Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, December 9 at 2:00 PM ET

Register Free →

Contract Types & Vehicles

T&M (Time and Materials)

What is a time-and-materials contract?

A time-and-materials (T&M) contract pays for direct labor hours at specified fixed hourly rates and materials on the applicable actual-cost basis. Federal Acquisition Regulation (FAR) 16.601 covers this contract type separately from the cost-reimbursement types in Subpart 16.3.

The labor rate includes wages, overhead, general and administrative expenses, and profit. The materials definition is broader than physical supplies. Review the contract before assuming how travel, other direct costs, or material handling will be paid.

When is a time-and-materials contract used?

A time-and-materials contract is used when the government cannot estimate the work or material quantity with enough accuracy for another contract type. FAR 16.601 requires the contracting officer to document why a T&M contract is suitable. Use a ceiling, labor-hour controls, invoice review, and technical oversight to limit cost growth. Revisit the contract type when the work becomes predictable.

A worked time-and-materials example

Suppose an illustrative contract specifies a qualified labor category at $120 per hour. Eighty accepted hours in that category produce a $9,600 labor amount. If $1,000 in materials is also payable under the contract, the combined amount is $10,600 before any other applicable adjustments.

The $120 rate is not the employee's wage. Do not add overhead and profit again if the specified rate already includes them. Keep labor and materials separate in the review worksheet so the billing basis remains clear.

Check labor qualifications and hours

Confirm that the proposed staff meet the labor category requirements. Reconcile each category, rate, and planned hour with the technical approach. A correct multiplication does not resolve an incorrect staffing assumption.

For example, a response might promise senior oversight but price every hour at a junior category. The proposal reviewer should resolve that mismatch before submission. Retain the basis for the staffing mix so the delivery team can follow it after award.

Monitor the contract ceiling

FAR 16.601 requires a ceiling price that the contractor exceeds at its own risk. Maintain a forecast of remaining work alongside expenditure. Review the contract's notice provisions before the ceiling becomes an immediate problem.

A weekly review can compare hours used, work completed, and expected remaining effort. Assign an owner to investigate a growing gap. An internal forecast or expected modification does not itself increase the authorized ceiling.

Review materials separately

Identify the materials and other costs the proposal expects to incur. Check their payment basis and supporting records against the solicitation. Avoid counting the same indirect cost in both the labor rate and material handling.

Keep assumptions visible when the quantity or timing remains uncertain. The buyer and contractor need to understand what the estimate includes before using it to plan delivery.

Compare the rate structure with firm-fixed-price contracts and cost-plus-fixed-fee contracts. Their payment approaches require different estimating and administration assumptions.

Frequently asked questions

No. The specified hourly rate includes wages, overhead, general and administrative expenses, and profit. Check the contract rate and labor category qualifications.

Access all Federal, State & Local contracts with unmatched AI-powered tools

Get the complete contract database, AI contract matching and proposal writing, real-time deadline alerts, and pursuit management from discovery to award.

Miguel
Hillary
Keith Deutsch
Christine

Join 900+ contractors already using CLEATUS