Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, August 19 at 2:00 PM EDT

Register Free →

Castle Mountain Mine Phase II Expansion Project

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

Castle Mountain Venture is proposing the Phase II Expansion of the Castle Mountain Mine, a project designed to extend the mine’s operational life by approximately 30 years, with 20 years dedicated to mining and processing followed by 10 years of reclamation. The expansion would quadruple the annual mining rate from 18 million tons to 80 million tons, resulting in an additional 296 million tons of ore extracted and 196 million tons of overburden stockpiled, while increasing the crushing rate from 6 million to 19 million tons per year. To support this scaled operation, the project requires 2,250 acre-feet of groundwater annually and up to 25 megawatts of power, necessitating the construction of a 32-mile water pipeline and a 16.5-mile powerline from Walking Box Ranch to the mine site. Walking Box Ranch, a historically registered property managed by the Bureau of Land Management and the University of Nevada, Las Vegas, would be crossed by these utilities, which are planned primarily within existing rights-of-way. The expansion would increase total land disturbance to 3,294 acres, including 1,800 acres outside the previously approved Approved Project Area, affecting BLM-managed land under the California Desert Conservation Area and the Nevada Las Vegas Field Office. A realignment of the existing access road is proposed to avoid crossing 1,000 feet of the Mojave National Preserve, resulting in the disturbance of an additional 5 acres of BLM land, with the National Park Service participating in the environmental review process. The project also includes deepening and expanding open pits beyond 400 feet below the water table, creating a permanent open pit lake, and reducing natural flow at Piute Springs by approximately 8%, impacting a riparian habitat. Operational workforce levels are projected to include up to 500 temporary and 400 permanent employees. Environmental compliance with NEPA, CEQA, CCR, and SMARA frameworks is central to the project, requiring detailed Leak Detection and Monitoring Plans, stormwater management to 20-year/1-hour storm standards, and reclamation success at 80% confidence levels. All inspections and acceptances are the responsibility of the Bureau of Land Management, conducted at operational sites within San Bernardino County, with no formal procurement contract structure, pricing, or federal acquisition clauses identified—indicating this is an environmental and land-use authorization process rather than a traditional federal procurement

General Info

Castle Mountain Mine Phase II expands operations 4.5x, requires new water and power lines, disturbs 3,294 acres, impacts groundwater and springs, and requires BLM oversight.

Agency

California → San Bernardino County

NAICS

541620 - Environmental Consulting ServicesView NAICS

Place of Performance

15 miles soutwest of State Route 164 and Walking Box Ranch Rd, CA, 92364

Set-Aside

NONE

Documents

(45)

Castle Mountain Mine Phase II Expansion Project CEQA Summary Form

PDFceqa-summary

EIS Appendix B - Referenced Tables for Castle Mountain Mine Project

PDFother

Appendix K POD_EQX-CMM_POD_App G_PL Eng(2025)_OCR

PDF

MRAA-2022-00002 Castle Mountain Mine Phase II Expansion Project CEQA Notice of Completion

PDFceqa-notice-of-completion

Castle Mountain Mine Phase 2 Project Socioeconomic Report

PDFsocioeconomic-report

EIS Appendix H - Legal Land Description

PDFother

EIS Appendix E Legal Descriptions for Castle Mountain Project

PDFlegal-description

Castle Mountain Mine Industrial Storm Water BMP Plan September 2022

PDFsow

Appendix D Right-of-Way Grants - Viceroy Gold Corporation

PDFright-of-way-grant

Castle Mountain Mine Project Phase II Expansion Draft Environmental Impact Statement

PDFdeis

EIS Appendix D - Consultation Coordination and Public Involvement

PDFappendix

EIS Appendix L - Alternatives Considered and Dismissed

PDFenvironmental-impact-statement-appendix

Castle Mountain Venture SPCC Plan Addendum February 2021

PDFspcc-plan

Castle Mountain Venture Ivanpah Water and Power Line Plan of Development

PDFplan-of-development

CDFW Comments on Castle Mountain Mine Phase II Expansion DEIR

PDFcomment

EIS Appendix F - List of Preparers

PDFother

2024-2025 Federal Mining Claim Maintenance Fee Payments - Castle Mountain Venture

PDFcontract-document

EIS Appendix E - Applicant Committed Environmental Protection Measures

PDFappendix

_CMM Public Review Draft EIR_April 2026_V2_DEIR Appendices_re-OCR

PDF

NAHC Comment on Castle Mountain Mine Phase II Expansion Project

PDFcomment

Castle Mountain Mine Plan of Operation & Reclamation Plan Amendment 2022

PDFmine-plan-amendment

Castle Mountain Mine Project Phase II Expansion Draft Environmental Impact Report

PDFenvironmental-impact-report

CDFW Comments on Castle Mountain Mine Phase II Expansion NOP

PDFcomment-letter

Appendix K POD_EQX-CMM_POD_App A_Figures 2025

PDFspecifications

Appendix J MPO_App D - Figures 1-3ah: San Bernardino Meridian Pit and Facility Boundaries

PDFother

EIS Appendix C - Referenced Figures

PDFother

Appendix J MPO_App B - Figures 1-2h Support Facilities Map

PDFspecifications

Castle Mountain Mine 69 kV Power Transmission Line Environmental Assessment (1990)

PDFenvironmental-assessment

Castle Mountain Mine Emergency Response Plan 2024

PDFemergency-response-plan

Castle Mountain Mine Geochemical Characterization Report 2024

PDFreport

Castle Mountain Mine Phase II Expansion Project Notice of Completion

PDFnotice-of-completion

EIS Appendix G - Permits and Approvals for Phase II Expansion Project

PDFother

Castle Mountain Geotechnical Feasibility Report April 2020

PDFgeotechnical-report

Appendix F Proposed Water Line Preliminary Engineered Drawings

PDFspecifications

MRAA-2022-00002 Castle Mountain Mine Phase II Expansion NOP CEQA

PDFpresolicitation

CMM Spill Prevention & Response Plan v2.1

PDFsop

Castle Mountain Mine Phase II Expansion Project NOA/NOI

PDFspecial-notice

Updated Water Supply Assessment for Castle Mountain Mine Project

PDFwater-supply-assessment

EIS Appendix I Visual Simulations

PDFappendix

Castle Mountain Mine Phase II Expansion Project Summary Form

PDFenvironmental-summary

CEQA Initial Study for Castle Mountain Mine Power Line Project Amendment

PDFceqa-initial-study

Revised Groundwater Monitoring Plan for Castle Mountain Mine 2024

PDFmonitoring-plan

Castle Mountain Mine Road Use and Maintenance Plan November 2023

PDFroad-use-and-maintenance-plan

Castle Mountain Venture Waste Rock Management Plan 2024

PDFwaste-rock-management-plan

Castle Mountain Mine Interim Management Plan Aug 2024

PDFinterim-management-plan

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

1 update
Posted

forecast

Amendment 1

Contract was updated

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → San Bernardino County
Contacts4 people available
OfficeN/A
Organization / Agency
California → San Bernardino County
Office AddressN/A
Contacts
Aren HallEnvironmental & Permitting Manager
Jessica CleavengerSenior Environmental Planner

Interested Companies (1)

Show more
SWCA Environmental Consultants
Phoenix, CA

Full Description

Show more
Castle Mountain Venture (CMV) has submitted a proposal for the second expansion of the CMM. The Project is referred to as the “Phase II Expansion.” The Phase II Expansion would extend the mine life by approximately 30 years, with 20 years of mining and processing and 10 years of reclamation. Operations would effectively quadruple the annual mining rate from 18 million tons to 80 million tons. The increased rate would require a total of 2,250 acre-feet per year of groundwater and up to 25 megawatts of power. To meet these demands, CMV would construct a 32-mile water pipeline and a 16.5-mile powerline (Figure 1) from Walking Box Ranch to the second phase of development. Walking Box Ranch is listed on the National Register of Historic Places, owned by the BLM, and managed by the BLM and the University of Nevada, Las Vegas Public Lands Institute. The proposed utilities would be located largely within existing rights-of-way and would cross public land managed by the BLM CA NFO and the BLM NV Las Vegas Field Office (Figure 2). The proposed Project would include the expansion of the mine pits, overburden sites, and heap leach pad, all within the existing Approved Project Area (APA). The APA, shown in Figure 2, was previously approved by the BLM and the County. The Project would also include the installation of the associated pipeline and powerline, which would disturb an additional 1,800 acres of BLM land outside of the APA, for a total project disturbance of 3,294 acres. CMM’s access road was approved under the mine’s original BLM Plan of Operations (CACA-031137) in 1990. When the California Desert Protection Act of 1994 established the Mojave National Preserve, it inadvertently included 1,000 feet of the mine’s access road and proposed utilities. CMV has proposed a realignment of the mine’s access road that avoids the Preserve but would disturb 5 acres of BLM land. The National Park Service will participate in the NEPA/CEQA process and will assist BLM in selecting the preferred road alignment. The proposed expansion includes: - Extending the mine life by approximately 30 years, with 20 years of mining and processing and 10 years of reclamation. - Quadrupling the annual mining rate from 18 million tons to 80 million tons. - Increasing the total land disturbance by an additional 1,800 acres. - Increasing mining by an additional 296 million tons. - Increasing overburden stockpiling by an additional 196 million tons. - Increasing crushing rate from 6 million to 19 million tons per year. - Increasing power usage to 25 megawatts of power per year. - Increasing groundwater use by an additional 1,625-acre feet per year: - 830 to 1,340 acre-feet per year would be supplied from wells at the mine site within Lanfair Valley Groundwater Basin - 830 to 1,340-acre feet per year would be supplied via a pipeline from wells within the adjacent Ivanpah Valley Groundwater Basin - ~8% reduction in flow at Piute Springs (riparian habitat and ecological reserve). - Expanding and deepening open pits to more than 400 ft. below the water table. - Employing up to 500 temporary and 400 permanent workers. - Creating an open pit lake, which will remain as a permanent land feature.

Similar Contracts

Same NAICS industry code

NAICS: 541620
New
Federal
PROJECT VA GWMP CLI-CULTURAL RESOURCE SURVEY
Solicitation # 693C7326Q000015
The contract is a Request for Quotation issued by the Federal Highway Administration’s Eastern Federal Lands Highway Division for the development of a Cultural Landscape Inventory for the Spout Run Parkway segment of the George Washington Memorial Parkway in Arlington, Virginia, covering approximately 46 acres bounded by the Memorial Parkway to the north, Interstate 66 to the south, the North Highland neighborhood to the east, and the Woodmont neighborhood to the west. The contractor must possess specialized expertise in cultural resource surveying and be capable of conducting technical analyses to produce a comprehensive final inventory that includes a narrative and graphic chronology of physical history, an integrity assessment, a condition evaluation, treatment recommendations, maps, GIS geodatabases, and supporting documentation adhering to National Park Service standards, including the NPS Cultural Landscapes Inventory Professional Procedures Guide (2025), the Secretary of the Interior’s Standards for Archeology and Historic Preservation, and the Chicago Manual of Style (18th Edition). All deliverables must comply with Section 508 accessibility requirements, be produced using NAD83 (2011) datum for GIS data, and follow the NPS Core Data Standards model, with final GIS layers requiring explicit approval by NPS GIS staff. The contract is firm-fixed price and requires itemized cost breakdowns for all tasks, including reimbursable travel expenses limited to GSA per diem rates for McCalla, Alabama, with receipts mandatory for airfare, rentals, and miscellaneous costs, and administrative expenses must detail actual hours and costs. Award will be determined based on best value rather than lowest cost, evaluating proposed methods and techniques, contractor qualifications and experience alongside price, with no small business set-aside and no formal weighting system provided. Contractors must maintain an active SAM registration with up-to-date UEI, CAGE, and tax information and affirm representations related to entity responsibility, non-inversion, tax compliance, and small business status. The contract incorporates unique clauses including a deviation of FAR 52.212-4 for commercial services, a requirement to comply with 52.222-90 prohibiting racially discriminatory DEI activities, and mandates for electronic invoicing through the DOT’s Delphi eInvoicing portal accessed via Login.gov, with a copy emailed to the FHWA COR. All work product becomes the sole property of the U.S. government, and contractors may retain only copies. Performance is required through December 30, 2027, with final government acceptance scheduled from August
693C73 Eastern Federal Lands Division

POSTED

about 10 hours ago

DEADLINE

in 4 days
View Details
NAICS: 541620
New
Federal
F107--Asbestos Baseline Survey Northern California VA Health Care System
Solicitation # 36C26126Q1100
The Department of Veterans Affairs, through its Network Contracting Office 21, is seeking information from contractors capable of performing an Asbestos Baseline Survey at the Northern California VA Health Care System under NAICS code 541620, with a small business size standard of $19 million. This is a sources sought announcement only, not a solicitation, and no binding commitments or payments are guaranteed. Responses must be submitted by email to Angela Gerlitzki no later than 10:00 a.m. EST on August 14, 2026, and must include the company’s legal name, SAM Unique Entity Identifier, socioeconomic status, certifications, capability statements, similar past projects, teaming or subcontracting plans complying with FAR and VAAR limitations, GSA contract number if applicable, and a completed price estimate. Participation requires current SAM registration and, for SDVOSB or VOSB firms, active certification in the SBA’s database. The anticipated period of performance is from September 8, 2026, to September 7, 2027, with the solicitation number 36C26126Q1100 to be referenced in all communications. All submissions will be used solely by the VA to inform future procurement decisions and will not be disclosed outside the government. Failure to provide all requested information will result in a non-responsive submission.
261-NETWORK Contract Office 21 (36C261)

POSTED

about 10 hours ago

DEADLINE

in 7 days
View Details