Amirault Street Elevated Water Storage Tank

Open
ENG-26-06International

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

Solicitation ENG-26-06, issued by the City of Dieppe, New Brunswick, concerns the construction and commissioning of a 2,756 m3 composite elevated water storage tank on Amirault Street. The scope of work encompasses the tank foundation, process piping, electrical and mechanical systems, instrumentation and controls, site access roads, and site services. Key technical requirements include adherence to AWWA D103 standards and the City of Dieppe Standard Municipal Specifications. The contractor is responsible for the design, fabrication, and packaging of equipment, as well as the application of interior linings and exterior coatings. Deliverables include shop drawings and operation and maintenance manuals, with final acceptance contingent upon a manufacturer's representative report confirming successful start-up and commissioning. The bidding process requires electronic submissions via the Bids&Tenders platform by November 10, 2026, with an anticipated award date of November 23, 2026. Tenderers must provide a bid bond equal to 10% of the total price and a Gantt/Bar type schedule. Evaluation may be based on the initial purchase price and life cycle cost analysis. The contract includes a financial incentive and penalty structure of 1,000 dollars per working day for early or late completion. Additionally, the tank supplier must maintain professional liability insurance for errors and omissions with a minimum coverage of 3,000,000 dollars for the tank and foundation design.

General Info

City of Dieppe solicitation for constructing and commissioning a composite elevated water tank.

Documents

3
PDF, High priority: read this first20 pages · specifications
High
PDF, High priority: read this first219 pages · itb
High
PDF, High priority: read this first9 pages · rfb
High

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseSolicitation
Posted

Solicitation

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Get full access to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyVille de Dieppe / City of Dieppe
ContactsNo contacts available
OfficeCAN
Office AddressCAN
ContactsNo contact information available

Full Description

Show more
SCOPE OF WORK:In general, the work consists of the construction of a composite elevated water storage tank as shown on the Project Drawings and as specified in the Specifications. Work includes construction and commissioning of a 2,756 m3 composite elevated water storage tank complete with tank foundation, process piping, electrical and mechanical systems, instrumentation and controls, site access road and site services.OBJECTIF:En général, les travaux consistent en la construction d'un réservoir d'eau surélevé composite, comme indiqué sur les plans du projet et spécifié dans les spécifications. Les travaux comprennent la construction et la mise en service d'un réservoir d'eau surélevé composite de 2 756 m3, complet avec fondation de réservoir, tuyauterie de procédé, systèmes électriques et mécaniques, instrumentation et contrôles, accès au site, route et services de site.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project, solicitation number SRP-W-134-0290, is a construction contract for the City of Belmont, North Carolina, with an estimated value of 16,690,000 dollars. The scope of work involves the construction of 16,435 linear feet of new 20-inch ductile iron force main and extensive upgrades to the Morgans Branch Pumping Station. Key deliverables include the installation of a new wet well, valve vault, pumps, a generator, and odor control equipment, as well as the demolition of existing pumps and piping. Additional requirements include site improvements, stormwater facilities, fencing, and the installation of new gravity sewers and manholes. The contract will be awarded to the responsible bidder submitting the lowest responsive bid, with evaluation focusing on qualifications, financial ability, and strict adherence to bidding documents. Bidders must provide bid security, evidence of authority to sign, and M/WBE compliance documentation, including a Good Faith Efforts Form and Table A. The successful contractor is required to furnish performance and payment bonds equal to the contract price and maintain insurance from companies with an A.M. Best rating of A-VII or better. Project administration follows EJCDC standards, with payments processed monthly via applications for payment submitted to the Engineer, and final acceptance contingent upon the Engineer's written recommendation.
Don Moorhead Construction, Inc.

POSTED

about 3 hours ago

DEADLINE

in 2 days
View Details
NAICS: 237110
New
Jefferson St. Pump Station Replacement
Solicitation # ITB-2026141
The Jefferson Street Pump Station Replacement project for the City of Winchester, Virginia, involves the construction of a new pump station featuring a precast concrete building, controls, and a standby generator. The scope of work includes site electrical, yard piping, security fencing, grading, paving, the relocation of an existing fuel tank, and the demolition of existing facilities. All work must be completed within 610 calendar days following the Notice to Proceed, with liquidated damages set at 1,000 dollars per day for delays. The project is governed by VDOT 2020 Road and Bridge Specifications and the City of Winchester Standards Manual, with strict adherence to OSHA and ADA requirements. WG Construction is seeking MBE/WBE subcontractor participation for paving, material supply, site development, fencing, MEP, roofing, and carpentry. Bids are due by 2:00 pm on November 12, 2026, via the City's e-Procurement Portal. The contract will be awarded to the lowest responsive and responsible bidder. Requirements for bidders include registration in the Commonwealth of Virginia, submission of a bid guarantee, and the provision of performance and payment bonds equal to 100 percent of the contract amount. Additionally, the project is subject to Davis-Bacon wage determinations and requires compliance with various federal executive orders regarding non-discrimination and the use of American Iron and Steel.
WG Construction Co., Inc.

POSTED

about 3 hours ago

DEADLINE

in 2 days
View Details

More opportunities from Ville de Dieppe / City of Dieppe

Same awarding agency

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS