This Solicitation opportunity from Ohio was posted on October 19, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
The City of Piqua, Ohio, is soliciting bids for Project No. 24-17.11, which involves the construction of the Washington Road 69kV Transmission Line. The project scope includes the furnishing and installation of approximately 2.0 miles of 69kV transmission line terminating at a new 69kV/13.8kV substation. Key technical requirements include a 12.47kV distribution underbuild from Pole P1 through P18, the installation of all-dielectric self-supporting fiber optic cable along the entire line, and the use of specific materials such as ductile iron and self-supporting steel poles. The engineer's estimate for the project is $1,900,000.
Bidders must demonstrate adequate financial and performance experience and provide a bid bond of no less than 10% of the total bid amount. The successful contractor will be required to post a combined performance and payment bond for 100% of the contract value. Compliance with State of Ohio Prevailing Wage laws, the Americans with Disabilities Act, and Drug-Free Workplace certifications is mandatory. All work must adhere to the National Electrical Safety Code and relevant ASTM standards. Bids are due by October 29, 2026, and may be submitted via Bid Express, email, or sealed hard copy.
General Info
City of Piqua bids for 2-mile transmission line construction estimated at $1,900,000.
PDF, High priority: read this first1 page · amendment
HighAI Summary for Addendum #2 - Project 24-17.11 Transmission Line Construction Washington Road 69kV: Addendum No. 2 dated October 6, 2026, for the City of Piqua project 24-17.11 regarding Transmission Line Construction on Washington Road. This amendment updates the required bid bond percentage to no less than 10%.
PDF
PDF, High priority: read this first1 page · amendment
HighAI Summary for Addendum 3 - Project 24-17.11 City of Piqua Transmission Line Construction: Addendum No. 3 dated October 19, 2026, for the Washington Road 69kV Transmission Line Construction project. It extends the bid opening date to October 29, 2026, and updates the Bid Bond requirement to no less than 10%.
PDF
PDF, High priority: read this first6 pages · amendment
HighAI Summary for Addendum No. 1 - Piqua The Site Substation & Transmission Line: Addendum No. 1 for Project No. 24-17.XX regarding the Piqua 69kV The Site Substation & Washington Road 69kv Transmission Line. The document provides clarifications to bidder questions across multiple packages, including Control Building and Relay Panels (24-17.9A), Major Equipment (24-17.9B), and Substation Electrical Construction (24-17.10). Key updates include bid deadline extensions to October 21st and 22nd, guidance on award structures, and technical clarifications regarding site preparation, equipment weights, and documentation references.
PDF
PDF, High priority: read this first7 pages · amendment
HighAI Summary for Addendum No. 2 - Piqua The Site Substation & Transmission Line: Addendum No. 2 for Project No. 24-17.XX (Piqua 69kV The Site Substation & Washington Road 69kv Transmission Line) issued by Encompass Engineers and Architects, Inc. for the City of Piqua, Ohio. The document provides technical clarifications in response to bidder questions regarding control building relay panels, major equipment specifications, steel structures, substation and transmission line construction (including fiber optic ADSS cable requirements and tree clearing responsibilities), and drilled pier foundations. It also clarifies prevailing wage documentation requirements.
PDF
PDF, High priority: read this first7 pages · specifications
HighAI Summary for Appendix B - Self-Supporting Steel Pole Set (Piqua 69kV Site Substation): Technical drawing set dated 7/20/2026 for self-supporting steel poles at the Piqua 69kV Site Substation (Project No. 25-0972). The document contains preliminary bid details across multiple sheets (S-9.0 through S-15.0) for the Piqua Powersystem on Washington Rd, Piqua, Ohio.
PDF
PDF, High priority: read this first2 pages · bid-bond
HighAI Summary for Bid Guaranty Bond for City of Piqua Project: This Bid Guaranty Bond document serves as a surety agreement between the bidder (principal) and surety to the City of Piqua (owner) for a specified project. It guarantees the bidder's commitment to enter into a contract if awarded and to perform according to the bid, plans, and specifications. The bond penal sum equals the bid amount or a specified minimum, ensuring financial coverage if the bidder defaults. The surety's liability is limited to the penal sum. The bond also covers payment claims by subcontractors and material suppliers. The document includes signature blocks for the bidder, surety, and surety agent, and stipulates that modifications to the contract do not affect the surety's obligations. This bond is a critical part of the bidding process to protect the owner from bidder default.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for C-1.0 Civil Site Plan - Conceptual Grading Plan: A conceptual grading and civil site plan for a crowned fenced area with a perimeter swale. The document specifies grading slopes (0.5%), dimensions for crowns/pads, and the use of lightweight concrete masonry bricks for the swale and curb.
PDF
PDF, High priority: read this first1 page · ifb
HighAI Summary for City of Piqua Project 24-17.11 - Washington Road 69kV Transmission Line Construction: Advertisement for Bids issued by the City of Piqua, Ohio, on September 6, 2026, for project 24-17.11. The procurement seeks transmission line construction work for the Washington Road 69kV Transmission Line. Bids are due by 10:00am on October 19, 2026, and can be submitted via Bid Express, email, or hard copy.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for E-7.1 - Conduit Schedule: Technical conduit schedule detailing conduit numbers, cable numbers, routing (from/to), sizes, PVC fitting requirements, and approximate lengths for electrical infrastructure, including transformers and breaker bays.
PDF
PDF, High priority: read this first77 pages · contract-document
HighAI Summary for EJCDC C-700 Standard General Conditions of the Construction Contract (2018): This document is the 2018 EJCDC C-700 Standard General Conditions of the Construction Contract, prepared by the Engineers Joint Contract Documents Committee. It establishes the legal framework and standard terms for construction contracts, covering critical areas such as definitions, bonds and insurance, contractor and owner responsibilities, change orders, claims, and dispute resolution.
PDF
PDF, High priority: read this first15 pages · specifications
HighAI Summary for EJCDC C-800 Supplementary Conditions of the Construction Contract: This document contains the Supplementary Conditions for a construction contract, based on the 2018 EJCDC C-800 template (revised 01.2022). It serves to amend or supplement the EJCDC C-700 Standard General Conditions, specifically addressing insurance requirements, document delivery, commencement of work, and site conditions.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for Loading Table - Pole 17: Technical load table for Pole 17, detailing vertical (V), transverse (T), and longitudinal (L) load cases in pounds (lbs) for various components including distribution, communication, static, and conductor phases.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for Loading Table Pole 28: Technical load table for Pole 28, detailing structural load cases (1-5) with vertical (V), transverse (T), and longitudinal (L) forces in pounds. Includes specific loading data for static, conductor, communication, and distribution components per phase.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for Loading Table Pole 63: Technical load table for Pole 63, detailing vertical, transverse, and longitudinal load cases (1-5) in pounds (LBS) for various components including communication, distribution, and conductor phases.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for Load Table - Pole 1: Technical loading table for Pole 1, detailing load cases (1-5) with vertical (V), transverse (T), and longitudinal (L) forces in lbs for communication, distribution, static, and conductor phases.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for Load Table - Pole 18: Load Table - Pole 18 showing static, conductor, distribution, and communication per-phase loading cases. Includes V, T, and L load values in pounds across multiple cases and items, likely for pole design/structural analysis.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for Load Table - Pole 2: Technical load table for Pole 2, detailing vertical (V), transverse (T), and longitudinal (L) load cases in pounds (LBS) for various components including static, conductor, distribution, and communication lines.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for Load Table - Pole 29: Technical loading table for Pole 29, detailing load cases (1-5) with corresponding vertical (V), transverse (T), and longitudinal (L) forces in pounds. The document specifies load requirements for static, conductor, distribution, and communication components per phase.
PDF
PDF, High priority: read this first4 pages · wage-determination
HighAI Summary for Payroll Submittals and Wage Determination Document: This document outlines the requirements for payroll submittals and prevailing wage determinations for public improvement projects as per Ohio Revised Code Sections 4115.03 to 4115.16. It details contractor obligations to submit certified payrolls, schedules of pay dates, and notifications to employees. The document includes penalties for violations and specifies the duties of contractors regarding wage rate postings, payroll reporting, and compliance affidavits. It serves as a guide for contractors to ensure adherence to prevailing wage laws and proper documentation throughout the contract period.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for Piqua 69kV Site Substation - Civil Site Plan Details: Technical civil site plan details for the Piqua 69kV Site Substation on Washington Road, Piqua, Ohio. The document specifies swale dimensions, profiles, low-flow channel requirements (2-4 inch stone on geotextile), and culvert specifications (18 inch, 40 LF) for the proposed drive.
PDF
PDF, High priority: read this firstwage-determination
HighAI Summary for Prevailing Wage Guide for Contractors - 2026: A comprehensive guide detailing the responsibilities of contractors regarding Ohio's prevailing wage laws (Chapter 4115 of the Ohio Revised Code) for the 2026 period. It outlines project cost thresholds for applicability, penalties for violations, requirements for apprentice ratios, payroll record-keeping, and specific instructions for submitting certified payroll reports.
PDF
PDF, High priority: read this first71 pages · wage-determination
HighAI Summary for Prevailing Wage Rate Schedule (LCN01-2026ib): Prevailing wage rate document listing skilled craft wage determinations and fringe benefit rates for multiple unions and classifications. Includes effective dates ranging from 2013 to 2026, change numbers (e.g., LCN01-2026ib, LCN02-2013fb), apprentice/journeyman ratios, jurisdictions, special jurisdictional notes, and detailed rate tables for asbestos workers, insulators, boilermakers, and bricklayers. This appears to be a prevailing wage schedule used for construction procurement compliance.
PDF
PDF, High priority: read this first72 pages · specifications
HighAI Summary for Soil Study for Washington and Drake Road Water Main and Sanitary Sewer: Geotechnical soil study report (No. 20001445 0425 077) dated April 9, 2025, prepared by Bowser-Morner, Inc. for Fishbeck. The document details subgrade soil conditions, groundwater levels, and bearing capacities for the installation of 3,800 LF of water main and 7,600 LF of sanitary sewer in Piqua, Ohio. It includes field work results from 17 soil borings, laboratory plasticity and moisture testing, and provides technical recommendations for trench excavation, compaction, and foundation preparation.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for Virginia Transformer Corp - Liquid Filled Step Down Transformer Cutsheet: Technical specification sheet for a Virginia Transformer Corp liquid filled step down transformer (Serial: 47012MA285-DA523B). Document includes electrical ratings (12000/16000/20000 kVA), voltage levels (69kV HV / 13.8kV LV), cooling class (ONAN/ONAF/ONAF), and physical dimensions/lifting diameters.
XLSX
XLSX, High priority: read this first2 pages · bid-tabulation
HighAI Summary for Washington Road 69kV Transmission Line Construction Bid Tabulation: Bid tabulation sheet for the Washington Road 69kV Transmission Line Construction project (Project No. 25-0972-TL, Bid Package 24-17.11) for the City of Piqua, Ohio, dated July 8, 2026. The document contains a detailed CLIN-style bid schedule including quantities and unit price fields for steel poles, ductile iron poles, transmission assemblies, and ACSR conductors.
PDF
PDF, High priority: read this first55 pages · ifb
HighAI Summary for Washington Road 69kV Transmission Line Construction - Project No. 24-17.11: Invitation for Bids (IFB) issued by the City of Piqua, Ohio, for the construction of the Washington Road 69kV Transmission Line (Project No. 24-17.11). The document, dated September 2026, includes a legal notice, bid submission requirements, an engineer's estimate of $1,900,000, and a detailed index of specifications and drawings. Bids are due by 10:00 AM on October 19, 2026.
PDF
PDF, High priority: read this first17 pages · specifications
HighAI Summary for Washington Road 69kV Transmission Line Drawing Set: Preliminary for bid drawing set dated 7/20/2026 for the Washington Road 69kV Transmission Line in Piqua, Ohio. The document includes an index of drawings, vicinity maps, and detailed bills of materials for pole specifications, including double tangent and transmission tap configurations, listing specific hardware, insulators, and conductor requirements.
PDF
PDF, Low priority1 page · certification
LowAI Summary for Americans with Disabilities Act Compliance Certification: A certification form requiring an authorized officer of a contracting firm to attest that the company is in compliance with the Americans with Disabilities Act (ADA) as of the bid submission date.
PDF
PDF, Low priority2 pages · bid-bond
LowAI Summary for City of Piqua Bid Guaranty Bond: A template for a Bid Guaranty Bond for the City of Piqua. The document outlines the legal obligations of the bidder (principal) and the surety to ensure the contract is entered into upon award, specifying penal sums and conditions for voiding the obligation.
PDF
PDF, Low priority1 page · past-performance
LowAI Summary for City of Piqua, Ohio - Contractor's Qualification Statement: A standard form from the City of Piqua, Ohio, dated January 2022, requiring bidders to provide references and details of previous work to establish their responsibility, experience, skill, and financial standing.
PDF
PDF, Low priority1 page · compliance-form
LowAI Summary for Drug Free Workplace Compliance Affidavit Form: A legal affidavit form requiring contractors to certify enrollment and good standing with the Ohio Bureau of Workers' Compensation Drug-Free Workplace Program or a comparable approved program. It includes a requirement that subcontractors also maintain compliance.
CITY OF PIQUA OHIO - Transmission Line Construction Washington Road 69kV Transmission Line.
ENGINEER’S ESTIMATE: $1,900,000 In general, the work consists of providing transmission line construction work for the Washington Road 69kV Transmission Line Project - Transmission Line Construction for The City of Piqua. State of Ohio Prevailing Wages are required.