37250PR260000050 - USCG AIR STATION SAN DIEGO CREW BERTHING ROOMS RENOVATIONS - CONSTRUCTION
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
The U.S. Coast Guard is seeking a small business contractor to perform complete renovations of the Aircrew Duty Berthing Room in Building D at Sector San Diego. The project involves the demolition and installation of commercial-grade fixtures, including dimmable LED lighting with red-light modes, a full bathroom renovation with new plumbing and flooring, the installation of approximately 590 square feet of luxury vinyl plank flooring, and interior painting of six sleeping rooms and common areas. All work must be completed within 60 calendar days of the Notice to Proceed, with standard weekday working hours. Due to the detection of low concentrations of lead, the contractor must comply with Cal/OSHA Lead in Construction Standards and ensure proper off-site disposal of hazardous waste. Proposals are due by September 18, 2026, and must include product data sheets, safety plans, a technical schedule, and proof of professional licensing. This contract is subject to the Davis-Bacon Act, requiring the payment of prevailing wages for San Diego County.
General Info
Agency
NAICS
Place of Performance
San Diego, CA, 92101, USASet-Aside
Documents
(3)AI Contract Breakdown
Uniform Contract FormatWhat is UCF?
Uniform Contract Format (UCF) uses AI to break down any contract into standardized sections—scope, pricing, deliverables, and evaluation criteria.
Timeline
Response Deadline
Organization & Contact Information
Full Description
Solicitation: Aircrew Duty Berthing Renovations
Set-Aside: Total Small Business Set-Aside (FAR Subpart 19.5)
Location: USCG Sector San Diego, Building D (Aircrew Duty Berthing Room), 2170 N. Harbor Drive, San Diego, CA 92101
Important Dates
-
Questions Due: September 15, 2026
-
Proposals Due: September 18, 2026, by 11:59 PM Eastern Time
1. Project Background and Objective
The U.S. Coast Guard requires complete renovations of the Aircrew Duty Berthing Room in Building D at Sector San Diego. The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, and supervision necessary to modernize the space for active-duty personnel.
2. Scope of Work (Summary) - Please review the attached Statement of Work (SOW) for full technical requirements, safety standards, and applicable codes.
The Contractor is responsible for the demolition of existing materials and the installation of new commercial-grade fixtures. Key tasks include:
-
Lighting Renovation: Replace existing light fixtures with new fully dimmable LED fixtures featuring a selectable red-light mode across 6 sleeping rooms, 1 central hallway, and 1 bathroom.
-
Bathroom Renovation: Demolish existing fixtures, tile, and shower pan. Install a new commercial-grade toilet, sink/vanity with enclosed storage, shower pan, low-maintenance sheet vinyl flooring, and a new mirror.
-
Flooring Installation: Remove approximately 590 sq ft of existing carpet and install new Luxury Vinyl Plank (LVP) flooring, including new baseboards and trim.
-
Interior Painting: Prepare and paint all interior walls and trim in the 6 sleeping rooms and the common passageway.
3. Site Conditions & Hazardous Materials
An Asbestos and Lead Survey was conducted for this facility (AESS Job No. 26-092).
-
Asbestos: No asbestos was detected in the Berthing Room in Building D.
-
Lead: Lead was detected at very low concentrations (<0.00146% to 0.0039% by weight). While below the EPA/HUD threshold for Lead-Based Paint, any detectable level of lead triggers Cal/OSHA Lead in Construction Standard (8 CCR § 1532.1) compliance.
-
Handling & Disposal: Debris and waste generated from the removal of lead-containing materials must be evaluated for appropriate disposal classification (TCLP or TTLC) prior to off-site disposal. Government dumpsters shall not be used.
4. Period of Performance and Hours
All work shall be completed within 60 calendar days from the issuance of the written Notice to Proceed (NTP). Work hours are Monday through Friday, 0800 to 1700 hours, excluding federal holidays. Any disruption to utilities must be coordinated at least 72 hours in advance.
5. Wage Determinations
This project is subject to the Davis-Bacon Act (FAR 52.222-6). Prevailing wages for San Diego County, CA, apply. See the attached General Decision Wage Determination.
6. Proposal Submission Requirements
To be considered for award, interested offerors must submit the following documents with their proposal:
-
Product Data Sheets & Warranties: For LED lighting fixtures, bathroom vanity, toilet, shower pan, LVP flooring, and any other major items to be replaced.
-
Samples: Paint color and flooring finish samples or spec sheets.
-
Safety Plans: An Activity Hazard Analysis (AHA) & Accident Prevention Plan (APP) detailing Cal/OSHA compliance for lead-containing materials and general construction safety.
-
Technical Plan: Detailed technical plan outlining the project schedule from the post-award walk-through to construction completion.
-
Past Performance & Licensing: Relevant past performance examples and proof of valid professional and trade licenses (plumbing, electrical, tile-setting).
-
Pricing: Transparent pricing sheet breaking down labor, materials, waste disposal, and the total proposed cost.
Attachments
-
Statement of Work (SOW) - Aircrew Duty Berthing Renovations
-
Davis-Bacon Wage Determination - San Diego, CA
-
Asbestos and Lead Survey Report - AESS Job No. 26-092
All questions should be directed to the Contracting Officer prior to the Q&A deadline.
Similar Contracts
Same NAICS industry code
More opportunities from Department Of Homeland Security → Base Los Angeles/long BEACH(00037)
Same awarding agency