Contract Types & Vehicles
CPFF (Cost-Plus-Fixed-Fee)
What is a cost-plus-fixed-fee contract?
A cost-plus-fixed-fee (CPFF) contract reimburses allowable performance costs under the contract terms and provides a negotiated fee. The fee is an amount fixed at the start, not a percentage that automatically grows with actual cost. Federal Acquisition Regulation (FAR) 16.306 explains the arrangement.
The fee can change when the contracted work changes. It is not a guaranteed profit margin. A contractor can incur costs that are not reimbursed, and fee payment remains subject to the performance conditions in the contract.
When is a cost-plus-fixed-fee contract used?
A cost-plus-fixed-fee contract is used when the government needs a defined result or level of effort but cannot estimate the cost with enough confidence for a fixed-price contract. FAR 16.306 covers completion and term forms. Agencies often use CPFF contracts for research, development, and complex professional services. The contracting officer must still define funding, oversight, allowable costs, and the conditions for fee payment.
A worked cost-and-fee example
Consider an illustrative estimate of $1 million in cost and a negotiated fee of $60,000. If allowable cost reaches $1.1 million with the required authorization and funding, the fee does not automatically become $66,000. The original $60,000 is separate from the cost increase.
Keep cost and fee in separate columns in the proposal workbook. That makes it easier for reviewers to distinguish staffing or rate changes from a proposed fee change. Label the total clearly rather than treating every dollar as performance cost.
Completion and term forms
The completion form defines a goal and an end product. The term form commits a specified level of effort for a stated period. The contract's form affects what the team must demonstrate to support fee payment.
For a completion effort, connect the staffing and estimate to the required result. For a term effort, reconcile the proposed hours and period with the specified level of effort. The proposal manager should confirm which form the solicitation uses before reusing a prior response.
Funding is a separate control
An estimated total cost is not the same as the amount currently funded. FAR 16.301-1 describes cost-reimbursement ceilings. The applicable contract clauses establish the specific funding, notice, and performance obligations.
Track available funding and forecast expenditure separately. Assign an owner to monitor the relevant limit and prepare required notices. Do not assume a likely funding increase has already been authorized.
Questions for the bid review
Identify the completion or term form, cost assumptions, fee basis, and current funding schedule. Confirm which team owns timekeeping, cost records, and the forecast to complete. Record open questions for the contracting officer instead of hiding uncertainty inside a single total.
Review the work plan with finance. Check whether proposed hours cover the promised effort and whether the rate assumptions match the estimate period. Keep the basis for each major input available for review.
Compare this approach with firm-fixed-price contracts, where performance costs affect the contractor's result without automatically changing the agreed price.
