This Solicitation opportunity from Department Of Defense was posted on July 14, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
HOUSING, MECHANICAL
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
This contract pertains to the procurement of a mechanical housing with NSN 3040-01-527-8176, requiring strict compliance with first article testing and production lot testing protocols. The contractor must test one unit of the specified item and submit a comprehensive first article test report within 120 calendar days of contract award, providing prior written notice to the contracting officer and quality assurance representative at least 14 days before shipment for government inspection. The approved first article unit must be retained by the contractor as a manufacturing standard throughout the entire production lifecycle and may be referenced to resolve quality issues, with final disposition governed by DFARS 252.245-7004(d). Production lot testing is mandatory following first article approval, requiring the contractor to present samples for government selection, with one unit randomly chosen from each production lot; testing samples must be shipped to the Redstone Technical Test Center with full documentation including signed inspection forms, test results, certifications, drawings, and a prepaid return label. The contractor is responsible for covering all costs associated with consumed or destroyed samples during testing. The contract specifies a delivery timeline of 591 days after award and falls under solicitation SPE4A6-26-T-06LU issued by the Department of Defense’s ASC Commodities Division. Fast pay is not applicable, and all testing and delivery requirements are tied to specific procurement notes addressing first article disposition and production lot verification. The contractor must adhere to detailed shipment protocols, including proper labeling, inclusion of required forms per MIL STD 129, and submission of tracking and return documentation to the contracting officer. The item is to be delivered to New Cumberland, Pennsylvania, with contract performance closely monitored by the quality assurance representative. The government will issue written approval, conditional approval, or disapproval of the first article within 120 days of receiving the test report. All proprietary information must be marked appropriately to restrict public disclosure, and sample sizes not explicitly defined as “ZZ” must be confirmed with the QAR in accordance with the technical data package or government-provided sample plan.
General Info
Agency
NAICS
Place of Performance
2083 NORMANDY DRIVE DOOR 113 TO 134, NEW CUMBERLAND, PA, 17070-5002, USASet-Aside
Timeline
Submission Closed
Organization & Contact Information
Full Description
‘OTHER EQUIVALENT' AND PROVIDE DETAILS OF CURRENT DEALER/DISTRIBUTOR
CERTIFICATION AND/OR ACCREDITATION.
Fast Pay does not apply to this solicitation
FIRST ARTICLE APPROVAL – CONTRACTOR TESTING REQUIRED (FAR 52.209-3 and ALT I)
THE CONTRACTOR SHALL TEST 1 UNIT(S) OF LOT/ITEM 3040 / 15278176 AS SPECIFIED IN THIS CONTRACT. PROVIDE WRITTEN NOTICE TO THE CONTRACTING OFFICER AND THE QAR AT LEAST FOURTEEN (14) CALENDAR DAYS PRIOR TO SHIPMENT TO GOVERNMENT FOR FAT, TO ACCOMODATE IN-PROCESS VERIFICATION AND/OR FINAL INSPECTION BY THE QAR. THE CONTRACTOR SHALL SUBMIT THE FIRST ARTICLE TEST REPORT WITHIN 120 CALENDAR DAYS FROM THE DATE OF THIS CONTRACT. NOTIFICATION AND SUBMITTAL ADDRESSES ARE IAW PROCUREMENT NOTE H03. WITHIN 120 CALENDAR DAYS AFTER THE GOVERNMENT RECEIVES THE TEST REPORT, THE CONTRACTING OFFICER SHALL NOTIFY THE CONTRACTOR, IN WRITING, OF THE CONDITIONAL APPROVAL, APPROVAL, OR DISAPPROVAL OF THE FIRST ARTICLE. SEE PROCUREMENT NOTE H03: SUPPLEMENTAL FIRST ARTICLE TESTTING REQUIREMENTS (SEP 2016) FOR ADDITIONAL FAT REQUIREMENTS.
DISPOSITION OF FIRST ARTICLES:
Procurement Note E01: Supplemental First Article Exhibit Disposition Contractor Maintained (MAY 2020)
The first article units will be maintained or returned to the contractor to be used as a manufacturing standard. The contractor shall hold the approved first article units at the production facility until all production quantities have been produced and accepted. In the case of indefinite delivery contracts, the contractor shall hold the first article units until final production run has been approved and accepted on the first delivery order. The unit shall be considered a production guide or manufacturing standard if defects are reported on delivered material or problems are encountered during production. When disposing the units, the contractor shall follow DFARS 252.245-7004(d).
Procurement Note E04: Production Lot Testing – Government (MAY 2020)
(1) The purpose of production lot testing (PLT) is to validate quality conformance of products. PLT is to be completed on the production lot(s) after First Article approval, when a first article is required. The contractor shall price the PLT CLIN to cover the cost of the approved samples that are consumed, destroyed or otherwise rendered unusable during testing.
(2) The contractor shall provide written notice to the contracting
SPE4A6-26-T-06LU
SECTION A
officer and the QAR at least fourteen (14) calendar days (or as otherwise specified in the contract) prior to the date when the contractor will present the production lot to the QAR for selection of PLT samples.
(3) The QAR will select 1 samples, at random from the production lot(s) produced. If the quantity stated in the previous sentence equals "ZZ", the contractor should use the appropriate sample size identified within the Technical Data Package or applicable Sample Plan provided by the Government. The contractor will seek approval of the sample size with the QAR.
(4) The contractor shall ship the PLT samples by traceable means to:
RTTC REDSTONE W31P0W REDSTONE ARSENAL REDSTONE TECHNICAL TEST CENTER ATTN: CHARLES EAKES BLDG 4500
REDSTONE ARSENAL AL 35898
Shipment shall be marked “Production lot samples – do not post to stock”, contract and lot number. A copy of the DD250/IRAPT Receiving Report shall be placed on the exterior of the shipping container in accordance with MIL STD 129. Include the following interior documentation: DD Form 1222 and DD250/IRAPT receiving report signed by the QAR, copy of contract/order, copies of test reports showing actual results and tolerances specified in the technical data package, material and process certifications, process operations and inspection method sheets, copies of drawings used to manufacture the PLT sample (proper marking to assert proprietary or other rights to restrict public disclosure is the contractor’s responsibility), documents required under contract deliverables requirements list, a prepaid shipping label or document with the information required to return the PLT samples to the contractor at no cost to the Government.
(5) At time of shipment, copies of the signed DD Form 1222, DD250/IRAPT Receiving Report, transportation tracking information and information for return of the PLT samples shall be provided to the contracting officer. The Government testing time will be 90 test plus 90 NSN/Part Number: 3040-01-527-8176 Quantity: 1 EA Purchase Request: 7017486596QTY: 1 Delivery: 591 days ADO
More opportunities from Department Of Defense → ASC COMMODITIES DIVISION
Same awarding agency
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 650+ contractors already using CLEATUS