and ensure proper contract clauses and pricing.
- Contractors: Must comply with the value engineering approach specified in the contract, submit VECPs as appropriate, and follow program requirements if mandated.
- Agencies: Oversee implementation, review VECPs, and ensure savings are realized without loss of essential functions.
Practical Implications
- Value engineering encourages cost savings and efficiency in contract performance. Contractors can benefit financially from accepted proposals, but must follow specific procedures. Misunderstanding the approach or failing to comply with program requirements can result in lost savings opportunities or noncompliance.
(a) Value engineering is the formal technique by which contractors may (1) voluntarily suggest methods for performing more economically and share in any resulting savings or (2)be required to establish a program to identify and submit to the Government methods for performing more economically. Value engineering attempts to eliminate, without impairing essential functions or characteristics, anything that increases acquisition, operation, or support costs.
(b) There are two value engineering approaches:
(1) The first is an incentive approach in which contractor participation is voluntary and the contractor uses its own resources to develop and submit any value engineering change proposals (VECP’s). The contract provides for sharing of savings and for payment of the contractor’s allowable development and implementation costs only if a VECP is accepted. This voluntary approach should not in itself increase costs to the Government.
(2) The second approach is a mandatory program in which the Government requires and pays for a specific value engineering program effort. The contractor must perform value engineering of the scope and level of effort required by the Government’s program plan and included as a separately priced item of work in the contract Schedule. No value engineering sharing is permitted in architect engineer contracts. All other contracts with a program clause share in savings on accepted VECP’s, but at a lower percentage rate than under the voluntary approach. The objective of this value engineering program requirement is to ensure that the contractor’s value engineering effort is applied to areas of the contract that offer opportunities for considerable savings consistent with the functional requirements of the end item of the contract.
