Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, August 19 at 2:00 PM EDT

Register Free →

Installation of Electric Shore Power Infrastructure by San Diego Unified Port District at Fish Harbor Pier and Chesapeake Wharf

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The San Diego Unified Port District will install electric shore power infrastructure at Fish Harbor Pier and Chesapeake Wharf to comply with California Air Resources Board mandates, addressing the facility’s outdated electrical systems that currently cannot support required shore power capabilities for moored vessels. The project includes the removal of four multi-trunk paperbark trees, which will be replaced with four 24-inch box trees near Tuna Harbor, and the installation of a new 480V-208V power center connected via underground conduit to an existing SDG&E switchboard adjacent to the Chesapeake Fish Company parking lot. Three dual-receptacle pedestals will be mounted along the north side of the pier, each providing one 100A three-phase and one 30A single-phase outlet for vessel connections. The existing antiquated electrical distribution system serving the pier and wharf will be fully replaced, with all wiring upgraded and new conduits installed along the perimeter and under the pier, with no in-water work, fill, or overwater structures involved. Construction is scheduled to begin in Fall 2026 and will occur over two phases totaling four months, with Phase One focusing on the duct bank and connection from the SDG&E switchboard to the parking lot access driveway, and Phase Two completing the power center installation, pedestal placement, and final system integration. Work will occur Monday through Friday from 7:00 a.m. to 3:30 p.m., and partial promenade closures will be implemented for trenching, with one half closed at a time to maintain public access throughout the project. The project is exempt under CEQA categories 15301, 15303, 15304, and 15311, and the District will ensure compliance with all federal, state, and local regulations related to hazardous materials, demolition debris, stormwater runoff, and environmental protection. No formal contract pricing, evaluation factors, or federal acquisition clauses are included, as this is a pre-solicitation forecast with procurement processes to follow. All work is land-based and limited in scope, with no anticipated significant impact on air quality, greenhouse gas emissions, or traffic.

General Info

San Diego Port to install shore power infrastructure at Fish Harbor and Chesapeake Wharf with new electrical systems, tree replacement, and phased construction beginning Fall 2026.

Agency

California → San Diego Unified Port District

NAICS

238210 - Electrical Contractors and Other Wiring Installation ContractorsView NAICS

Place of Performance

San Diego, CA

Set-Aside

NONE

Documents

(1)

2025-028 Notice of Exemption for FHP and CW Shore Power Installation

PDFnotice-of-exemption

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → San Diego Unified Port District
Contacts2 people available
OfficeN/A
Organization / Agency
California → San Diego Unified Port District
Office AddressN/A
Contacts
Daniel Dela ResmaAssistant Engineer
Davin CoxAssistant Planner

Full Description

Show more
The proposed project would involve the installation of electric shore power infrastructure at Fish Harbor Pier by the San Diego Unified Port District (District) in the city of San Diego, California. Fish Harbor Pier (Pier) has historically supported in-transit commercial fishing vessels and various cargo operations, and continues to do so. With the large quantity of vessels operating through the Pier, it is required that the standard mandating the installation of maintenance and shore power infrastructure, set by the California Air Resources Board (CARB), be met; however, the Pier’s existing electrical infrastructure does not support these mandated shore power requirements. Implementation of the proposed project would equip the Pier with the infrastructure necessary to support these CARB requirements. Work to specifically complete the proposed project would include: • Removal of four (4) multi-trunk paperbark trees • Installation of one (1) 480V-208V power center • Installation of three (3) receptacle pedestals • Retrofitting of existing electrical distribution system Paperbark Tree Removal The proposed project would involve the removal of four (4) multi-trunk paperbark trees (Melaleuca quinquenervia) from the landscaped area adjacent to Fish Harbor Pier where the proposed power center would be installed. To comply with tree replacement requirements, four (4) 24-inch box trees would be planted within proximity of Tuna Harbor. Installation of New 480V-208V Power Center The proposed project would involve the installation of a new 480V-208V power center in the landscaped area adjacent to Fish Harbor Pier and underground electrical feeder circuit to connect the new power center to the existing 480V service entrance switchboard located on the northeastern corner of the Chesapeake Fish Company parking lot. The spare 400A SDG&E meter switchboard section would be repurposed as the connection point for the electrical supply, and the underground power circuit for the 400A meter switchboard would be extended south and west to service the pier and wharf areas. Installation of the underground power circuit would be completed by trenching along the parking lots directly adjacent to the Chesapeake Fish Company leasehold from the existing switchboard to the pier. Installation of Receptacle Pedestals The proposed project would also involve the installation of three (3) receptacle pedestals along the north side of Fish Harbor Pier. Each pedestal would have two (2) receptacles: one (1) 100A/3PH receptacle and one (1) 30A/1PH receptacle. Retrofit of Existing Electrical Distribution System The existing antiquated electrical distribution system currently serving Fish Harbor Pier and Chesapeake Wharf would be removed and replaced with a new shore power electrical distribution system. Electrical wiring from the pier and wharf areas would be integrated into the new shore power electrical distribution system where possible. Additionally, conduits under and along the perimeter of Fish Harbor Pier would have their wiring removed and replaced. There would be no in-water components to the project, installation of any structures into the water below, or addition of fill or overwater coverage. Construction of the proposed project is anticipated to begin in the Fall of 2026, and would be carried out in two (2) phases over the course of approximately four (4) months. Phase 1 would involve the installation of a duct bank from the existing SDG&E switchboard to the Chesapeake Fishing Co. access driveway and associated installations, and would require staging of equipment in the parking lot directly east of the Chesapeake Fishing Co. leasehold. Phase 2 would involve the installation of a duct bank from Chesapeake Fishing Co. to the pier, the installation of the 208V power center, and the installation of shore power infrastructure on the pier, and remaining installations associated with the proposed project. Staging for Phase 2 would be moved from the east lot to the south lot following the completion of Phase 1. Phase 1 would take approximately one (1) month to complete, while Phase 2 would take approximately three (3) months. Work would be conducted Monday through Friday during the work hours of approximately 7:00 a.m. to 3:30 p.m. Construction of the proposed project would require partial closure of the promenade due to necessary trenching to connect the infrastructure installed on the pier to the adjacent power center. Trenching activities would consist of one (1) trench across the promenade from the adjacent parking lot towards Fish Harbor Pier. To minimize impacts on the promenade and maintain public access along the bayfront, construction would close the promenade one half at a time so that the public may walk on one side of the promenade while work would be conducted on the other. This partial closure would ensure public access and allow the public to continue using the promenade throughout the duration of the project. Trenching and construction on the promenade would take approximately one (1) month to finish for each half of the promenade, or approximately two (2) months total. Due to its nature and limited scope, construction of the proposed project would generate a minor amount of vehicle trips and would require limited use of equipment. Therefore, impacts related to air quality, greenhouse gas emissions, and transportation and traffic are not anticipated to occur. Furthermore, the District would be responsible for complying with all applicable federal, state, and local laws regarding construction demolition debris, hazards and hazardous materials, and stormwater.

Similar Contracts

Same NAICS industry code

NAICS: 238210
New
MAIN GROUNDING ELECTRODE
Solicitation # main-grounding-electrode
The Woodland Job Corps Center, operated by Adams and Associates, Inc. for the US Department of Labor, is soliciting a single lump sum contract for a licensed electrical contractor to inspect and repair grounding systems at multiple campus buildings in Laurel, Maryland. The scope of work includes the Aspen Dorm, Vocational Building, Willow Hall, Holly Dorm, Maple Dorm, and Oak Dorm, as well as the Administration Building. Specific technical requirements include installing #2/0 awg conductors from underground copper water pipes, connecting to 16x2 inch ground bars, installing two 8-foot ground rods with 6-foot separation, and routing conductors in 3/4 inch EMT conduit. All work must comply with NEC 2023, 250, EPA and OSHA regulations, and Maryland state codes. Proposals are due by September 3, 2026, and must be submitted on company letterhead to Purchasing Manager Audrey Davis. Bids will be evaluated based on price (60 percent), quality (20 percent), past performance (10 percent), and schedule (10 percent). Required submission documents include a detailed cost breakdown, a valid Maryland contractor's license, insurance certificates, a W9, and a completed vendor questionnaire. The selected contractor must start work within 14 days of the Notice to Proceed and provide a one-year workmanship guarantee. Payment terms are Net 30, and the contract is set aside for various small business categories.
Adams & Associates\ Woodland Job Corps Center

POSTED

about 5 hours ago

DEADLINE

in 19 days
View Details
NAICS: 238210
New
PANELBOARDS
Solicitation # WL – 26 -0004
The Woodland Job Corps Center, operated by Adams and Associates, Inc. for the US Department of Labor, is soliciting a single lump sum contract for electrical panelboard repairs and labeling in Maryland. The scope of work focuses on ensuring compliance with NEC 2023 standards across several campus buildings, including Elm Hall, Birch Hall, the Vocational building, Willow, and Mahogany. Key tasks include providing non-handwritten circuit directories, reinstalling a panel cover in the welcome center mechanical room, and performing specific fire alarm control panel identification at the Oak Dormitory using UL listed red mark labels. The performance period is scheduled from May 11, 2026, through December 31, 2026. This solicitation is set aside for various small business categories and requires bidders to attend a mandatory bid conference to be considered. Proposals are due by September 3, 2026, and must be submitted on company letterhead with a detailed cost breakdown, a timeline for substantial completion, and proof of a valid Maryland Contractor's License. Award decisions will be based on best value, weighing technical quality and experience against price. Contractors must adhere to EPA and OSHA regulations, provide comprehensive general and automobile liability insurance, and comply with Service Contract Labor Standards for wage determinations. Final payment is contingent upon the submission of certified payroll records, a completed SF 1413, and the release of liens from all subcontractors and suppliers.
Adams & Associates\ Woodland Job Corps Center

POSTED

about 5 hours ago

DEADLINE

in 19 days
View Details
NAICS: 238210
New
Electrical Repair Services
Solicitation # Electrical Services 8-2026
The Management and Training Corporation, acting for the U.S. Department of Labor, is soliciting bids for a fixed-price, single lump sum contract to provide various electrical repair services at the Centennial Job Corps Center in Nampa, Idaho. This opportunity is set aside for small businesses, including disadvantaged, women-owned, HUBZone, and veteran-owned entities. Bids must be submitted via email to Sandra Clore by August 31, 2026, at 3:00pm MST. A pre-bid meeting is scheduled for August 21, 2026, at 10am MST. The scope of work includes all electrical services detailed in the Construction Bid Package, requiring the contractor to handle all incidental work, acquire necessary building permits, and provide a one-year written guarantee of workmanship. Bidders must provide a detailed cost breakout on company letterhead covering materials, labor, equipment, and overhead. For bids equal to or exceeding 25,000 dollars, a bid bond of 20 percent is required, and the awarded contractor must provide performance and payment bonds from a surety with at least an A- rating. The contract is subject to Construction Wage Rate Requirements, and the contractor must submit weekly certified payroll. Payment will be made via progress payments using AIA G702 and G703 forms, contingent upon the submission of a Schedule of Values and the acceptance of delivered services. Additionally, the contractor must adhere to strict Department of Labor security and privacy guidelines, including mandatory annual records management training and liability for data breaches. Final closeout requires the submission of two complete operation and maintenance manuals and all applicable manufacturer warranties.
Management & Training Corporation/Centennial Job Corps Center

POSTED

about 5 hours ago

DEADLINE

in 17 days
View Details