The SR 49 Emergency Sewer Replacement Project, managed by the City of Angels Camp in California, involves the removal of approximately 390 linear feet of degraded 6-inch unreinforced concrete pipe. The existing pipeline has suffered structural failure, including holes in the sidewalls and flow line that have allowed backfill materials to obstruct flow. This failing infrastructure will be replaced with new 6-inch PVC pipe, maintaining the original lines, grades, and horizontal alignment. To ensure continuous service during construction, a sewer bypass system will be operated, and traffic control measures will be implemented to protect the work zone and manage vehicle circulation. Following the installation of the new pipeline, all affected hardscape, asphalt, and minor concrete will be replaced in kind. The project is classified as a forecast and is subject to a statutory exemption under Public Resources Code Section 20180.21, as the pipeline replacement is less than one mile in length. Administrative oversight is provided by the City Planner and City Engineer, with the project located in Angels Camp, California.

General Info

City of Angels Camp replacing 390 feet of failed sewer pipe with PVC.

Agency

California → City of Angels Camp

Place of Performance

Stockton Road and SR 49, Angels Camp, CA, 95222

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → City of Angels Camp
Contacts2 people available
OfficeN/A
Organization / Agency
California → City of Angels Camp
Office AddressN/A
Contacts
Amy AugustineCity Planner
Angels Camp Contractor (to be determinedAaron Brusatori, City Engineer

Full Description

Show more
Remove 6” diameter unreinforced concrete pipe which has degraded and includes holes in the sidewalls and flow line allowing backfill materials to enter the pipe and obstruct flows. Replace with 390± linear feet of new 6” PVC pipe in the same lines and grades in the same horizontal alignment as the failing pipeline. All hardscape, asphalt and minor concrete will be replaced in kind. A sewer bypass system will be operated during removal and replacement of the sewer line. Traffic control will be in place to protect the work zone and facilitate orderly circulation during construction.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project, solicitation number SRP-W-134-0290, involves the construction of 16,435 linear feet of new 20-inch ductile iron force main and extensive upgrades to the existing Morgans Branch Pumping Station in Belmont, North Carolina. The scope of work includes the installation of a new wet well, valve vault, and associated appurtenances, as well as the demolition of existing pumps and piping. Key deliverables include the installation of mechanical and electrical systems, such as pumps, a generator, and odor control equipment, along with new gravity sewers and manholes. The project has an estimated value of 16,690,000 dollars and utilizes EJCDC standard forms for its contracting requirements. The contract will be awarded to the responsible bidder submitting the lowest responsive bid, with evaluation based on qualifications, financial ability, and strict adherence to bidding documents. Bidders must provide a bid bond, evidence of authority to do business in North Carolina, and documentation of good faith efforts to meet MBE and WBE participation goals, which are set at 10 percent combined for the state and approximately 10.9 percent for MBE and 10.4 percent for WBE per EPA goals. Performance and payment bonds, as well as proof of insurance, are required. Project administration is managed by the City of Belmont with Willis Engineers serving as the project engineer. Payment is processed via Applications for Payment, with payments becoming due 30 days after presentation to the owner.
Don Moorhead Construction, Inc.

POSTED

about 2 hours ago

DEADLINE

in 14 days
View Details
NAICS: 237110
New
Main Wastewater Treatment Plant Secondary Reactors Rehabilitation Phase 2 in CA
Solicitation # main-wastewater-treatment-plant-secondary-reactors-rehabilitation-phase-2-ca
Garney Pacific, Inc. is seeking quotes from qualified subcontractors for the Main Wastewater Treatment Plant Secondary Reactors Rehabilitation Phase 2 project located in Oakland, California, for the East Bay Municipal Utility District. The comprehensive scope of work involves the rehabilitation of covered and open concrete structures, including resurfacing, restoration, and the installation of FRP reinforcing systems and access hatches. Technical requirements include the relining, modification, or replacement of steel and ductile iron pipes, installation of valves and piping appurtenances, and the operation of a temporary 11 MGD pumped bypass. Additional tasks encompass electrical and instrumentation upgrades, rehabilitation of reactor mixers and aerators, motor control center component replacement, sluice and slide gate modifications, and general excavation and surveying. This solicitation is open to small businesses, including certified VOSB, SDVOSB, WOSB, and HUBZone entities, with a specific emphasis on DBE, MBE, WBE, and SBE subcontractors. All subcontractors are required to utilize union labor and must be prepared to provide a 100 percent Payment and Performance Bond from a US Treasury listed Surety Company, with bond rates submitted at the time of bid for reimbursement. Quotes for services and supplies, including lead abatement, metals fabrication, and trucking, are due by November 17, 2026, with the final bid date set for November 18, 2026. Any exceptions to standard subcontract forms must be submitted as redlines alongside the quote.
Garney Pacific, Inc.

POSTED

about 2 hours ago

DEADLINE

in 22 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS