Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, October 28 at 2:00 PM ET

Register Free →

This Solicitation opportunity from Georgia was posted on April 10, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

SEWERAGE SYSTEM IMPROVEMENTS-FY2024 CDGB

Closed
PE-66419-NONST-2026-000000013State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project, solicitation number SRP-W-134-0290, is a construction contract for the City of Belmont, North Carolina, with a project estimate of $16,690,000. The scope of work involves the construction of 16,435 linear feet of new 20-inch ductile iron force main and comprehensive upgrades to the Morgans Branch Pumping Station. Key deliverables include the installation of a new wet well, valve vault, and associated appurtenances, as well as the demolition of existing pumps and piping. The project also encompasses the installation of new gravity sewers, manholes, and a fully operational pumping station equipped with mechanical and electrical systems, a generator, odor control equipment, and stormwater facilities. The contract will be awarded to the responsible bidder submitting the lowest responsive bid, with a substantial completion timeline of 560 calendar days. Bidders must provide a bid bond using form EJCDC C-430 and submit required MWBE documentation, including a Good Faith Efforts Form and Table A. The project is administered by Willis Engineers, who serve as the Owner's Representative. Payment is processed via Applications for Payment, with payments becoming due 30 days after presentation to the owner. Technical standards for the work include compliance with AWS D1.2 for welding, NEMA standards for motors, and ASTM C 1093 for masonry testing.
Don Moorhead Construction, Inc.

POSTED

about 2 hours ago

DEADLINE

in 13 days
NAICS: 237110
New
Main Wastewater Treatment Plant Secondary Reactors Rehabilitation Phase 2 in CA
Solicitation # main-wastewater-treatment-plant-secondary-reactors-rehabilitation-phase-2-ca
Garney Pacific, Inc. is seeking quotes from qualified subcontractors for the Main Wastewater Treatment Plant Secondary Reactors Rehabilitation Phase 2 project located in Oakland, California, for the East Bay Municipal Utility District. This solicitation is open to small businesses, including certified Veteran Owned, Service-Disabled Veteran Owned, Women-Owned, and HUBZone small businesses. The comprehensive scope of work involves the rehabilitation of covered and open concrete structures, the relining or replacement of steel and ductile iron pipes and supports, and the installation of valves and piping appurtenances. Additional requirements include the operation of a temporary 11 MGD pumped bypass, rehabilitation of reactor mixers and aerators, upgrades to motor control center components, and the installation of new instrumentation, electrical systems, and slide gates. Key deliverables for the project include lead abatement, metals fabrication, painting and coatings, concrete resurfacing, and the installation of FRP reinforcing systems and access hatches. All subcontractors are required to utilize union labor and must be prepared to provide a 100 percent Payment and Performance Bond from a US Treasury listed Surety Company, with bond premiums reimbursed by Garney Pacific. Interested parties must submit their quotes, including their bond rate and any redlines to standard subcontract forms, by November 17, 2026, at 2:00 PM PT.
Garney Pacific, Inc.

POSTED

about 2 hours ago

DEADLINE

in 21 days
NAICS: 237110
New
IEUA RP-5 Offsite Facilities Project No. EN19001.03 and Butterfield Lift Station Improvements Project No. EN26054
Solicitation # EN19001.03 / EN26054
Filanc is soliciting quotes for the IEUA RP-5 Offsite Facilities Project No. EN19001.03 and the Butterfield Lift Station Improvements Project No. EN26054 located in Chino and Chino Hills, California. The comprehensive scope of work involves significant wastewater infrastructure improvements, including the installation of approximately 6,200 linear feet of dual 14 to 16-inch diameter HDPE DR 11 pipelines from El Prado Road to Kimball Avenue. Additionally, the project requires the construction of a new Mountain Avenue Lift Station featuring a concrete wet well and submersible pumps, modifications to the RP-2 Lift Station to include an elevated electrical platform and standby generator, and the replacement of the motor control center, pumps, and motors at the Butterfield Lift Station while maintaining continuous operation. Filanc is seeking quotes across a wide array of trades, including SWPPP, survey, aggregates, demolition, fencing, paving, striping, precast concrete, rebar, masonry, metals, coatings, signage, process equipment, pre-engineered FRP enclosures, fire suppression, piping, valves, pipe supports, and electrical and instrumentation and control. This solicitation is open to small businesses, including SDB, WOSB, HUBZone, and VOSB certifications, with a strong emphasis on DBE participation. Bids are due by 2:00 PM on October 29, 2025. The primary point of contact for this opportunity is Julia Masaitis.
Filanc

POSTED

about 2 hours ago

DEADLINE

in about 16 hours

AI Contract Overview

Show more

The contract involves comprehensive sewerage system improvements within Georgia, focusing on both traditional excavation and trenchless rehabilitation methods. Key tasks include replacing 238 linear feet of an existing 8-inch sewer line through digging, and trenchless pipe replacement for 1,153 linear feet of 8-inch and 4,411 linear feet of 10-inch sanitary sewer lines. The scope also encompasses cleaning, pre- and post-rehabilitation video inspections, and restoring 22 existing manholes. Additional work includes replacing 47 linear feet of concrete sidewalk, 54 square yards of asphalt, and 10 linear feet of curb and gutter. The project requires by-pass pumping and includes all necessary appurtenances to complete the system upgrades. Issued by the City of Soperton, Georgia, this solicitation is part of the Sewerage System Improvements for FY2024 under solicitation number PE-66419-NONST-2026-000000013. The contract was posted on April 10, 2026, with responses due by May 14, 2026. The project is managed through a local government entity with a primary contact available for inquiries. This contract targets improving sanitary sewer infrastructure durability and functionality, aiming to enhance service reliability and system performance within the designated service area.

General Info

Sewer system upgrade in Soperton, GA: pipe replacements, inspections, manhole restoration, sidewalk and asphalt repairs.

Documents

1

Advertisement for Bids - Sewerage System Improvements, City of Soperton, GA

PDF, High priority: read this firstifb
High

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseClosed
Posted

Solicitation

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Start your free trial to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyGeorgia → City of Soperton
Contacts1 person available
OfficeN/A
Organization / AgencyGeorgia → City of Soperton
Office AddressN/A

Full Description

Show more
Sewerage system rehabilitation including 238 L.F. of 8-inch dig and replace existing sewer line, rehabilitation of and 1,153 L.F. of 8-inch and 4,411 L.F. of 10-inch sanitary sewer sanitary sewer using trenchless pipe replacement, including cleaning, pre and post video, rehabilitating 22 existing manholes, 47 L.F. replace concrete sidewalk, 54 S.Y. asphalt replacement, 10 L.F. remove and replace existing curb and gutter, by-pass pumping, and appurtenances.

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS