Alessandro Ponds Optimization Phase II

Open
1575PState & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The Alessandro Ponds Optimization Phase II project, managed by the Construction Department of Eastern Municipal Water District, involves the deepening of existing retention ponds at the Alessandro Ponds site in San Jacinto, California. The scope of work includes the grading of Ponds No. 1, 2, and 3, including bottoms, slopes, and access roads, with an estimated export of 120,000 cubic yards of excess soil. Key infrastructure improvements include the replacement of a 21 inch pipeline with a new 20 inch PVC C900 pipeline, the installation of 12 inch inlet piping, 18 inch and 8 inch transfer piping, and the application of 8 inch thick soil cement protection to newly graded pond slopes. This public works contract is awarded based on the total bid, with a response deadline of December 15, 2026. Bidders must demonstrate responsibility by providing an eight year experience record showing the successful completion of at least three similar projects involving mass grading of 50,000 cubic yards or more and the installation of pipelines 12 inches or larger. Required submissions include resumes of key personnel, a 10 percent bid bond submitted via Surety 2000, Cal-OSHA Form 300A, and a non-collusion declaration. The contractor is responsible for all safety programs and must comply with South Coast Air Quality Management District Rule 403 for Large Operations. Upon award, the contractor must furnish performance and payment bonds each equal to 100 percent of the contract amount.

General Info

Contract for deepening retention ponds and installing pipelines in San Jacinto, California.

Place of Performance

EMWD’s Alessandro Ponds Site - Intersection of Olmstead Street and Alessandro Avenue, CA, USA

Set-Aside

NONE

Documents

4
PDF, High priority: read this firstspecifications
High
PDF, High priority: read this firstifb
High
PDF, High priority: read this first7 pages · ifb
High
PDF, High priority: read this first21 pages · rfp
High

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

View Full Breakdown

Timeline

PhaseSolicitation
Posted

Solicitation

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Get full access to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Construction Department of Eastern Municipal Water District
Contacts1 person available
OfficeCA, USA

Full Description

Show more
Scope: The work to be constructed is located at EMWD’s Alessandro Recycled Water Ponds Site located northeast of the intersection of Olmstead Street and Alessandro Avenue within Riverside County. The work comprises of the grading of Ponds No. 1, 2 and 3 at the Alessandro Ponds Site, including the bottom, slopes and access roads. Approximately 120,000 CY of excess soil export will be required. The project also includes replacement of an existing 21” pipeline that fills the ponds with a new 20” PVC C900 pipeline, installation of 12” PVC C900 inlet piping, 18” and 8” PVC C900 transfer piping installation, valves and appurtenances, and application of 8-inch thick soil cement protection to the newly graded pond slopes.
Notes: Bid Results will be available in PlanetBids once time for receiving bids has expired.
Bid Bond: 10.00%

Similar Contracts

Same NAICS industry code

More opportunities from California → Construction Department of Eastern Municipal Water District

Same awarding agency

NAICS: 237110
SLED
Lindenberger Road Pipeline Replacement
Solicitation # 1588W
The Lindenberger Road Pipeline Replacement project, solicitation number 1588W, is a public works contract issued by the Construction Department of the Eastern Municipal Water District in California. Located at the intersection of Lindenberger Road and Simpson Road in Menifee, the scope of work involves the installation of approximately 200 linear feet of 30-inch to 36-inch cement mortar lined and coated welded steel transmission pipeline and the removal or abandonment of approximately 300 linear feet of existing pipeline. The contractor is responsible for all associated tasks, including trenching, shoring, dewatering, installation of isolation and air/vac valves, corrosion monitoring systems, pressure testing, disinfection, and full site restoration including asphalt grind and overlay and pavement striping. Bids are due by 10:00 a.m. on November 17, 2026, and must be submitted electronically via the PlanetBids portal. The contract will be awarded to the lowest qualified bidder based on total price, provided they are responsive and a company employee has inspected the jobsite. Bidders must hold a Class A or C-34 license and provide a 10 percent bid bond via Surety 2000, with 100 percent performance and labor payment bonds required upon award. Compliance with Cal/OSHA safety standards, ADA accessibility regulations, and prevailing wage rates is mandatory. Progress payments are based on a Schedule of Values, with submissions due by the 10th of each month to ensure timely processing.
Water and Sewer Line and Related Structures Construction

POSTED

25 days ago

DEADLINE

in 4 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS