LCWA Watermain Lining Project

Forecast
2024050525State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The State Water Resources Control Board is funding the LCWA Watermain Lining Project to rehabilitate approximately 4,000 linear feet of 18-inch diameter watermain using cured-in-place pipe (CIPP) technology, allowing for in-place renewal without full replacement. The project requires the excavation of nine access pits along the watermain route, each measuring about seven feet by twelve feet, with surrounding work areas spanning roughly 20 feet by 50 feet per site. Following installation, all pits will be backfilled, hydroseeded, and restored to match pre-construction ground contours as closely as possible to minimize long-term environmental and aesthetic impact. The project is located in Seal Beach, California, and is identified internally under Project Number 3010041-001C. The project was posted as a forecast on May 28, 2026, and is managed by the California State Water Board’s Division of Financial Assistance. Primary points of contact include Abbygayle Guevara, Environmental Scientist at the State Water Board, and Iris Lee, Public Works Director for the City of Seal Beach. While no solicitation number or NAICS code has been assigned, the project remains under the oversight of state environmental and public works authorities to ensure compliance with water infrastructure standards and local restoration requirements. The work aims to enhance water system integrity while reducing disruption through minimally invasive rehabilitation techniques.

General Info

State funds CIPP watermain rehab in Seal Beach, 4,000 ft, nine access pits, restoration required.

Agency

California → SWRCB, Division of Financial Assistance

Place of Performance

Seal Beach, CA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseForecast
Posted

forecast

Prepare for this forecast

Research the agency, track this forecast, and prepare your capture plan before the solicitation opens.

Organization & Contact Information

Show more
AgencyCalifornia → SWRCB, Division of Financial Assistance
Contacts2 people available
OfficeN/A
Organization / Agency
California → SWRCB, Division of Financial Assistance
Office AddressN/A
Contacts
Abbygayle GuevaraEnvironmental Scientist
Iris LeePublic Works Director

Full Description

Show more
The State Water Resources Control Board (State Water Board) is funding the Project referred to internally as LCWA Watermain Lining Project. The Project includes the rehabilitation of approximately 4,000 linear feet (ft.) of 18-inch diameter watermain. The watermain will be rehabilitated in place by using cured in-place pipe (CIPP) liner methods. Installation of the CIPP lining will require the excavation of pits to access the existing 18-inch watermain. Nine pit locations have been identified along the existing watermain throughout the Project site. The dimensions of each access pit will be approximately seven ft. by 12 ft. The work area at each pit site is anticipated to be approximately 20 ft. by 50 ft. Access pits will be backfilled at the end of Project's completion, hydroseeded, and restored to as near pre-construction contours as possible. PROJECT NUMBER: 3010041-001C

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
IEUA Regional Water Recycling Plant No. 5(RP5) Offsite Facilities and Butterfield Lift Station
Solicitation # ieua-regional-water-recycling-plant-no-5rp5-offsite-facilities-butterfield-lift-station
The IEUA Regional Water Recycling Plant No. 5 Offsite Facilities and Butterfield Lift Station project, managed by Norstar Plumbing and Engineering, Inc. for the Inland Empire Utilities Agency, involves the comprehensive installation, commissioning, and delivery of critical water and sewer infrastructure in Chino, California. The scope of work is centered on four major components: the Butterfield Dual Force Main, the Mountain Avenue Lift Station, the RP-2 Lift Station, and the Butterfield Lift Station. To achieve a fully functional system, the project requires a wide array of materials and services, including AC paving, trucking, jack and bore operations, cold planing, piping and fittings, traffic control, demolition, and preconstruction video services. This solicitation is specifically targeted toward SBA certified HUBZone Small Businesses and Disadvantaged Business Enterprises, with a strong emphasis on partnering with certified DBE, MBE, SBE, WBE, SBRA, and LSAF firms. Interested parties must submit their responses by the deadline of November 19, 2026, at 2:00 PM. Primary points of contact for this effort are Destiny Plummer and Nathan Plummer of Norstar Plumbing and Engineering, Inc. All work must be performed in strict accordance with the project bid documents and specifications provided via the Inland Empire Utilities Agency bidding website.
Norstar Plumbing and Engineering, Inc

POSTED

about 2 hours ago

DEADLINE

in 7 days
View Details

Prepare for this forecast

Research this forecast and prepare for the solicitation

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS