This Award Notice opportunity from Florida was posted on January 31, 2025. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
Show more
Contract E3Y12 is a district maintenance agreement between the Florida Department of Transportation District 3 and Gaskin Contractors Landscape Division LLC for landscaping and irrigation work at the SR 75 (US 231) Welcome Center in Jackson County. Executed on January 31, 2025, for a total amount of 700,676.99 dollars, the project was designated as a Small Business set-aside under the Business Development Initiative. The work officially commenced on February 28, 2025, following a Notice to Proceed issued on March 4, 2025, with an original performance period extending to September 17, 2027.
The project scope included the installation of landscape materials and a comprehensive irrigation system adhering to technical specifications for PVC piping and weather sensors. Throughout the execution phase, the contract timeline was adjusted multiple times to account for holidays and inclement weather, resulting in a total of 61 weather days and 12 holiday days granted. Final acceptance of the project was recommended on November 12, 2025, upon the successful completion of installation items, initiating a two-year establishment period for the landscape elements managed by the contractor.
General Info
FDOT and Gaskin Contractors agreement for SR 75 Welcome Center landscaping and irrigation.
HighAI Summary for FDOT Contract E3Y12 - Holiday Letter No. 3 (Labor Day 2025): A formal notice from the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC regarding Contract E3Y12 for the SR 75 (US 231) Welcome Center in Jackson County. The letter grants a contract time extension of four (4) days for the Labor Day holiday period from 08/29/25 through 09/01/2025, bringing the total holiday days granted to date to 11.
PDF
PDF, High priority: read this firstrfb
HighAI Summary for FDOT District 3 Bid Solicitation Notice - November 12, 2024: A bid solicitation notice from the Florida Department of Transportation (FDOT) District 3, dated November 12, 2024. It outlines the requirements for submitting bids via Bid Express by December 12, 2024, including instructions for digital IDs, document ordering through CPP.fdot.gov, prequalification requirements for construction projects over $250,000, and protest procedures under Florida Statutes.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for FDOT Welcome Center Landscaping - Jackson County SR 75: Landscape and irrigation plans for the State of Florida Department of Transportation (FDOT) Welcome Center project in Jackson County (SR 75/US 231), Financial Project ID 453870-1-52-01. The document includes an index of plans, signature sheets, and general project notes regarding plant material delivery, site conditions, and utility coordination. Dated October 1, 2024.
PDF
PDF, High priority: read this firstmodification
HighAI Summary for Holiday Letter No. 1 (Memorial Day 2025) - Contract E3Y12: A notice from the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC regarding Contract E3Y12 for the SR 75 (US 231) Welcome Center in Jackson County. The letter grants a 3-day contract time extension for the period of 05/24/25 through 05/26/25 due to the Memorial Day holiday, in accordance with Supplemental Specifications Sub-Article 8-7.3.2.
PDF
PDF, High priority: read this firstmodification
HighAI Summary for Holiday Letter No. 2 - Contract E3Y12: A notice from the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC regarding Contract E3Y12 for the SR 75 (US 231) Welcome Center in Jackson County. The letter grants a 4-day contract time extension for the Independence Day holiday period (07/03/2025 through 07/06/2025), bringing the total holiday days granted to date to 7.
PDF
PDF, High priority: read this firstmodification
HighAI Summary for Holiday Letter No. 4 (Veterans Day 2025) - Contract E3Y12: A formal notice from the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC regarding a contract time extension for Contract E3Y12 (SR 75 Welcome Center). The letter grants one (1) additional day to the total authorized contract time due to the suspension of operations for Veterans Day on November 11, 2025, bringing the total holiday days granted to date to 12.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for T590 Irrigation Installation and Equipment: Technical Special Provision (TSP) T590 detailing the requirements for the furnishing and installation of an irrigation system and related equipment. It includes design requirements, quality assurance standards for licensed contractors, and detailed technical specifications for PVC piping, two-wire control systems, weather sensors, and control valves.
PDF
PDF, High priority: read this firstmodification
HighAI Summary for Weather Letter No. 2 (May 2025) - Contract E3Y12: A formal notice from the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC regarding Contract E3Y12 for the SR 75 (US 231) Welcome Center in Jackson County. The letter grants 7 calendar days of additional contract time due to inclement weather for the period of May 1 to May 31, 2025, bringing the total weather days granted to date to 12.
PDF
PDF, High priority: read this firstmodification
HighAI Summary for Weather Letter No. 4 - Contract E3Y12: Dated August 5, 2025, this letter from the Florida Department of Transportation notifies Gaskin Contractors Landscape Division LLC that seven (7) calendar days of additional contract time have been granted for inclement weather during July 2025 for the SR 75 (US 231) Welcome Center project in Jackson County.
PDF
PDF, High priority: read this firstmodification
HighAI Summary for Weather Letter No. 7 - Contract E3Y12: A formal notice from the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC regarding Weather Letter No. 7 for October 2025. The document grants ten (10) calendar days of additional contract time due to inclement weather for the SR 75 (US 231) Welcome Center project in Jackson County, bringing the total weather days granted to date to fifty-six (56).
PDF
PDF, High priority: read this firstmodification
HighAI Summary for Weather Letter No. 8 - Contract E3Y12: A formal notice from the Florida Department of Transportation dated December 9, 2025, regarding Contract E3Y12 for the SR 75 (US 231) Welcome Center in Jackson County. The letter grants Gaskin Contractors Landscape Division LLC five (5) additional calendar days for inclement weather occurring between November 1 and November 12, 2025, bringing the total weather days granted to date to 61.
PDF
PDF, Low priorityother
LowAI Summary for CN-550000-E3Y12-00090000: The document contains a single generic instruction stating that information should be factual and supported by reference. It does not contain specific procurement details.
PDF
PDF, Low priorityaward
LowAI Summary for Contract E3Y12 Final Acceptance - SR 75 Welcome Center: Correspondence from the Florida Department of Transportation recommending final acceptance for Contract E3Y12 (SR 75 Welcome Center in Jackson County) as of November 12, 2025. The document confirms completion of installation items per specifications and notes a two-year establishment period for landscape items managed by Gaskin Contractors Landscape Division LLC.
PDF
PDF, Low priorityaward
LowAI Summary for FDOT Contract E3Y12 - Gaskin Contractors Landscape Division LLC: Executed contract and bid blank between the Florida Department of Transportation (District 3) and Gaskin Contractors Landscape Division LLC for a landscaping project at the SR 75 (US 231) Welcome Center in Jackson County. The contract, numbered E3Y12, was executed on January 31, 2025, for a total amount of $700,676.99, with a performance period from February 20, 2025, to September 17, 2027.
PDF
PDF, Low prioritymodification
LowAI Summary for FDOT Weather Letter No. 1 - Contract E3Y12: A letter from the Florida Department of Transportation dated May 7, 2025, notifying Gaskin Contractors Landscape LLC that 5 calendar days of contract time have been granted due to inclement weather for the period of April 2025 regarding the SR 75 (US 231) Welcome Center project in Jackson County.
PDF
PDF, Low prioritynotice-to-proceed
LowAI Summary for Notice to Proceed - Contract E3Y12 (SR 75 Welcome Center Landscaping): A Notice to Proceed issued by the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC on March 4, 2025. It authorizes the commencement of work for Contract E3Y12 (SR 75 Welcome Center Landscaping in Jackson County) effective February 28, 2025.
PDF
PDF, Low priorityother
LowAI Summary for State of Florida Information Document: A brief document containing a date reference (8/26/2025) regarding information available to the State of Florida.
PDF
PDF, Low prioritymodification
LowAI Summary for Weather Letter No. 5 - Contract E3Y12: A formal notice from the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC regarding Weather Letter No. 5 for August 2025. The document grants 7 calendar days of additional contract time due to inclement weather for the SR 75 (US 231) Welcome Center project in Jackson County, bringing the total weather days granted to date to 38.
PDF
PDF, Low prioritymodification
LowAI Summary for Weather Letter No. 6 - Contract E3Y12 (September 2025): A formal notice from the Florida Department of Transportation to Gaskin Contractors Landscape Division LLC regarding Weather Letter No. 6 for the SR 75 (US 231) Welcome Center project. The letter grants 8 calendar days of additional contract time for inclement weather occurring in September 2025, bringing the total weather days granted to date to 46.