Kiefer Landfill Basin Discharge Piping

Active
20260901041State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The County of Sacramento is soliciting bids for the Kiefer Landfill Basin Discharge Piping project in Sloughhouse, California. The primary objective is to replace a deteriorating 6 inch HDPE outlet pipe at the Groundwater Treatment Plant by installing approximately 1,132 feet of new 8 inch HDPE piping. This new system will connect to existing 12 inch PVC piping at South Deer Creek, with most of the installation occurring above ground. The scope of work includes excavation, trenching, backfilling, and the selective demolition of the old piping. Contractors will also be responsible for installing new air relief valves, placing culvert pipes at two road crossing locations to protect the HDPE piping, and repairing the access road following installation. Interested parties must submit their responses by September 24, 2026.

General Info

Sacramento County seeks bids to replace Kiefer Landfill discharge piping by September 24, 2026.

Agency

California → County of SacramentoView Agency

NAICS

237110 - Water and Sewer Line and Related Structures ConstructionView NAICS

Place of Performance

Sloughhouse, CA, 95683, USA

Set-Aside

NONE

Documents

(3)

41019_Special_Provisions_20260824_r1.pdf

PDF

41019_BASIN_DISCHARGE_PIPE.pdf

PDF

Kiefer_Landfill_Basin_Discharge_Piping.pdf

PDF

AI Contract Breakdown

Uniform Contract Format

What is UCF?

Uniform Contract Format (UCF) uses AI to break down any contract into standardized sections—scope, pricing, deliverables, and evaluation criteria.

Timeline

PhaseSolicitation
Posted

Solicitation

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → County of Sacramento
Contacts1 person available
OfficeN/A
Organization / Agency
California → County of Sacramento
View Agency Profile
Office AddressN/A
Contacts

Full Description

Show more
Bid #41019: The project involves replacing a deteriorating 6” HDPE outlet pipe at the Kiefer Landfill Groundwater Treatment Plant. The scope includes installing approximately 1,132 feet of new 8” HDPE piping, connecting it to existing 12” PVC piping at South Deer Creek. A majority of the new piping will be placed above ground. Additional work includes providing new air relief valves, installing new culvert pipes to protect the HDPE piping at two road crossing locations, and repairing the access road after piping installation. The project also involves excavation, trenching, backfilling, selective demolition of existing 6" HDPE piping, and site cleanup.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
JCSD Intervalley Pipeline Project in CA
Solicitation # jcsd-intervalley-pipeline-project-ca
The JCSD Intervalley Pipeline Project in Fontana, California, involves the demolition, furnishing, installation, testing, and operationalization of approximately 3.3 miles of 42-inch cement mortar lined and coated steel potable water transmission pipeline. The scope of work includes the installation of associated appurtenances such as trenchless crossings, air release valves, blowoff assemblies, valves, fittings, and connections to existing water facilities. Additional requirements encompass the construction of flow control facility components, site improvements, pavement removal and restoration, traffic control, utility coordination, and the final disinfection, startup, and commissioning of the system. Managed by Garney Pacific, Inc. for the Jurupa Community Services District, this solicitation seeks subcontractor and supplier quotes by September 18, 2026, at 2:00 PM PT. The project is open to various set-asides, including Small Business, Small Disadvantaged Business, Women-Owned Small Business, HUBZone, DBE, and DVB enterprises. All subcontractors must utilize union labor and be prepared to provide a 100% Payment and Performance Bond from a US Treasury listed Surety Company, with bond premiums reimbursable by Garney. Requested trade scopes include trenchless construction, steel pipe welding, electrical and instrumentation, cathodic protection, and various restoration and hauling services.
Garney Pacific, Inc.

POSTED

about 2 hours ago

DEADLINE

in 16 days
View Details

More opportunities from California → County of Sacramento

Same awarding agency

NAICS: 237310
SLED
Hazel Avenue At US 50 Interchange Improvement Project - Segment 1
Solicitation # 4703
The Hazel Avenue at U.S. 50 Interchange Improvement Project – Segment 1 is a major infrastructure solicitation issued by the County of Sacramento with an estimated construction cost of $28,500,000. Located in Fair Oaks, California, the project scope involves significant roadway and multimodal enhancements, including widening the Hazel Avenue overcrossing of U.S. 50, modifying westbound on-and off-ramps to incorporate a shared-use path, and widening U.S. 50 between Alder Pond and Folsom Boulevard to add an eastbound auxiliary lane. Additional work includes constructing a retaining wall at the eastbound loop on-ramp to improve shoulder width and clear recovery zones, as well as various site improvements such as irrigation, drainage, signage, and erosion control. Prospective bidders must submit electronic proposals via the SacCountyEbids portal no later than September 24, 2026, at 2:00 PM. The contract requires a California Class A General Engineering license and mandates that both the prime contractor and all subcontractors be registered with the California Department of Industrial Relations. Financial security requirements include a bid bond equal to 10% of the bid value, as well as performance and payment bonds totaling 100% of the contract price. Compliance with several regulatory frameworks is mandatory, including the Iran Contracting Act, SB 1383 organic waste reduction reporting, the Advanced Clean Fleets regulation, and Buy America domestic content requirements. Technical oversight is managed by Senior Civil Engineer Spencer Ord, while Jesse Sanchez serves as the Senior Contract Services Officer.
Highway, Street, and Bridge Construction

POSTED

10 days ago

DEADLINE

in 22 days
View Details