Basketball court reconstruction
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
The contract involves the complete reconstruction of the basketball half-court at the U.S. Embassy Vienna Marine House, located in Vienna, Austria. The existing court is outdated and undersized, prompting a full demolition and rebuild. The scope includes the removal and disposal of the current asphalt court surface, substructure, lighting, and basketball hoop infrastructure. The new court will be significantly larger, measuring approximately 13 meters by 14 meters, and will feature a modern sports surface made of EPDM rubber or an equivalent material. Construction will also encompass subgrade preparation including drainage, installation of foundations for the basketball hoop and two light poles, new adjustable basketball hoop, exterior lighting with necessary cabling, surrounding stone slab installation, line painting, and final cleaning. Work must be conducted while the facility remains operational and residents are present, requiring strict adherence to U.S. government security regulations, safety standards, and a clearance process for all personnel, vehicles, and materials accessing the site. The project is managed by the U.S. Embassy Vienna under the Department of State, with an indicative construction period of five weeks scheduled for the fall of 2026. Proposals are to be submitted by the response deadline of late July 2026. The general contractor selected will be responsible for both the sport field construction and electrical installation, ensuring minimal disruption and compliance with all specified requirements.
General Info
Agency
NAICS
Place of Performance
Vienna, AT-9, AUTSet-Aside
Documents
(0)AI Contract Breakdown
Uniform Contract FormatNo contract breakdown available.
Cannot generate Contract Breakdown because no documents were found from this contract's source.
Timeline
Response Deadline
Organization & Contact Information
Full Description
This project if for the reconstruction of the basketball half-court at the U.S. Embassy Vienna Marine House, located in 1190 Vienna.
The existing outdoor basketball half-court is at the end of its life cycle and too small in dimensions.
The scope of work includes but is not limited to the demolition of the existing sports field surface and substructure, in their entirety, as well as the removal of the lighting.
Construction of a new sports field surface, including the substructure, in its entirety, as well as a new lighting system.
Scope of work: General Contractor for Construction of Sport Fields and Electrical Installation
- Site Installation
- Demolition
- Demolition, removal and disposal of existing basketball half- court (asphalt layer 7x8m), existing exterior lights and basketball basket with posts
- Soil removal and disposal for new basketball half- court dimension (13mx14m = 182m²), 0.3m depth = ~55m³
- Construction of a new sport field
- Preparation/installation subgrade/subbase incl. drainage
- Installation top layer (EPDM rubber surface or equal)
- Installation point foundation for 1 basketball hoop and for 2 light poles
- Installation 1 adjustable basketball hoop, and 2 exterior lights incl. cabling/rewiring
- Laying stone slabs 40x40x5cm around the court
- Painting lines
- Final cleaning
- Special requirements
- The work will be carried out while the facility remains in operation and in the presence of the residents, who should not be disturbed during the construction work
- USG Security regulations
- Clearance process for employees, cars, material on site
- Safety and protective measures
Execution periods
Indicative construction schedule: 5 weeks in fall 2026