This Solicitation opportunity from New Jersey was posted on May 1, 2025. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
The contract pertains to the ACUA Solids Handling Improvements - Phase 1A project at the City Island Treatment Plant in Atlantic City, New Jersey. It involves significant upgrades to the plant’s solids handling infrastructure, including the replacement of three existing waste activated sludge thickening centrifuges with new Rotary Drum Thickening Units, installation of two emulsion polymer make-up systems, and the replacement of two sludge dewatering centrifuges along with all associated conveyance equipment. The scope of work is comprehensive, requiring adherence to detailed plans and specifications, and aims to enhance the plant’s operational efficiency and capacity.
The solicitation, identified as number 2025-ITB-04, was posted on May 1, 2025, with a response deadline of June 12, 2025. The project is estimated to cost between five and ten million dollars and is managed by the Atlantic County Utilities Authority under the jurisdiction of New Jersey. The contract will be governed by standard agreement terms, including provisions for performance security, insurance, warranties, compliance with the New Jersey Prevailing Wage Act, and record-keeping requirements. The contract may be subject to annual funding availability and could include renewal options. The primary point of contact for the project is John Conover, reachable via email or phone, and detailed project information can be accessed through the specified procurement portal.
HighAI Summary for 2025-ITB-04 ACUA Solids Handling Improvements - Phase 1A: Invitation to Bid (ITB) issued by the Atlantic County Utilities Authority (ACUA) for Solids Handling Improvements - Phase 1A at the City Island Treatment Plant. The project involves replacing three waste activated sludge thickening centrifuges with Rotary Drum Thickening (RDT) units, installing two emulsion polymer make-up systems, replacing one sludge dewatering centrifuge with two new units, and replacing sludge cake conveyors. Bids are due electronically by June 12, 2025, at 11:00 A.M. The document includes instructions to bidders, bid security requirements (10% up to $20,000), and compliance mandates for NJDEP and SED participation.
PDF
PDF, High priority: read this firstitb
HighAI Summary for 2025-ITB-04 Wilson Pike 16 inch & Ellendale Area Water Line Project: Invitation to Bid (ITB) issued by the City of Brentwood on April 24, 2025, for the Wilson Pike 16-inch and Ellendale Area Water Line Project. The scope includes the installation of approximately 3,200 LF of 16-inch, 110 LF of 12-inch, and 1,020 LF of 6-inch ductile iron water lines, along with service lines, tie-ins, and related appurtenances. Bids are due electronically by May 27, 2025, at 2:00 pm. Award will be made to the lowest responsive and responsible bidder.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for 29 CFR Part 5 Labor Standards Provisions: Current as of 01/28/25. This document is a regulatory extract from 29 CFR Part 5 covering labor standards provisions applicable to federally financed and assisted construction and certain nonconstruction contracts subject to the Contract Work Hours and Safety Standards Act. It includes purpose and scope, definitions, Davis-Bacon and Related Acts provisions, and labor standards concepts relevant to wage determinations, construction work, apprentices, helpers, and covered transportation.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for ACUA BID NO: 2025-ITB-04 - Technical Specifications: Technical specifications for the Atlantic County Utilities Authority (ACUA) Solids Handling Improvements - Phase 1A project (Bid No: 2025-ITB-04). Dated April 23, 2025, the document includes a detailed table of contents covering general requirements, concrete, metals, HVAC, electrical, process interconnections, and wastewater equipment. It specifically outlines the summary of work at the City Island Treatment Plant in Atlantic City, NJ.
PDF
PDF, High priority: read this first2 pages · contract-document
HighAI Summary for Atlantic County Utilities Authority Contract Agreement: This contract agreement between Atlantic County Utilities Authority (ACUA) and the Contractor outlines the terms for furnishing, delivering, and installing goods and services as per the specifications, proposal, and bidding documents. It includes provisions for performance security, insurance, warranties, compliance with the New Jersey Prevailing Wage Act, record maintenance, payment terms, and authority of signatories. The agreement is effective until delivery and acceptance or one year, subject to fund availability and renewal options. It ensures ACUA's rights in case of breach and mandates compliance with applicable laws and conditions.
PDF
PDF, High priority: read this firstcontract-document
HighAI Summary for Atlantic County Utilities Authority - General Conditions - Phase 1A: General Conditions of the Construction Contract for Phase 1A, prepared by the Atlantic County Utilities Authority. The document establishes the legal and operational framework for the project, including articles on contract time, bonds, insurance, contractor responsibilities, payment terms, change orders, and dispute resolution. It includes a detailed table of contents and index covering prevailing wage rates and liquidated damages.
PDF
PDF, High priority: read this first10 pages · wage-determination
HighAI Summary for Attachment 2 Davis Bacon Wage Rate Requirements: Attachment 2 outlines the wage rate requirements under The Consolidated and Further Continuing Appropriations Act, 2013 (P.I. 113-6) related to Davis-Bacon prevailing wage standards for construction projects funded by Clean Water and Safe Drinking Water State Revolving Funds. It specifies applicability, obtaining wage determinations, contract provisions, and compliance responsibilities for governmental and non-governmental subrecipients. The document provides detailed instructions on incorporating wage determinations into solicitations and contracts, monitoring updates, and ensuring subcontractor compliance. It serves as a critical guide for subrecipients to meet federal labor standards in EPA-funded construction activities.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for Bid No. 2025-ITB-04 Electrical Dewatering - Level 1: Engineering drawing sheet for Phase 1A: Solids Handling Improvements at the City Island Wastewater Treatment Plant in Atlantic City, New Jersey. Dated April 2025 and associated with Bid No. 2025-ITB-04, Drawing E-201, titled "Electrical Dewatering - Level 1." Includes project engineer, design/check signatures, firm information, and revision/title block details.
PDF
PDF, High priority: read this firstimplementation-procedures
HighAI Summary for Build America, Buy America Act Implementation Procedures for EPA Office of Water: This November 3, 2022 memorandum outlines the EPA Office of Water's procedures for implementing the Build America, Buy America (BABA) Act under the Bipartisan Infrastructure Law. It supplements OMB Guidance M-22-11 with specific clarifications for EPA water infrastructure programs. The document details the application of BABA requirements to various EPA water infrastructure investment programs, effective for funds obligated on or after May 14, 2022. It includes sections on general guidance, product coverage, co-funding, waivers, compliance documentation, and program-specific issues, along with example contract and assistance agreement language. The procedures aim to ensure domestic sourcing of iron, steel, manufactured products, and construction materials, supporting resilient U.S. supply chains and manufacturing jobs.
PDF
PDF, High priority: read this first3 pages · modification
HighAI Summary for Contract Modification Proposal and Acceptance Form: This document is a Contract Modification Proposal and Acceptance Form used to propose changes to an existing contract. It includes sections for issuing office, project and contract numbers, description of the change, cost adjustments, and contract time modifications. The form requires detailed cost breakdowns and signatures from the contractor, owner, and engineer. It also documents the necessity for the change, impacts, and negotiation summaries. The form is essential for formalizing contract amendments and ensuring all parties agree to the modifications.
PDF
PDF, High priority: read this first20 pages · special-notice
HighAI Summary for Implementation of American Iron and Steel Provisions of P.L. 113-76: This memorandum from the EPA outlines the implementation of the American Iron and Steel (AIS) provisions of P.L. 113-76, Consolidated Appropriations Act, 2014. It details the requirement that Clean Water and Drinking Water State Revolving Fund assistance recipients use U.S.-produced iron and steel products for relevant projects funded from January 17, 2014, through the end of Fiscal Year 2014. The document explains project coverage, product definitions, waiver conditions, and exemptions, including projects with engineering plans approved before the enactment date. It provides a Q&A format for guidance on compliance and waiver requests, emphasizing EPA's management and oversight role.
PDF
PDF, High priority: read this firstwage-determination
HighAI Summary for NJ State Prevailing Wage Rate Determination - Atlantic County: Official prevailing wage rate determination from the New Jersey Department of Labor and Workforce Development for Atlantic County. The document specifies hourly wage rates (W), fringe benefit rates (B), and total rates (T) for various crafts, including Air Conditioning & Refrigeration (Service and Repair) and Boilermakers. It includes apprentice rate schedules, ratio requirements, shift differentials, overtime rules, and mandatory public works contractor registration requirements.
PDF
PDF, High priority: read this first6 pages · reporting-form
HighAI Summary for SED Participation Building Phase Quarterly Reporting Form: This document is the SED Participation Building Phase Quarterly Reporting Form (OEO-002) issued by the New Jersey Department of Environmental Protection's Office of Equal Opportunity and Public Contract Assistance. It provides instructions and a form for quarterly reporting on the utilization of Socially and Economically Disadvantaged Businesses (SEDs) including MBEs and WBEs during the building phase of projects financed through New Jersey environmental infrastructure programs. The form requires detailed information about project sponsors, contractors, contract numbers, project descriptions, SED participation goals, subcontract awards, and signatures. It is intended for contracting agencies and contractors to submit quarterly reports within 15 days after each fiscal quarter to ensure compliance with SED utilization requirements under New Jersey regulations.
PDF
PDF, High priority: read this firstwage-determination
HighAI Summary for Wage Determination - Atlantic County, NJ (03-14-2025): Davis-Bacon Act wage determination for building construction projects in Atlantic County, New Jersey, published on March 14, 2025 (Modification 2). The document specifies minimum hourly wage rates and fringe benefits for various trades, including carpenters, electricians, power equipment operators, and elevator mechanics. It also outlines applicable Executive Order minimum wage requirements and detailed group definitions for equipment operators.
PDF
PDF, Low prioritysupporting-documents
LowAI Summary for ACUA Solids Handling Improvements Phase 1A - SED Utilization Plan: Dated January 2025, this document outlines the Socially and Economically Disadvantaged (SED) Utilization Plan for the Atlantic County Utilities Authority's Treatment Plant Resiliency project (Phase 1A). It establishes a goal of at least 10% contract awards to SED-owned small businesses, defines compliance procedures for prime contractors, and details the reporting requirements and responsibilities of the project compliance officer.
PDF
PDF, Low prioritybond-form
LowAI Summary for Atlantic County Utilities Authority Payment and Performance Bond Form: A statutory required form for a Payment and Performance Bond for the Atlantic County Utilities Authority. The document provides the legal language for the bond agreement and includes a mandatory Surety Disclosure Statement and Certification to verify the surety's capital, surplus, and underwriting limitations.
PDF
PDF, Low priority3 pages · contract-document
LowAI Summary for Environmental Maintenance Bond Document: This document is an Environmental Maintenance Bond in accordance with N.J.A.C. 7.22-10.11 (p). It binds the Principal and Surety to the Owner for $25,000 or 50% of the price bid for materials fulfilling environmental specifications. The bond ensures faithful performance of the contract, indemnifies the Owner against damages or costs arising from the work, and obligates the Surety to complete the work if the Principal fails. The bond remains effective for one year after final acceptance of the work. It includes provisions for modifications, waivers, and assignments without impairing the Surety's obligations. The document requires signatures and seals from the Principal and Surety, with instructions for execution depending on the Contractor's legal status.
PDF
PDF, Low priority2 pages · bond
LowAI Summary for General Maintenance Bond Sample Form: This document is a sample General Maintenance Bond form used in construction contracts. It outlines the bond obligation where the Principal and Surety guarantee to the Obligee the remedy of defects resulting from poor workmanship, defective materials, or contract non-compliance for one year after final acceptance. The bond includes provisions for modifications to the contract and requires signatures from individual and corporate principals, along with attestation by the Surety. Instructions for completing the bond, including details on parties involved, dates, and attachments like Power of Attorney and Financial Statement, are provided. The document also mentions premium rates and charges to be filled by the Corporate Surety.
PDF
PDF, Low priorityother
LowAI Summary for N.J.A.C. 7:22 Subchapter 9 - SED Awarding Contracts: A courtesy copy of the New Jersey Administrative Code (N.J.A.C. 7:22 Subchapter 9), readopted December 10, 2018. This regulatory document establishes procedures and requirements for awarding contracts for State-assisted environmental infrastructure projects to small business concerns owned and controlled by socially and economically disadvantaged (SED) individuals, including a minimum 10 percent participation goal.
LowAI Summary for SED Participation Monthly Progress Report OEO-003: This document is the SED Participation Monthly Progress Report (OEO-003) used by the New Jersey Department of Environmental Protection's Office of Equal Opportunity and Public Contract Assistance. It is designed to monitor the utilization progress of small business enterprises owned and controlled by socially and economically disadvantaged individuals (SED) in the Environmental Infrastructure Financing Program. The report requires contractors to provide updates on solicitation, bidding, negotiation, and subcontract awards involving SEDs for the reporting month. It includes sections for contractor and project details, and requires signatures from the contractor and project compliance officer.
PDF
PDF, Low priority1 page · other
LowAI Summary for State Treasurer's List of Debarred, Suspended, & Disqualified Bidders: This document provides information about the current list of firms and individuals debarred under the New Jersey Prevailing Wage Act from participating in Public Works Contracts in New Jersey. It directs readers to an online resource for the most up-to-date list of debarred, suspended, and disqualified bidders.
PDF
PDF
AI Contract Breakdown
Uniform Contract Format
Sign up to view the full breakdown with detailed analysis of each section.
Timeline
1 update
PhaseClosed
Posted
Solicitation
Notice updated
Response deadline changed from May 27, 2025 to Jun 12, 2025. The notice title changed. NAICS code changed from 237110 to 561210. The notice description changed. The point of contact changed.
Response Deadline
Deadline has passed
Submission Closed
Find active opportunities like this
Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.
Organization & Contact Information
Show more
AgencyNew Jersey → Atlantic County Utilities Authority
Bids are solicited for ACUA Solids Handling Improvements - Phase 1A at the ACUA City Island Treatment Plant in Atlantic City, NJ. The work includes, but is not limited to:Replacement of three (3) existing waste activated sludge thickening centrifuges with three (3) new Rotary Drum Thickening (RDT) UnitsInstallation of two (2) emulsion polymer make-up systemsReplacement of the existing sludge dewatering centrifuge with new two (2) new sludge dewatering centrifugesReplacement of Sludge Cake ConveyorsAll associated workAll work shall be performed according to the plans and specifications.
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award