Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, September 2 at 2:00 PM EDT

Register Free →

McCullough-Victorville Lines 1 and 2 Upgrade Project

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The McCullough-Victorville Transmission Lines 1 and 2 Upgrade Project is a major infrastructure initiative by the Los Angeles Department of Water and Power to completely replace 1,750 existing transmission towers along a 160-mile corridor stretching from the McCullough Switching Station in Nevada to the Victorville Switching Station in California. Originally approved for upgrading the 500kV lines to 570kV with partial structural enhancements, new engineering evaluations have determined that full tower replacement is necessary to ensure long-term reliability and resilience of the grid. The project includes shifting the alignment of Line 1 by approximately 110 feet southeast over 95 miles, installing new foundations positioned 50 to 300 feet from existing tower sites, replacing insulators, hardware, conductors, and ground wires, re-tensioning lines, and upgrading access roads while establishing new spur routes. Construction is scheduled to begin in mid-2027 and extend through 2029, with work carried out in temporary areas adjacent to each tower location using existing right-of-way access routes. This upgrade is critical to integrating increasing volumes of renewable energy from west of the Colorado River along the Path 46 transmission corridor, directly supporting LADWP’s commitment to achieve 100 percent carbon-free energy by 2035—decade ahead of California’s state mandate. The additional 475 megawatts of capacity will contribute more than 15 percent toward meeting the Renewable Portfolio Standard. Strict environmental, safety, and emissions standards govern all aspects of construction, requiring OSHA compliance, daily safety briefings, personal protective equipment, fire prevention plans, and traffic control signage. Contractors must implement a comprehensive environmental education program for all personnel, maintain training logs, protect wildlife including special-status species, and report any incidents involving animals. Diesel and gasoline equipment must be replaced with electric or compressed natural gas alternatives where feasible, all internal combustion engines over 50 horsepower must meet U.S. EPA Tier 4 Final standards, and MDAQMD permits must be secured for non-exempt equipment. GHG emissions reductions are mandatory in all subcontracts, and immediate notification to LADWP is required for certain activities to allow for project halt if warranted. The project’s environmental compliance framework is supported by detailed location data in Attachment A and regulatory guidance from state and federal appendices.

General Info

Replace 1,750 towers on 160-mile corridor to boost grid resilience and renewable energy capacity by 475 MW by 2029.

Agency

California Los Angeles Department of Water and Power

NAICS

237130 - Power and Communication Line and Related Structures ConstructionView NAICS

Place of Performance

US Route 66, Quarry Rd., Sorrell Trail, Stoddard Valley Rd., Barstow Rd., I-15 and State Line, CA, See Att: A

Set-Aside

NONE

Documents

(6)

MCC-VIC SEIR Appendices_combined

PDF

MCC-VIC Lines 1 and 2 Draft Subsequent Environmental Impact Report NOA

PDFnotice-of-availability

SCH Summary Form for McCullough-Victorville Lines 1 and 2 Upgrade Project

PDFenvironmental-summary

MCC-VIC Attachment A Location Details APN List

PDFattachment

NOC McCullough-Victorville Lines 1 and 2 Upgrade Project SEIR Final

PDFnotice-of-completion

Draft Subsequent Environmental Impact Report for McCullough-Victorville Transmission Lines Upgrade Project

PDFenvironmental-impact-report

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia Los Angeles Department of Water and Power
Contacts2 people available
OfficeN/A
Organization / Agency
California Los Angeles Department of Water and Power
Office AddressN/A
Contacts
Matthew KerbyEnvironmental Specialist
Michele FinneyfrockProject Manager

Interested Companies (1)

Show more
Dudek
Encinitas, CA

Full Description

Show more
LADWP had previously prepared an Environmental Impact Report (EIR) for the McCullough-Victorville (MCC-VIC) Transmission Lines 1 and 2 Upgrade Project (State Clearinghouse No. 2024040144). MCC-VIC Transmission Lines 1 and 2 are two existing 500 kilovolt (kV) electrical power lines which run parallel to each other and are supported on approximately 1,750 single-circuit towers and spanning over 160 miles from McCullough Switching Station in Nevada, through several mountain ranges, into the Mojave Desert and ending at the Victorville Switching Station in California. The previously-approved Project would upgrade the MCC-VIC Lines 1 and 2 circuits to newly rate them as 570kV from their current rating of 500kV, including significant upgrades of existing transmission tower steel members and foundation repairs as needed. Since the certification of the MCC-VIC EIR, project design and evaluation of the condition of the existing transmission towers have determined that complete replacement of transmission towers is necessary to ensure long term reliability of power transmission through the lines. Implementation of the Proposed Project would ensure reliable and continued operation of the transmission lines for decades. The modification of the existing MCC-VIC Transmission Lines would provide critical transmission capacity and is required to accommodate incoming renewable energy resources along the west of Colorado River Path 46 transmission corridor to ensure the continued safe and reliable operation of the lines. Both the Proposed Project and previously-approved project support LADWP’s goal to transition to a clean energy future, with ongoing efforts to transition from coal to renewable energy, influenced by Los Angeles City Council’s vote in 2021 to commit to 100 percent carbon-free energy. The additional 475 megawatts would contribute over 15 percent towards LADWP’s Renewable Portfolio Standard as part of LADWP’s commitment to be 100 percent carbon-free by 2035, 10 years ahead of the State’s target. The Proposed Project would require complete replacement of 1,750 existing transmission towers. The existing MCC-VIC Line 1 alignment will shift approximately 110 feet southeast for approximately 95 miles from the City of Victorville to the City of Baker. The Proposed Project would consist of installation of new foundations, replacement of existing insulators and hardware assemblies, replacing conductors, ground wire, and re-tensioning conductors, repairing/retrofitting existing main access roads and establishment of new spur roads. Construction of the Proposed Project would require establishing a temporary work area at each transmission structure and pulling and tensioning sites along the entire length of the transmission lines. New foundations and tower footprints will be shifted 50 to 300 feet from existing tower sites along the existing centerlines. Access to the project site is available from various existing access routes along the MCC-VIC transmission line corridor. Construction of the Proposed Project is anticipated to begin in mid-2027 and continue through 2029.

Similar Contracts

Same NAICS industry code

NAICS: 237130
New
Keystone Power Outage Repairs
Solicitation # keystone-power-outage-repairs
The Keystone Power Outage Repairs solicitation, issued by Adams and Associates Keystone Red Rock Job Corps, seeks a contractor to perform electrical infrastructure repairs at the Keystone Red Rock Job Corps Center in Drums, Pennsylvania. The scope of work involves repairing three poles damaged during a power outage, specifically poles 35, 43, and 45. Technical requirements include the installation of one 75 kva transformer on pole 35, one 100 kva transformer on pole 43, and a bank replacement on pole 45 consisting of one 100 kva and two 50 kva transformers. Additionally, the contractor must install new polymer cutouts and 10kv lightning arresters on poles 35 and 43, establish new service drops to buildings from all three poles, install a new secondary quadplex for the main trunk line, and handle the demolition and disposal of old secondary cables. Final deliverables include the verification of voltage and proper rotation within the buildings. This opportunity is set aside for various small business categories, including Small Disadvantaged, Women-Owned, HUBZone, and Veteran-Owned small businesses. Bidders must be registered and active in SAM.gov and are required to separate labor and materials on their bids. The contract is subject to Davis-Bacon wage standards, and the successful contractor must provide certified payroll. The solicitation was posted on August 30, 2026, with a response deadline of September 9, 2026. The primary point of contact for this effort is Jennie Drumheller.
Adams & Associates Keystone Red Rock Job Corps

POSTED

about 10 hours ago

DEADLINE

in 9 days
View Details
NAICS: 237130
New
Federal
SP-364 Replace Underground Cabling in SP Area
Solicitation # N4008526R0249
Solicitation N4008526R0249 is an 8(a) set-aside Indefinite Delivery/Indefinite Quantity contract issued by the Naval Facilities Engineering Systems Command Mid-Atlantic. The project, titled SP-364 Replace Underground Cabling in SP Area, involves replacing underground electrical cabling from SW 111 at SP-35 to manholes serving buildings SP-254, 257, 362, 364, and 366, as well as installing above-ground junction boxes near SP-254 and 257. Performance will take place at Naval Station Norfolk, Virginia, with a total completion period of 330 calendar days from the date of the task order award. Award will be granted to the eligible offeror submitting the lowest price based on the total sum of Contract Line Item 0001AA and the extensions of items 0001AB through 0001AE. The contractor must provide a project superintendent with at least 10 years of construction experience, including 5 years on projects of similar complexity, and a site-based Quality Control Manager. Key requirements include adherence to USACE EM 385-1-1 safety standards, the submission of a Government-approved Salvage Plan, and compliance with NETA ATS and various ASTM standards for electrical and materials testing. Invoicing is managed via Wide Area Work Flow (WAWF) using specific NAVFAC forms, and payments are governed by FAR 52.232-5 and FAR 52.232-27. Proposals must be submitted electronically through the PIEE Solicitation Module by September 7, 2026, at 1400 EDT.
Navfacsyscom Mid-Atlantic

POSTED

2 days ago

DEADLINE

in 4 days
View Details
NAICS: 237130
New
Federal
Feeder 7 Repair
Solicitation # W50S8526BA007
The U.S. Air Force, through the W7NF Uspfo Activity Miang 127, is preparing to issue an Invitation for Bids under solicitation number W50S85-26-B-A007 for the construction of Electrical Repair Feeder 7 at Selfridge Air National Guard Base in Michigan. This is a firm fixed-price contract entirely set aside for small businesses under FAR 19.5, with the NAICS code 237130 for Power and Communication Line and Related Structures, and a size standard of $45 million. The project requires the contractor to furnish all plant, labor, transportation, materials, tools, equipment, appliances, and supervision necessary to complete approximately 5,706 feet of new underground and overhead conductors, demolition of existing cables, full-depth pavement repairs, mill/overlay, crack repairs, and associated site restoration work along Perimeter Road and Jefferson Ave. All work must strictly adhere to Drawings VGLZ262005 Repair Feeder #7, the Statement of Work, and project specifications, with any conflicts resolved in favor of the more stringent or higher-quality requirement. A Macomb County Soil Erosion Permit is mandatory and the responsibility of the contractor to obtain and pay for. The contract period is 240 calendar days from notice to proceed, inclusive of inspection and punch list items. The solicitation is being issued under FAR Part 14 procedures, with award determined solely on price and price-related factors. The prime contractor must comply with limitations on subcontracting, prohibiting payments exceeding 85 percent of the contract value (excluding materials) to non-similarly situated subcontractors under FAR clause 52.219-14(e)(3) with deviation 2021-O0008. All bidders must be registered in SAM.gov, and inquiries must be submitted in writing via email to TSgt Jack Garrettson. The formal solicitation is tentatively scheduled for release on July 13, 2026, with a pre-bid conference on July 22, 2026, and bid opening anticipated on or about August 31, 2026. The estimated contract value ranges between $1 million and $5 million, with the final amount to be determined upon bid submission.
W7NF Uspfo Activity Miang 127

POSTED

2 days ago

DEADLINE

in 10 days
View Details