Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, August 19 at 2:00 PM EDT

Register Free →

486363_Sentinel Peak Resources_UIC

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The project involves reworking two existing oil wells in the Arroyo Grande Oil Field—Hyla 16 SPNR (API #079-21280) and Rock 12L R (API #079-21268)—by cementing an inner casing string to repair casing holes and restore well integrity. Operations are scheduled to take place over five days per well during the Fall, Winter, or Spring seasons, with daily work hours from 7:00 AM to 6:00 PM, totaling 10 hours per day. All activities will be conducted on existing well pads using current roadways and infrastructure, with no new surface disturbance, no expansion of facilities, and no change in the use of underground resources. Electricity, production storage, treatment, and transportation will all rely on pre-existing systems, ensuring minimal environmental impact. The California Department of Conservation’s Geologic Energy Management Division (CalGEM) is overseeing the permitting process under the California Environmental Quality Act (CEQA), with the project qualifying for multiple categorical exemptions including Class 1 (Existing Facilities), Class 2 (Replacement or Reconstruction), Class 4 (Minor Land Alterations), and Classes 7 and 8 (Protection of Natural Resources and Environment). Compliance with Public Resources Code § 3280(b) regarding Health Protection Zones is required, and all work must adhere to regulatory standards protecting public health, safety, and environmental quality. No federal contract clauses from the Federal Acquisition Regulation (FAR) or Defense FAR Supplement (DFARS) are applicable, as this is a state-regulated environmental permitting action rather than a federal procurement. The estimated duration, location, operational constraints, and environmental compliance measures are clearly defined, but no contract value, pricing, evaluation factors, payment details, or submission deadlines are specified in the available documentation. The primary point of contact for inquiries is Bryan Norman, Associate Oil and Gas Engineer at CalGEM, reachable via phone or email, with additional administrative support provided through the Orcutt office.

General Info

Rework two existing oil wells with casing repair, no new surface disturbance, under CalGEM oversight during fall-winter-spring.

Agency

California Conservation, Department of

NAICS

213112 - Support Activities for Oil and Gas OperationsView NAICS

Place of Performance

1821 Price Canyon Rd, CA, 93401

Set-Aside

NONE

Documents

(1)

486363 Sentinel Peak Resources UIC CEQA Notice of Exemption

PDFceqa-notice-of-exemption

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia Conservation, Department of
Contacts1 person available
OfficeN/A
Organization / Agency
California Conservation, Department of
Office AddressN/A
Contacts
Bryan NormanAssociate Oil and Gas Engineer

Full Description

Show more
Work involves cementing an inner casing string to cover a casing hole. The estimated duration of this project is 5 days per well with 10-hour operations from 7:00AM to 6:00PM. The work will be completed in the Fall/Winter/Spring. Work will occur on an existing well pad and will be accessed by existing roadways. There will be no surface disturbance and no change in the utilization of the underground resource. No expansion or new facilities will be required. Electricity will be supplied by the existing infrastructure. The production will be stored, treated, and transported utilizing existing facilities. The proposed project consists of the California Department of Conservation, Geologic Energy Management Division (CalGEM) approving 2 permits for Sentinel Peak Resources to rework the wells listed below, in the Arroyo Grande Oil Field. API # Well Name 079-21280 Hyla 16 SPNR 079-21268 Rock 12L R

Similar Contracts

Same NAICS industry code

NAICS: 213112
New
Federal
E-Seal Technology: A New Paradigm for Leaky Well Remediation
Solicitation # S-197080
E-Seal Technology is an intelligent, electrokinetic sealant designed to remediate leaks in aging wellbores by flowing like water into sub-millimeter fractures and then transforming into a durable, jammed plug when an electric field is applied. Unlike conventional cement or polymer treatments that fail to reach narrow cracks due to particle bridging, E-Seal uses engineered micelles and colloidal particles that are precisely steered by electrophoresis, electro-osmosis, and dielectrophoresis to penetrate and seal the smallest leak pathways. Once concentrated in the fracture, the micelles form a high-viscosity network that remains intact after power is removed, creating a long-lasting barrier resistant to high temperatures, pressures, and aggressive brines. The system is further enhanced by optional additives such as lanthanum and cerium trivalent cations, which accelerate aggregation and precipitate low-solubility minerals, and polymer gel particles that swell and reinforce the seal upon contact with leaking fluids. The technology integrates an AI-powered control system that monitors seal formation in real time and dynamically adjusts voltage to optimize performance, making it the first actively steered wellbore repair platform. Beyond sealing, the applied electric field simultaneously mitigates galvanic corrosion of well casings, addressing a critical integrity issue. E-Seal offers a tenfold cost reduction compared to existing solutions and is not limited to oil and gas applications—it is equally effective in geothermal wells, carbon capture storage sites, dams, tunnels, mining infrastructure, and radioactive containment systems. The technology is patent pending and developed by Los Alamos National Laboratory under Triad, a Department of Energy contractor, with licensing opportunities available for commercialization. Deployment is targeted at legacy well plugging, methane leak compliance, asset life extension, and subsurface infrastructure repair, with performance validated in challenging environments where traditional methods fail.
Triad - DOE Contractor

POSTED

2 days ago

DEADLINE

in about 2 months
View Details
NAICS: 213112
New
Federal
F--JELA Well Plugging - 2026
Solicitation # 140PS126B0009
The contract pertains to oil and well plugging activities at Jean Lafitte National Historical Park and Preserve, with a focus on environmental restoration and infrastructure maintenance. Work is scheduled to begin following the issuance of a Not-to-Proceed notice, with the primary period of performance running from September 15, 2026, to March 14, 2027, or within 180 days of full mobilization approval. The scope includes plugging four specific wells—Flemming Plant, Marrero Land Well, and Anne C Herrick Well—alongside the removal of flowlines and junk from the JELA oilfield. All work must adhere to a detailed Statement of Work, comply with federal, state, and local codes including 29 CFR 1910.1200, EPA SNAP and WaterSense standards, and be executed in a workmanlike manner per FAR 52.236-5. Performance is restricted to weekday business hours unless special authorization is granted, and all materials must be new, suitable, and approved by the Contracting Officer. The procurement is conducted as a sealed bid under FAR Part 14 using a Lowest Price Technically Acceptable (LPTA) evaluation method, meaning award is solely based on the lowest responsive and responsible offer with no trade-offs for technical merit or past performance. Offerors must hold a valid Unique Entity Identifier and CAGE code, and submit electronically via email to the designated Contracting Officer by the deadline of August 20, 2026, at noon local time. All submissions must include the Standard Form 1442, Limitation in Subcontracting Worksheet, Davis Bacon Wage Determination, and applicable representations regarding small business status, socioeconomic criteria, and compliance with federal prohibitions on Chinese telecom equipment and ByteDance applications. Subcontracting is capped at 85% for general construction and 75% for special trades, and the contractor must indemnify the government against all liabilities. Safety requirements include MUTCD and OSHA compliance, mandatory submission of Safety Data Sheets, and adherence to stop-work authority provisions. Payment must be submitted electronically through the Treasury’s Invoice Processing Platform, and the Contracting Officer’s Representative will be named post-award to oversee performance while carrying no authority to modify contract terms.
Nps Conops Strategic DOI

POSTED

3 days ago

DEADLINE

in 13 days
View Details
NAICS: 213112
New
SLED
Oil Well Casing Repair ServicesThe contract involves repairing damaged casing on the existing oil well designated as 6-8UW located in Taft, California, using reclaimed produced water as part of the restoration process. The scope of work includes a comprehensive well integrity assessment to evaluate the condition of the casing, followed by targeted patching or full replacement of compromised sections to ensure structural soundness and operational safety. All repair activities must comply with industry standards for well abandonment and rehabilitation protocols, with a specific emphasis on environmental stewardship through the use of reused produced water. The project requires final pressure testing to validate the integrity of the repaired casing and confirm conformity to regulatory and safety benchmarks. The contract is classified as a subcontract under NAICS code 213112, which pertains to oil and gas well drilling and servicing activities. It was posted on August 3, 2026, by the California Department of Conservation, indicating state-level oversight and alignment with California’s environmental and energy regulations. The work is to be performed at the specified location in Taft, with all materials and methods subject to state environmental compliance requirements, particularly regarding water usage and waste management. Although no solicitation number or point of contact is provided, the official project page is accessible via the California CEQA Net portal for administrative reference.
California Conservation, Department of

POSTED

5 days ago

DEADLINE

N/A
View Details