PLER2025-00142 Aquifer Storage and Recovery Project Vineyard Surface Water Treatment Plant

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The Sacramento County Water Agency is implementing the Aquifer Storage and Recovery Project at the Vineyard Surface Water Treatment Plant under solicitation PLER2025-00142. The primary scope of work involves converting the inactive supply well PW-1 into an ASR well, which includes the installation of a permanent 100-horsepower pump, electrical controls, and 12-inch piping and valves to connect to the existing potable water system. The project also encompasses the future construction of four additional ASR wells and the conversion of three active Excelsior supply wells. The conversion process requires removing existing pumps, conducting pre- and post-rehabilitation downhole video surveys, cleaning well screens and filter packs to remove sediment and biomatter, and reinstalling pumps with ASR valves. Additionally, existing above-ground pipelines will be reconfigured to include a backflushing loop. The project is subject to a Mitigated Negative Declaration, concluding that the work will not have a significant environmental effect, provided that specific mitigation measures are followed. Key compliance requirements include adherence to the California Environmental Quality Act, EPA and CARB air quality standards, and Sacramento Metropolitan Air Quality Management District emission control practices. Strict protocols are in place for the discovery of unanticipated human remains, requiring immediate work stoppage and notification of the County Coroner. Performance schedules indicate a phased approach, with initial pump and piping installations occurring in July and August 2026, and subsequent new ASR well installations and testing extending through October 2027.

General Info

Sacramento County Water Agency converting wells for Aquifer Storage and Recovery project through 2027.

Agency

California → Sacramento County

NAICS

237110 - Water and Sewer Line and Related Structures ConstructionView NAICS

Place of Performance

Florin Road, Knox Road, Excelsior Road, CA, 95641

Set-Aside

NONE

Documents

(4)

PLER2025-00142 Notice of Intent - Aquifer Storage and Recovery Project

PDFpresolicitation

PLER2025-00142 - Aquifer Storage and Recovery Project MND

PDFother

PLER2025-00142 Aquifer Storage and Recovery Project Vineyard Surface Water Treatment Plant Summary Form

PDFother

PLER2025-00142 - Aquifer Storage and Recovery Project Vineyard Surface Water Treatment Plant

PDFother

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Sacramento County
Contacts3 people available
OfficeN/A
Organization / Agency
California → Sacramento County
Office AddressN/A
Contacts
Matt SatowDirector of Water Resources
Julie NewtonEnvironmental Coordinator
Rodney FrickeSenior Hydrogeologist

Interested Companies (1)

Show more
GEI Consultants
Rancho Cordova, CA

Full Description

Show more
Sacramento County Water Agency (SCWA) proposes to convert an inactive supply well (PW-1) at the Vineyard Surface Water Treatment Plant into an Aquifer Storage and Recovery (ASR) well and construct associated conveyance pipelines. The work includes installing a permanent 100-horsepower pump, electrical controls, and 12-inch piping and valves connecting to the existing potable water system. SCWA also plans four future ASR wells, associated pipelines, and the conversion of three active Excelsior supply wells to ASR. ASR implementation would involve removing the existing pump, performing pre- and post-rehabilitation downhole video surveys, cleaning the well screen and filter pack to remove scaling, biomatter, and sediment, and reinstalling the pump with an ASR valve. The existing above-ground pipeline would be reconfigured to include a backflushing loop.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
Biola CSD - Wastewater Treatment Plant Improvements (C-06-8155-210), Kerman, CA
Solicitation # biola-csd-wastewater-treatment-plant-improvements-c-06-8155-210-kerman-ca
GSE Construction Co., Inc. is seeking quotes from qualified subcontractors and suppliers for the Biola Community Services District Wastewater Treatment Plant Improvements (Redesign) Project in Kerman, California. This comprehensive project involves the demolition of existing infrastructure and the draining of multiple lagoons and ponds. Key construction elements include a new headworks facility with mechanical screening and compaction units, a new influent eccentric manhole, a flow meter vault, and the replacement of influent pumps and surface aerators. Additionally, the scope includes a new sludge dewatering pipeline, soil cement lined dewatering ponds, an emergency generator pad, and a new CMU operations and electrical building equipped with HVAC and plumbing. The project also requires the implementation of a facility-wide PLC/SCADA monitoring system and various civil improvements such as asphalt resurfacing, grading, and piping installation. This solicitation is open to small businesses and certified disadvantaged, minority, and women-owned business enterprises across a wide range of NAICS codes related to heavy and civil engineering construction. Interested parties must submit their responses by October 21, 2026, and can direct inquiries to Christina Pauls at GSE Construction Co., Inc.
GSE Construction Co., Inc.

POSTED

about 7 hours ago

DEADLINE

in about 1 month
View Details
NAICS: 237110
New
Seeking MBE/DBE/WBE Subcontractors and Suppliers for South Marsham Street Green Infrastructure Project (Romney, WV)
Solicitation # seeking-mbedbewbe-subcontractors-suppliers-south-marsham-street-green-infrastructure-project-romney
Harbel, Inc. is soliciting bids for a green-street retrofit project located on South Marsham Street between Gravel Lane and US Route 50 in Downtown Romney, West Virginia. The scope of work involves the targeted retrofit of approximately 343.59 linear feet of roadway to implement green infrastructure. Key deliverables include the installation of approximately 1,450 square feet of permeable pavement, eight vegetated stormwater management cells, and the planting of six native trees and approximately 345 native plants or approved equivalents. The project is designed to treat approximately 1.7 acres of impervious surface within a 3.3-acre drainage area and requires necessary drainage, underdrain, inlet, pipe, and downspout work, as well as ADA-compliant curb, sidewalk, apron, crossing, and traffic-calming improvements. This solicitation specifically seeks MBE, DBE, and WBE subcontractors and suppliers, with a strong emphasis on small business concerns, including veteran-owned, service-disabled veteran-owned, HUBZone, disadvantaged, woman-owned, and minority-owned businesses. To accommodate the project scale, small businesses are encouraged to form consortiums. Bids must be submitted by September 17, 2026, at 4:00 P.M. Primary points of contact for this opportunity are Jennifer Wilson and Jonah Leith. The project concludes with final stabilization, cleanup, and restoration of the site.
Harbel, Inc.

POSTED

about 7 hours ago

DEADLINE

in about 13 hours
View Details
NAICS: 237110
New
Inland Feeder/SBVMWD Foothill PS Intertie, Stage 1
Solicitation # inland-feedersbvmwd-foothill-ps-intertie-stage-1
The Inland Feeder/SBVMWD Foothill PS Intertie, Stage 1 project, located in Highland, California, involves extensive infrastructure installation for the Metropolitan Water District of Southern California. The scope of work includes furnishing and installing approximately 2,150 linear feet of 54-inch to 66-inch diameter steel pipe and 200 linear feet of 144-inch diameter steel pipe. The project also requires the installation of various contractor-furnished and Metropolitan-furnished valves, 54-inch and 145.5-inch diameter tie-ins, four surge tanks, two valve vaults, and an air compressor yard structure. Additional requirements include drainage improvements, electrical upgrades, instrumentation and controls, piping systems, the excavation of cobbles and large boulders, welding, disinfection, and surface restoration. This solicitation, issued by James W. Fowler Co., is open to small businesses, including SBA-certified service-disabled veteran-owned small businesses, minority business enterprises, and women business enterprises. Bids are due by September 29, 2026. The project emphasizes the inclusion of M/W/DBE subcontractors, with James W. Fowler Co. offering assistance in obtaining bonding, insurance, and necessary equipment. Quality control testing is a required component of the subcontract pricing, and the utilization of apprentices is encouraged. All negotiations must be finalized 24 hours prior to the bid opening.
James W. Fowler Co.

POSTED

about 7 hours ago

DEADLINE

in 13 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement