Question and Answer Two (2) Amendment #5 updates the Performance Work Statement (PWS) by adding the section 5.3 Areas to be Cleared, clarifies federal/contractor holidays and adds the revised Pricing Schedule. Q3 - Would it be permissible to place storage containers to store sidewalk salt and small equipment at the salt domes (or other location) at both the Aberdeen and Edgewood areas? A3 - DPW will provide a location for a storage container at the salt dome for each area. The contractor will be responsible for locking and removal at the end of the snow season. The Government offers no surveillance. Q4 - Would it be permissible to place an above ground fuel tank for fueling small equipment at the salt domes (or other location) at both the Aberdeen and Edgewood areas? A4 - No above ground fuel tanks. The contractor will be responsible for the fueling of equipment and vehicles. Q5 - If the area is subjected to multiple snow events it may become necessary to load and transport snow by truck to the approved stockpile locations. This work would entail additional cost to the contractor over and above the costs associated with clearing a specific depth of snow. Are we to anticipate the potential for this to occur and incorporate those costs into the bid items presently provided or will an additional bid item be added specifically to cover loading and transport of snow? A5 - Line 14 is added to the bidders list for this requirement. Q6 - How will instances of freezing rain be dealt with when plowing is not required but salt is? (We believe this to be in reference to the way the contractor will get paid.) A6 - This will have to be paid under a 0 quote mark to 2 quote mark CLIN. Q7 - Will the contractor be required to wait for a call prior to mobilizing or will the contractor be allowed to mobilize and begin work as (s)he sees fit? A7 -The contractor will be contacted and will have a two hour response time beginning at that phone call. Q8 - How will the contractor be compensated in the event of a government delay in providing/loading of road salt? A8 -The Government will have personnel on site at all snow events. Statement - The fenced areas of 3090 and 3200 presently contain a significant quantity of vehicles and equipment in the secure area. Q9 - Can the 90% clear requirement be reduced in these locations to allow for areas made inaccessible by these obstructions? A9 - Yes, For Building 3090 there is no requirement for snow removal inside the fenced in area. Q10 - Please clarify the access arrangements for the secure areas to the rear of E-3400 in Edgewood and the fenced areas at 3090 & 3200 in Aberdeen. A10 - All secured areas at Aberdeen and Edgewood will be confirmed by the Contracting Officers Representative (COR) prior to access. Q11 - There is a Parking lot arm at 5100, will that be open during snow plow operations. A11 - Yes, the arm will be open during snow events. Q12 - The 6000 Complex, are the interior walks and court yard all part of this proposal, or is it done by housekeeping. A12 - The interior court yard shall be completed by the contractor and is included in section 5.3, area description to be cleared, of the Performance Work Statement (PWS). Maps displayed during the site visit were for reference only. A complete set of maps shall be given to the contractor who wins the award. (End of Q&A #2) 5.3 Area description to be cleared 8.5 Miles of roadway to be cleared. 45,000 Linear Foot of sidewalk to be cleared. 74 Acres of parking space to be cleared. 20 Each of air conditioners to be cleared. 80 entrance ways to be cleared. 12 flights of stairs to be cleared. All locked, secured areas shall be reported to the COR immediately. BASE YEAR Event# Base Year Snow Removal Contract SUPPLIES/SERVICES UNIT QTY UNIT PRICE AMOUNT 0001 Base Year Snow Removal 0 quote mark -2 quote mark Each 12 (On site within 2 Hours of notification) 0002 Base Year Snow Removal 2 quote mark -4 quote mark Each 12 (On site within 2 hours of notification) 0003 Base Year Snow Removal 4 quote mark -8 quote mark Each 10 (On site within 2 hours of notification) 0004 Base Year Snow Removal 8 quote mark -14 quote mark Each 5 (On site within 2 hours of notification) 0005 Base Year Snow Removal 14 quote mark + Each 2 0006 Base Year Snow Removal Sidewalks 0-2 quote mark LF 534,000 (One event includes 44,500 LF of sidewalk) 0007 Base Year Snow Removal Sidewalks 2 quote mark -4 quote mark LF 534,000 (One event includes 44,500 LF of sidewalk) 0008 Base Year Snow Removal Sidewalks 4 quote mark -8 quote mark LF 445,000 (One event includes 44,500 LF of sidewalk) 0009 Base Year Snow Removal Sidewalks 8 quote mark -14 quote mark LF 222,500 (One event includes 44,500 LF of sidewalk) 0010 Base Year Snow Removal Sidewalks 14 quote mark + LF 89,000 (One event includes 44,500 LF of sidewalk) 0011 Base Year Ice Melt Pallet 20 0012 Salt Containers Each 40 0013 Base Year Contract Manpower Reporting Each 1 http://www.cmra.mil 0014 Tandum 20 Ton Transport to secondary stockpile 3 mile maximum. Each 100 TOTAL OPTION YEAR ONE (1) Event# Option Year One Snow Removal Contract SUPPLIES/SERVICES UNIT QTY UNIT PRICE AMOUNT 1001 Option Year One Snow Removal 0 quote mark -2 quote mark Each 12 (On site within 2 Hours of notification) 1002 Option Year One Snow Removal 2 quote mark -4 quote mark Each 12 (On site within 2 hours of notification) 1003 Option Year One Snow Removal 4 quote mark -8 quote mark Each 10 (On site within 2 hours of notification) 1004 Option Year One Snow Removal 8 quote mark -14 quote mark Each 5 (On site within 2 hours of notification) 1005 Option Year One Snow Removal 14 quote mark + Each 2 1006 Option Year One Snow Removal Sidewalks 0-2 quote mark LF 534,000 (One event includes 44,500 LF of sidewalk) 1007 Option Year One Snow Removal Sidewalks 2 quote mark -4 quote mark LF 534,000 (One event includes 44,500 LF of sidewalk) 1008 Option Year One Snow Removal Sidewalks 4 quote mark -8 quote mark LF 445,000 (One event includes 44,500 LF of sidewalk) 1009 Option Year One Snow Removal Sidewalks 8 quote mark -14 quote mark LF 222,500 (One event includes 44,500 LF of sidewalk) 1010 Option Year One Snow Removal Sidewalks 14 quote mark + LF 89,000 (One event includes 44,500 LF of sidewalk) 1011 Option Year One Ice Melt Pallet 20 1012 Salt Containers Each 40 1013 Option Year One Contract Manpower Reporting Each 1 http://www.cmra.mil 1014 Tandum 20 Ton Transport to secondary stockpile 3 mile maximum. Each 100 TOTAL OPTION YEAR TWO (2) EVENT# Option Year Two Snow Removal Contract SUPPLIES/SERVICES UNIT QTY UNIT PRICE AMOUNT 2001 Option Year Two Snow Removal 0 quote mark -2 quote mark Each 12 (On site within 2 Hours of notification) 2002 Option Year Two Snow Removal 2 quote mark -4 quote mark Each 12 (On site within 2 hours of notification) 2003 Option Year Two Snow Removal 4 quote mark -8 quote mark Each 10 (On site within 2 hours of notification) 2004 Option Year Two Snow Removal 8 quote mark -14 quote mark Each 5 (On site within 2 hours of notification) 2005 Option Year Two Snow Removal 14 quote mark + Each 2 2006 Option Year Two Snow Removal Sidewalks 0-2 quote mark LF 534,000 (One event includes 44,500 LF of sidewalk) 2007 Option Year Two Snow Removal Sidewalks 2 quote mark -4 quote mark LF 534,000 (One event includes 44,500 LF of sidewalk) 2008 Option Year Two Snow Removal Sidewalks 4 quote mark -8 quote mark LF 445,000 (One event includes 44,500 LF of sidewalk) 2009 Option Year Two Snow Removal Sidewalks 8 quote mark -14 quote mark LF 222,500 (One event includes 44,500 LF of sidewalk) 2010 Option Year Two Snow Removal Sidewalks 14 quote mark + LF 89,000 (One event includes 44,500 LF of sidewalk) 2011 Option Year Two Ice Melt Pallet 20 2012 Salt Containers Each 40 2013 Option Year Two Contract Manpower Reporting Each 1 http://www.cmra.mil 2014 Tandum 20 Ton Transport to secondary stockpile 3 mile maximum. Each 100 TOTAL This will be a non-personal services contract to provide Snow & Ice removal services at Aberdeen Proving Ground, Maryland (APG), including both the Aberdeen Area, and the Edgewood area of APG. - A site visit will be posted by The Government. - The contractor shall provide all personnel, labor, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform snow removal services as defined in a Performance Work Statement (PWS) except for those items specified as government furnished property and services. - The period of performance shall be for one (1) Base Year of 12 months with two (2) 12 month option years. If it is in the best interest of the Government.