This Government Contract opportunity from Department Of Defense was posted on April 3, 2020. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

Design-Bid-Build Walter F. George (WFG) Long Term Riprap Repair - Walter F. George Dam, Chattahoochee River, AL and GA

Awarded
W9127819R0076Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237990
New
SLED
Carlson Field Athletic Complex: Construction of new Pickleball Courts
Solicitation # BCP-REC-26
The Town of Hingham, Massachusetts, is soliciting sealed bids for the construction of eight new pickleball courts at the Carlson Field Athletic Complex, with an estimated project cost of $1,300,000. The scope of work includes site preparation such as the removal of trees and shrubs, re-grading, and the installation of the courts, posts, nets, walkways, benches, shade shelters, and ADA pathways. Additionally, the project requires a new asphalt parking lot and the installation of solid AF-6 Acoustifence Panels around the entire perimeter for sound attenuation. The contractor is responsible for maintaining construction fencing and erosion control, coordinating closely with the Town and the demolition contractor, Pasquazzi Bros, Inc. The contract will be awarded to the lowest responsible and eligible bidder who possesses at least seven years of experience constructing sports courts or similar athletic facilities. Bidders must provide a statement of qualifications, including three similar public project examples and three references, one of which must be a Massachusetts municipality from the last two years. This is a lump sum, fixed-price contract with no escalation for fuel, labor, or materials. Compliance with Massachusetts prevailing wage laws, OSHA regulations, and the Massachusetts Building Code is mandatory. Bids must be submitted electronically via the OpenGov portal by November 3, 2026, at 9:00 am, and must include a 5% bid security.
Recreation

POSTED

about 12 hours ago

DEADLINE

in 4 days

AI Contract Overview

Show more

The contract involves a large-scale repair project for the Walter F. George Dam located on the Chattahoochee River, addressing the upstream armored face on two non-overflow earthen dikes on both the Alabama and Georgia sides. The government plans to award a single Firm Fixed Price contract, with an estimated value ranging from $25 million to $100 million. The work is to be completed in three phases: first, the removal and replacement of the armoring system on the dikes between elevation 186.00 and 190.00 during a six-week reservoir pool drawdown; second, similar repairs from elevation 190.00 to 205.00 under normal water levels, with recovery and stockpiling of existing stones; and third, the restoration and stabilization of haul roads and laydown areas impacted during construction. The project requires strict adherence to work procedures such as not penetrating the soil embankment and maintaining existing armor stone ownership by the U.S. Government. The Walter F. George Lock and the George Andrews Lock will be closed for the duration of the project. The solicitation will be publicly advertised using FAR Part 15 source selection procedures and posted as a downloadable PDF on the Federal Business Opportunities website (FedBizOpps). Prospective contractors and their teams must be registered in both FedBizOpps and the System for Award Management (SAM) to access solicitation documents and submit bids, which must be done electronically. The project falls under NAICS code 237990, and small businesses are defined based on average annual receipts of less than $39.5 million over three years. Bidders will communicate questions via an online RFI system specified in the solicitation, with limited responses guaranteed. There will be no printed bid packages, telephonic or mailed requests for documents, and bid options are not anticipated but may be included if deemed beneficial. Site visit information and Clarification processes will also be managed through official electronic channels to ensure transparency and equal access to information.

General Info

Firm fixed-price $25-$100M repair for Walter F. George Dam dike armor, three-phase project.

Contract Value

$23,726,799.29

NAICS

237990 - Other Heavy and Civil Engineering Construction

Place of Performance

AL, USA

Set-Aside

NONE

Award Issued Date

Documents

8

W9127819R0076_AM01.pdf

PDF

W9127819R0076_DRAWINGS.pdf

PDF

W9127819R0076_EM_385-1-1.pdf

PDF

W9127819R0076+Pre-Proposal+Conference+Slides.pdf

PDF

W9127819R0076+Sign-in+Sheet+for+Pre-Proposal+Conference.pdf

PDF

W9127819R0076+Solicitation+-+AM02+DRAWINGS.pdf

PDF

W9127819R0076+Solicitation+-+AM02.pdf

PDF

W9127819R0076+Solicitation.pdf

PDF

AI Contract Breakdown

Uniform Contract Format

Contract not broken down yet

CLEATUS splits the solicitation into Uniform Contract Format (UCF) sections: scope, pricing, deliverables, and evaluation criteria.

Timeline

5 updates
PhaseAwarded
Posted

Presolicitation

Notice updated

Response deadline added: Dec 19, 2019. The notice description changed.

Type Changed

Presolicitation → Solicitation

Notice updated

Response deadline time changed from 8:00 PM UTC to 7:00 PM UTC on Dec 19, 2019. The notice description changed.

Notice updated

Notice details unchanged. Attachments may have changed.

Notice updated

Notice details unchanged. Attachments may have changed.

Notice updated

Notice details unchanged. Attachments may have changed.

Awarded

Contract was awarded

Submission Closed

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → W074 Endist Mobile
Contacts2 people available
OfficeMOBILE, AL, 36602-3630, USA
Office AddressMOBILE, AL, 36602-3630, USA
Contacts
Chanda D. StrenthContract Specialist
Sara G. LogsdonContract Officer

Full Description

Show more
THIS PROJECT WILL BE ADVERTISED ON AN UNRESTRICTED BASIS UTILIZING FAR PART 15 SOURCE SELECTION PROCEDURES THE NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE FOR THIS PROJECT IS 237990. The solicitation will be available for download 29 October 2019 (approximately). The estimated cost range of this project is between $25,000,000 and $100,000,000. The Government intends to award one Firm Fixed Price 'C' type contract as a result of this solicitation. The work to be performed under this contract consists of repairing the upstream armored face on two non-overflow earthen dikes at Walter F. George Dam on the Chattahoochee River. The non-overflow earthen dikes are located on the right (west - Alabama side) and left (east - Georgia side) overbank areas. The new armoring system will be placed on both the Alabama earthen dike and the Georgia earthen dike. Construction shall be completed in three phases and staging areas are provided on both the Alabama and Georgia side. During the removal and placing of the new armor system, the contractor shall not penetrate the soil embankment. All existing armor stone shall remain the property of the United States Government. Phase I will include the removal of the existing armor stone & bedding stone and installation of the new armoring system from elevation 186.00 to elevation 190.00. To facilitate removal of the existing armor system without damaging the impervious embankment, the reservoir pool will be lowered to elevation 186.0 feet for 6 weeks. The Contractor shall remove the existing armor system and install the new armoring system from elevation 186.00 to elevation 190.00 in this 6 week period. The contractor shall ensure sufficient amount of material, equipment, and personnel are on site to perform the work in this specified time frame. Phase II will include the removal of the existing armor stone & bedding stone and installation of the new armoring system from elevation 190 to 205. Normal summer/winter pool levels will be operated during this phase of construction. All existing armor stone shall be recovered and stock piled from elevation 195 to 205. Phase III will include the milling or removal and or reconstruction of pavements for the Haul roads utilized and impacted throughout Phase I and Phase II Construction. Phase III will also include the final stabilization of the Georgia and Alabama laydown areas. Walter F. George Lock and George Andrews Lock will remain closed for the duration of this project. Note No. 1: All prospective contractors and their subcontractors and suppliers must be registered in Federal Business Opportunities (FedBizOpps) before they will be allowed to download solicitation information. Contractors must be registered in the System for Award Management (SAM) at https://www.sam.gov/SAM/ prior to award of this contract. Solicitation documents, plans and specifications will only be available via FedBizOpps. Registration for plans and specifications should be made via FedBizOpps Internet Homepage. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. This solicitation will not be issued on CD-ROM. Neither telephonic, mailed, nor fax requests will be accepted. Registration should be completed one week prior to the issue date. It is therefore the Contractor's responsibility to monitor the website daily for the solicitation to be posted, and for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. Plans and specifications will not be provided in a printed-paper format; however, the Government reserves the right to revert to paper medium when it is determined to be in the Government's best interest. NOTE: This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/reader. Note No. 2: All bid forms, bid bonds, and other normal documents required for the bid submittal, including amendments to the bid submittal, shall be electronic format with the proposal. Note No. 3: Critical path method (network analysis system) is not required. Note No. 4: For this job, a small business is defined as having average annual receipts of less than $39,500,000 for the past three years. Note No. 5: It is anticipated that this solicitation will not have bid options. However, optional bid items may be added if it is determined to be in the Government's best interest. Note No. 6: All advertisements of Mobile District projects will be through the Federal Business Opportunities (FedBizOpps). Detailed information on this and other Mobile District Projects (Ordering Solicitations, Points of Contact, Synopsis of Work, etc.) are available on the Internet at: https://www.fbo.gov. Address questions concerning downloading of plans/specifications to the Contract Specialist indicated above. Note No. 7: Site Visit information will be posted with the solicitation. Note No. 8: The request for information (RFI) process for bidder inquiries during the advertisement period will be through the ProjNet internet based system, and specifics will be contained in the RFP solicitation package available exclusively from FedBizOpps. Other forms of communicating RFIs to the Government will not be honored. The Government will try to respond to all questions. However, responses may not be furnished to all questions and particularly those received late in the advertisement period (0-10 days prior to bid opening.)

More opportunities from Department Of Defense → W074 Endist Mobile

Same awarding agency

NAICS: 236220
New
Federal
Black Warrior, Tombigbee, Alabama, Coosa Rivers Project Management Office
Solicitation # W9127826RA087
Solicitation W9127826RA087 is an unrestricted, two-phase, design-build construction project issued by the U.S. Army Corps of Engineers, Mobile District. The project involves the construction of a multi-level Operations Division office building for the Black Warrior, Tombigbee, Alabama, Coosa Rivers Project Management Office in Tuscaloosa, Alabama. The scope of work encompasses all necessary labor, equipment, and materials for site work, utilities, and environmental remediations, ensuring compliance with Department of War, U.S. Federal, and partner nation codes. The project has an estimated value between 10 million and 25 million dollars, with a strict Construction Cost Limitation of 21 million dollars; any proposal exceeding this limit will be deemed non-responsive. The anticipated completion period is 545 days. The procurement process is divided into two phases, with Phase One focusing on the evaluation of proposals to select a maximum of five firms for Phase Two, where detailed design requirements will be provided. Award will be based on a non-price/price trade-off analysis to determine the best value, prioritizing the design concept, preliminary schedule, and small business participation. Key requirements include a 100 percent performance bond, adherence to EM 385-1-1 safety standards, and the provision of a specialized design-build team including a Design Quality Control Manager. Proposals must be submitted electronically via the Procurement Integrated Enterprise Environment portal in PDF format.
Commercial and Institutional Building Construction

POSTED

about 16 hours ago

DEADLINE

in 7 days
View Details

Earlier notices in this NAICS code

Posted before this notice, open and closed

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS