C1DA--Project 575-23-107 | Expand Electrical Capability | Design

Awarded
36C25925R0113Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This contract awards design services for expanding the electrical capacity of the Grand Junction VA Medical Center to support future growth and temporary facilities. The project involves remodeling and expanding two existing electrical rooms on the north side of the campus, adding 800 square feet of space to accommodate new switchboards, panels, and an Automatic Transfer Switch, while also constructing a new electrical room on the east side to supply power to future temporary workspaces. The electrical system must deliver a minimum of three-phase, 208V, 800A with dedicated circuits for normal, critical, life safety, and emergency loads, terminating at the new eastern electrical room after passing through necessary step-down equipment. All temporary facilities must be designed to integrate with this new infrastructure, using 208V and operating at no more than 80% of available amperage per branch circuit. The design must strictly comply with the National Electric Code, VA Design Manuals, NFPA standards, IBC 2003, and other applicable codes and VA publications, with all work coordinated through the VA’s technical information library. Penetrations through fire barriers require prior approval and must meet VA and NFPA requirements, and all systems must be tested and commissioned as part of the design deliverables. The contractor is responsible for ensuring compatibility with existing building control systems and integrating energy-efficient technologies. All finishes must align with the VA interior designer’s specifications, and detailed construction documents including red-lined changes must be submitted within 30 days of project completion. The contract is awarded under a Service-Disabled Veteran-Owned Small Business set-aside, managed by the Department of Veterans Affairs, Network Contract Office 19, with completion expected to support expanded medical services and operational continuity on the Grand Junction campus.

General Info

Extension granted to SF-330 submission deadline for SDVOSB electrical expansion project at Grand Junction VA.

Agency

Department Of Veterans Affairs → Network Contract Office 19 (36C259)View Agency

Contract Value

$574,773

NAICS

541330 - Engineering ServicesView NAICS

Place of Performance

CO

Set-Aside

SDVOSBC

Awardee

CITRINE LLCView Profile

Award Issued Date

Documents

(3)

36C25926C0059_1.docx

DOCX

36C25925R0113.docx

DOCX

Past+Performance+Questionnaire.pdf

PDF

AI Contract Breakdown

Uniform Contract Format

What is UCF?

Uniform Contract Format (UCF) uses AI to break down any contract into standardized sections—scope, pricing, deliverables, and evaluation criteria.

Timeline

PhaseAwarded
Posted

Presolicitation

Awarded

Contract was awarded

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyDepartment Of Veterans Affairs → Network Contract Office 19 (36C259)
Contacts1 person available
OfficeGreenwood Village, CO, 80111, USA
Organization / Agency
Department Of Veterans Affairs → Network Contract Office 19 (36C259)
View Agency Profile
Office AddressGreenwood Village, CO, 80111, USA
Contacts
Mark HollandContract Specialist

Full Description

Show more
SCOPE OF WORK: This contract will provide designs for expanding the electrical capacity of the Grand Junction VA Medical Center. The A-E is to provide design services to expand the electrical capacity of the Grand Junction VA Medical Center (2121 North Ave, Grand Junction, CO  81501).
The contractor shall design the following:
Statement of Work: The Grand Junction VA Medical Center campus has 22 buildings, with 321,557 gross square feet of space. To expand services, the VA requires additional electrical power on the north and east sides of the campus. The northern electrical room remodel will support future expansions while the newly created eastern electrical room will support temporary facilities that provide workspaces for displaced employees. In the past, temporary spaces have been modular in nature and could be tents, trailers or other types of temporary facilities.
Most work will be conducted indoors, however, Grand Junction, CO has a semi-arid climate, with hot summers and generally mild winters. During the summer months temperatures typically reach into the 90s Fahrenheit during the day, while evenings tend to remain comfortable and cool. Winters are usually mild, but snow does occur, and temperatures can cool down to freezing averages. Spring and fall tend to be transitional seasons with moderate temperatures. The area receives around ten (10) inches of precipitation per year with most of it falling from April through August.
Specific project tasks:
Remodel and add on to 1634-1 (433 SF) / 1635-1 (433 SF) to ensure adequate electrical utilities exist to support the north portion of the WCHCS on the Grand Junction, CO campus. This will include expanding the rooms by 800 SF to the west. This additional space will allow the hospital to add switchboards and panels when needed and enclose an Automatic Transfer Switch (ATS).
Add a new electrical room to ensure adequate electrical utilities are in place on the eastern side of the WCHCS on the Grand Junction, CO campus. This will provide electrical capacity from location 1 on the western side of the WCHCS to location 2 (see attachment A) on the eastern side.
The minimum power requirements are three-phase, 208V, 800A and include normal, critical, life safety and emergency power circuits. This electrical run will terminate in a new conditioned electrical space at location 2 after passing through necessary electrical step-down equipment at site 3. Any future projects that have temporary facilities will be designed to be compatible with 208V and use no more than 80% of the amperage available per branch circuit. These facilities will be expected to run power from their location to the new electrical room distribution point designed at location 2.
All aspects of the design must adhere to the NEC Design manuals posted on the VA technical information library at the following sites: http://www.cfm.va.gov/til/ and https://vatilms.va.gov/vatilms/catalog.
All electrical, architectural, and mechanical work for these systems will be designed by the A-E.
The installation must, at a minimum, be in accordance with all applicable codes indicated in the Department of Veterans Affairs (VA) Design Manuals and VA Publications (Master Construction Specifications, Construction Standards, National Fire Protection Association (NFPA), Underwriters Laboratory, International Building Code IBC 2003, NFPA and National Electric Code (NEC), building codes and standards, and VA Information Security Handbook 6500.6, etc.).
DESIGN CRITERIA: As part of the design the following list needs to be considered:
All electrical work will be terminated by the contractor. The design must be clear who and what is supplied for the termination equipment.
Any penetration through any fire barriers whether a floor or wall will be done in this contract to meet VA standards and National Fire Protection Association (NFPA). The contractor shall obtain permits issued by the facility before any penetration shall occur.
The installed system and its components shall be tested and commissioned. This will be included in the design and construction documents.
Implement new technologies in electrical systems to improve and facilitate energy usage reductions. The system will be compatible with the existing control systems on station.
All finishes will be coordinated with the VA interior designer and called out in a finish schedule.
All testing and balancing parameters will be provided by the A-E.
Design documents that show the red lines will be submitted by the contractor to the A-E, put into the AutoCAD drawings and submitted within 30 days of the completion of the construction project. According to VA standards as outlined in the VA Specifications Technical Library.
All existing utilities which are designed to be relocated or modified shall have directions to the contractor on the new location and modifications.

Similar Contracts

Same NAICS industry code

NAICS: 541330
New
Scattergood GS. Units 1&2 Green Hydrogen-Reaady Modernization
Solicitation # scattergood-gs-units-12-green-hydrogen-reaady-modernization
Kiewit Infrastructure West Co. is seeking sub-quotes for the Scattergood GS Units 1 and 2 Green Hydrogen-Ready Modernization project for the City of Los Angeles Department of Water and Power. The scope of work is extensive, encompassing professional and technical services such as civil, structural, mechanical, electrical, and instrumentation and controls engineering, as well as utility locating, geotechnical and geophysical investigations, BIM/3D modeling, and environmental assessments. Additional requirements include hazardous materials surveys, permitting support, and CPM scheduling. Interested firms must contact Kiewit to receive an Invitation to Bid via the Building Connected system, with a bid date of September 11, 2026, and a response deadline of September 30, 2026. Eligible bidders include Disadvantaged, Minority, Women, and Other Business Enterprises, provided they hold certifications from recognized agencies such as the SBA or MBDA. Responsive bidders must possess a valid California Contractor's license and provide acceptable insurance. Subcontractors and material contractors are required to provide bonding for 100 percent of their contract value, though Kiewit will reimburse the associated bond premiums. Furthermore, Kiewit, as a signatory to various collective bargaining agreements, requires bidders to demonstrate an ability to maintain labor harmony on the project. For further information or to review plans and specifications, interested parties should contact Lead Estimator Joe Bockelman.
Kiewit Infrastructure West Co.

POSTED

about 7 hours ago

DEADLINE

in 18 days
View Details
NAICS: 541330
New
Subcontracting Opportunity: City of Bend’s Southwest Sewer Improvement Phase 3, Project No. 1SSW3
Solicitation # 27-3214
Parametrix is seeking qualified subconsultants to provide civil engineering design and right-of-way services for the City of Bend’s Southwest Sewer Improvement Phase 3, Project No. 1SSW3. The project aims to address sewer system deficiencies in southwest Bend by extending a gravity trunk sewer line to unsewered areas, decommissioning existing pump stations in the Romaine Village area, and installing service laterals to transition properties from private septic systems to public sewer. The scope may also include roadway reconstruction, ADA curb ramp and curb design, and minor transportation improvements such as turn lanes or mini roundabouts. The project is funded by the Clean Water State Revolving Fund administered through the Oregon Department of Environmental Quality, with a total design and construction budget of 3,875,000 dollars. The procurement process is managed by the City of Bend, with a proposal deadline of September 29, 2026. Selection is based on technical and administrative capabilities, with the potential for interviews to influence final scoring. Key deliverables include a preliminary engineering report, a public outreach plan, and construction contract documents at 30, 60, 90, and 100 percent completion, culminating in record drawings. The City intends to advertise for construction services in Fall or Winter 2027. Parametrix is actively soliciting firms with recognized federal, tribal, state, local, or independent DBE certifications as part of a good faith effort to include small, minority-owned, women-owned, and veteran-owned businesses.
Parametrix

POSTED

about 7 hours ago

DEADLINE

in 17 days
View Details
NAICS: 541330
New
SLED
Design / Engineering for Microgrid System and DC fast charger
Solicitation # PE-64458-NONST-2027-000000037
The City of Decatur is seeking qualified professional engineering firms to provide turnkey services for the design, bid assistance, and construction administration of a microgrid system and DC fast charger for electric vehicles at the Decatur Police Department located at 420 West Trinity Place. The project involves integrating a solar photovoltaic generation system and a battery energy storage system designed to optimize renewable energy and peak demand management during normal grid-connected operations, while ensuring critical loads remain operational during emergency grid-islanded conditions. The selected consultant will be responsible for delivering complete design plans for bidding and providing construction administration through installation, commissioning, testing, and interconnection with Georgia Power. This solicitation, posted on September 11, 2026, requires proposals to be submitted by October 13, 2026. The project is funded by the City and a Department of Energy grant, necessitating strict compliance with Build America, Buy America (BABA) requirements and federal regulations. Awarded firms must maintain a non-discrimination policy and carry an umbrella insurance policy of at least 5 million dollars. Evaluation is based on a 100-point weighted system, and the expected project start date is November 2026, following coordination with Georgia Power. Payment will be made monthly based on progress reports and invoices submitted to the City Manager.
City of Decatur

POSTED

about 19 hours ago

DEADLINE

in about 1 month
View Details

More opportunities from Department Of Veterans Affairs → Network Contract Office 19 (36C259)

Same awarding agency

NAICS: 334510
New
Federal
36C25926Q0858| Sources Sought on Brain Stimulator for Salt Lake City VA Medical Center
Solicitation # 36C25926Q0858
The Department of Veterans Affairs, through Network Contracting Office 19, is conducting a market survey to identify potential sources for a Transcranial Magnetic Stimulation (TMS) machine for the Salt Lake City VA Medical Center. This Sources Sought Notice, under NAICS code 334510, is intended for planning purposes to determine vendor capabilities and socioeconomic size classifications. Interested companies must submit their responses to Lynn Lim by 12:00 pm MT on September 14, 2026, providing company details, entity IDs, delivery timelines, and manufacturer information. The required equipment must be a biphasic waveform stimulator supporting repetitive (rTMS) and Intermittent Theta Burst Stimulation (iTBS) capabilities, featuring air-cooled figure-of-eight coils and a 3D navigation stim guide coil positioning system. The scope of work includes the procurement, delivery, installation, provider training, and ongoing maintenance of the machine at the George E. Whalen VA Medical Center in Salt Lake City, Utah. All equipment must comply with FDA regulations and medical device standards, incorporating safety features such as emergency stop buttons and software safeguards to prevent over-stimulation. Respondents must certify the country of origin for the end products using the Buy American Certificate (FAR 52.225-2) and demonstrate robust quality assurance processes. While the contractor will not have access to sensitive VA information, they are obligated to protect any PHI or PII in accordance with federal guidelines. This notice is for research only and does not constitute a solicitation or a commitment by the government to award a contract.
Electromedical and Electrotherapeutic Apparatus Manufacturing

POSTED

about 23 hours ago

DEADLINE

in 2 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 650+ contractors already using CLEATUS