Secondary Control Building Basin Drain Pump Replacements at South Shore Water Reclamation Facility
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The project involves the complete replacement of two centrifugal basin drain pumps, identified as basin drain pump 1 and basin drain pump 3, along with their associated equipment at the South Shore Water Reclamation Facility's Secondary Control Buildings 5 and 6 in Wisconsin. The scope includes removing and disposing of the existing pumps, motors, baseplates, and related valves such as 12-inch knife gate valves, air release valves, and a check valve on basin drain pump 3. The contractor will then furnish and install new equipment, including reinforced concrete pads, pump baseplates with epoxy coating, new basin drain pumps with flexible couplings, electrical motors, and all necessary valves. The work also encompasses connecting, aligning, and balancing the new pumps and motors, followed by a comprehensive 7-day test run to ensure proper operation. All tasks must adhere to the specifications provided, with the contractor responsible for completing any additional work required to finalize the project. The contract, issued by the Milwaukee Metropolitan Sewerage District, has a project value estimated between $200,000 and $500,000. It was posted on May 29, 2025, with a response deadline of June 26, 2025. The project emphasizes thorough equipment replacement and testing to ensure reliable operation of the basin drain pumps within the water reclamation facility, with primary contact for inquiries being Millie Neidhardt. Interested parties can access further details through the provided online link.
General Info
Place of Performance
WI, USASet-Aside
Documents
0AI Contract Breakdown
Uniform Contract FormatNo documents to break down
The breakdown needs solicitation documents. None were found from this contract's source.
This one is closed. Find the next one like it.
Open contracts like this one, right now:
- 26350 Lynchburg, VA - CSO 70 Sewer ImprovementsOpen now, due in 17 days
- Lift Station No. 85 ReplacementOpen now, due in 28 days
Ask CLEATUS
I've read this contract. Ask me anything.
Timeline
Submission Closed
Organization & Contact Information
Full Description
- Remove and dispose of basin drain pump 1 (located in Building 331) and basin drain pump 3 (located in Building 332). - Remove and dispose of the pump motors and baseplates. - Remove and dispose of the 12-inch knife gate valves in the suction side of each pump. - Remove and dispose of the air release valves on the discharge side of each pump. - Remove and dispose of the 12-inch check valve located on the discharge side of basin drain pump 3. - Remove the basin drain pump reinforced concrete equipment pads. - Furnish and install new 12-inch knife gates valves on the suction side of each pump. - Furnish and install new air release valves on the discharge side of each pump. - Furnish and install a new 12-inch check valve on the discharge side of basin drain pump 3. - Form and place new reinforced concrete equipment pads in the location of basin drain pumps 1 and 3. - Furnish and install two new pump baseplates. Epoxy coat the new baseplates prior to installing the new pump equipment. - Furnish and install two new basin drain pumps, flexible couplings, and electrical motors on the new baseplates. - Connect, align, and balance the new motors and pumps. - Complete 7-day test run for each of the new pumps and valves. - Complete all other work described in the Specifications and as necessary to complete the project.
More opportunities from Wisconsin → Milwaukee Metropolitan Sewerage District
Same awarding agency
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS