Z -- Repair Airfield Taxiways and Overruns

Active
FA4897-04-R-0004Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The contract involves repair and rehabilitation work on airfield taxiways and overruns at Mountain Home Air Force Base, focusing on multiple pavement repair techniques including asphalt mill and overlay, full-depth concrete replacement, and slab jacking, along with limited electrical work for new edge lighting installation. The project scope covers approximately 520,000 square feet of asphalt overlay, 150,000 square feet of concrete replacement, and 16,250 square feet of slab jacking. The work requires strict adherence to material and quality specifications for concrete and asphalt, including aggregate quality, mix design, and rigorous testing protocols. The project budget is estimated between $1 million and $5 million, structured as a firm-fixed-price contract with a maximum completion timeline of 120 days. Phasing and traffic flow, especially around the runway and specific access gates, are significant logistical considerations, with the government supplying necessary radios and security coordinating controlled access through a single designated gate. Contract award will be based on evaluation factors such as past performance, mission capability, and price, with the government reserving the right to select other than the lowest bid. Proposals must be fully responsive to initial requests as awards may proceed without discussions. Solicitation releases and updates will be handled electronically via the Federal Business Opportunities website, requiring interested contractors to register and maintain eligibility through the Central Contractor Registration system, noting that registration can take several weeks. Additional details including handling of existing materials, project timelines, and specific technical queries were addressed during an industry day Q&A session, underscoring the importance of proven aggregate quality, definitive project start and end dates, and specialized approaches for construction aspects like slab jacking tie-down anchors and foreign object debris removal.

General Info

Repair and rehabilitate Mountain Home AFB taxiways with asphalt, concrete, lighting, under fixed price.

NAICS

237990 - Other Heavy and Civil Engineering Construction

Place of Performance

Mountain Home AFB, ID 83648, ID

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

3 updates
PhasePresolicitation
Posted

Presolicitation

Notice updated

The notice description changed. The point of contact changed.

Notice updated

The notice description changed.

Notice updated

The notice description changed. The point of contact changed.

Ready to pursue this opportunity?

Get full access to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → FA4897 366 Cons Pkp
Contacts1 person available
OfficeMOUNTAIN HOME AFB, ID, 83648-5296, USA
Office AddressMOUNTAIN HOME AFB, ID, 83648-5296, USA
Contacts
Cindy R DixonContract Administrator

Full Description

Show more
These are the questions and answers that occurred on the March 12, 2004 Industry day. Industry Day Questions and Answers 1) What criteria are you looking for in terms of Quality of Aggregate? A. Geologic testing and x years of proven performance or no geologic testing and x + y years of proven performance. Solicitation will include more detail and time frames. 2) Is the phasing plan a key issue, due to working around the runway? A. Yes. 3) Is the planned start date an evaluation factor? A. The actual planned start date will not be an evaluation factor if the proposal can meet the not to exceed threshold listed in the solicitation. 4) Can millings be reincorporated? A. No. 5) Is there a stockpile of crushed concrete currently on base? Is it going to balance out? Can we use that stockpile? How much is left? A. Yes. Calculations show the project will use less crushed concrete for base material than will be produced through demolition. The existing stockpile is usable, but not a sufficient quantity to complete the project without crushing material generated by this job. 6) Who will supply the radios that Airfield Management requires for the contractor to be in contact with the tower during operational hours? The contractor or the government? A. Government. 7) Is the 40V gate or another gate available to use? Will privately owned vehicles (POVs) be allowed through that gate or only marked construction vehicles? A. A single construction gate will be available and staffed as needed by Security Forces. All construction traffic for this project will be routed through the construction gate. Gates will allow direct access to either State Highway 51 (Bruneau Highway) or State Highway 67 (Grandview Highway). Following award, contractor will choose the preferred gate, which will be coordinated with Security Forces for use. 8) How will the flow of traffic work at the 40V gate if it is utilized? That is a one way flow on private property; will there be a two-way flow? A. Intent is for one-way loop traffic flow. This has yet to be finalized. 9) Is the end date defined? A. Yes, it will be defined in the solicitation. 10) In the overruns, is the asphalt milled up to existing base gravel underneath? A. Yes. 11) In the overruns, is it an option to move the thresholds up? A. No. 12) On the taxiways, does the milling and replacement go all the way to the runway? A. Yes, and the 200 clearance line is distinctly marked. 13) The foreign object debris (FOD) ridden concrete on H will be taken out. Will it be hauled and crushed? A. Yes. 14) On the portions of the project that require slab jacking, what will be done with the tie down anchors? A. Design Engineer is evaluating and solution will be included with the solicitation. 15) There are some roads that were utilized previously to access the overruns; will they be available for use on this project? A. Yes. This project repairs existing taxiways and overruns through various methods to include urethane injection slab jacking, mill and overlay of asphalt surfaces, and full-depth concrete replacement. A relatively small amount of electrical work is also included to install new edge lighting on one connecting taxiway. Concrete and asphalt products must meet strict guidelines as described in project specifications to include aggregate quality, mix design, quality control testing, batching tolerances, as-placed testing, and final performance. The approximate breakout of pavement repair methods are 520,000 square feet of asphalt mill and overlay, 150,000 square feet of full depth concrete replacement, and 16,250 square feet of slab jacking. The Magnitude of this project is between $1,000,000 and $5,000,000. This contract will be a FFP contract with a NTE 120 days. The successful contractor will be selected based upon several evaluation factors to include: past performance, mission capability, and cost/price. The Government reserves the right to award a contract to other than the lowest proposed price. Offerors shall submit proposals that can be accepted solely on the basis of the initial offer as the Government may proceed with award of contract without discussion. It is anticipated that the solicitation will be issued electronically on or about 31 Mar 04 using the Government's Federal Business Opportunities (FedBizOps). Paper copies are not available. You must register on the subject site in order to receive notification of changes to the solicitation; however, you may still retrieve the changes without registering. Note: Any prospective contractor must be registered in the Central Contractor Registration (CCR) (http://www.ccr.gov) in order to be eligible for award. Registration requires a DUNS number. Registration may take up to three weeks to process. Recommend registering immediately in order to be eligible for timely award.

Similar Contracts

Same NAICS industry code

NAICS: 237990
New
SLED
Carlson Field Athletic Complex: Construction of new Pickleball Courts
Solicitation # BCP-REC-26
The Town of Hingham, Massachusetts, is soliciting sealed bids for the construction of eight new pickleball courts at the Carlson Field Athletic Complex located at 28 Bare Cove Park Drive. This fixed-price lump sum project has an estimated construction cost of $1,300,000. The scope of work includes site preparation such as the removal of trees, shrubs, and stumps, re-grading the site, and the installation of the courts, posts, nets, walkways, benches, shade shelters, and ADA pathways. Additionally, the contractor is responsible for a new asphalt parking lot and the installation of solid AF-6 Acoustifence Panels around the entire perimeter for sound attenuation. The contractor must coordinate with the Town and the demolition contractor, Pasquazzi Bros, Inc., and is responsible for maintaining construction fencing and erosion control throughout the project duration. The contract will be awarded to the lowest responsible and eligible bidder who possesses at least seven years of experience constructing sports courts or paved athletic facilities. Bidders must submit their proposals electronically via the OpenGov portal by November 3, 2026, including a 5% bid security and a Statement of Qualifications with at least three similar public project references. Awarded contractors must provide a payment bond equal to 50% of the total project cost and adhere to Massachusetts prevailing wage laws, OSHA regulations, and the Massachusetts Building Code. The project includes a minimum one-year warranty for labor and a two-year warranty for materials. Final payment is contingent upon the submission of AIA affidavits for the payment of debts and release of liens.
Recreation

POSTED

about 6 hours ago

DEADLINE

in 5 days
View Details
NAICS: 237990
New
SLED
Pre-Qualification For Construction Of Park, Recreation & Libraries Parks And Facilities For 2027
Solicitation # 13-202
Solicitation 13-202 is a pre-qualification process issued by the City of Roseville, California, for the construction of park, recreation, and library facilities scheduled for 2027. The objective is to identify qualified contractors with the capacity and experience to execute new park construction and rehabilitation projects. Interested parties must submit their pre-qualification packages via email to the City Clerk’s Office by 3:00 p.m. on November 23, 2026. Submissions are limited to 25 megabytes and must include a signed questionnaire, DIR registration for all contractors and subcontractors, and current workers' compensation certificates of insurance. To achieve pre-qualified status, applicants must meet essential qualifications, including a valid California Contractor's license and specific insurance limits of 1,000,000 dollars per occurrence and 2,000,000 dollars aggregate. Experience requirements mandate the completion of at least six new park construction projects for public agencies within the last three years, with a maximum of three rehabilitation projects allowed toward this total. Financial solvency is verified through third-party credit checks, where a score of 650 or less may lead to disqualification. Evaluation also considers compliance with California apprenticeship laws, Davis-Bacon prevailing wage requirements, and CAL OSHA safety standards.
City of Roseville, Parks, Recreation & Libraries Department (PRL)

POSTED

about 7 hours ago

DEADLINE

in 25 days
View Details

More opportunities from Department Of Defense → FA4897 366 Cons Pkp

Same awarding agency

Earlier notices in this NAICS code

Posted before this notice, open and closed

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS