This Solicitation opportunity from Iowa was posted on May 29, 2024. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
Big Cedar Industrial Center Water Main Extension (Phase 1
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The contract involves the installation of approximately 5,650 linear feet of 30-inch water main, connecting the intersection of Edgewood Road SW and 60th Avenue SW to Old Bridge Road SW in Cedar Rapids, Iowa. The project is estimated to cost around $5 million and is scheduled to commence immediately upon receipt of the Notice to Proceed, with a late start date set for August 12, 2024. The work is divided into two stages, with Stage 1 requiring completion by September 20, 2024, including construction, disinfection, and hydrostatic testing of the initial segment. Stage 2 involves completing the remaining pipe, installing an automatic flushing station, and final testing, with a deadline of May 20, 2025. The overall project is expected to take 75 working days, with Stage 1 allocated 25 days and Stage 2 allocated 50 days. Key milestones include the completion of Stage 1 by September 2024 and Stage 2 by May 2025, with provisions for sewer construction by other contractors and the possibility of constructing parts of Stage 2 prior to sewer work. The contract is managed by the City of Cedar Rapids, with a designated point of contact and a detailed procurement process outlined, including submission deadlines and project specifications. This project forms part of broader municipal infrastructure improvements, emphasizing timely delivery and adherence to testing and disinfection standards.
General Info
Place of Performance
IA, USASet-Aside
Documents
7AI Contract Breakdown
Uniform Contract FormatContract not broken down yet
CLEATUS splits the solicitation into Uniform Contract Format (UCF) sections: scope, pricing, deliverables, and evaluation criteria.
This one is closed. Find the next one like it.
Open contracts like this one, right now:
- 26350 Lynchburg, VA - CSO 70 Sewer ImprovementsOpen now, due in 17 days
- Lift Station No. 85 ReplacementOpen now, due in 28 days
Ask CLEATUS
I've read this contract. Ask me anything.
Timeline
Submission Closed
Organization & Contact Information
Full Description
Early Start Date: Upon Receipt of Notice to Proceed Late Start Date: 8/12/2024 Milestones: Milestone 1: 9/20/2024 – Construction, disinfection, and hydrostatic testing of Stage 1 Water Main from STA 500+00 to STA 524+47 Including 30” Tee with 30” Service Butterfly Valve. Milestone 2: 5/20/2025 – After sewer construction by others is completed, construct Stage 2 pipe, install automatic flushing station, hydrostatic test and disinfect Stage 2 watermain, complete seeding and final completion items. Note Stage 2 pipe can be constructed to Station 554+66 including butterfly valve V-7 prior to sewer work. Leave Stage 2 pipe empty until all pipe is installed and ready for testing and disinfection. Final Completion: Overall: Working Days - 75 Stage 1: Working Days - 25 Stage 2: Working Days – 50
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS