The City of Morgan Hill is planning to upgrade its existing Glen Ayre Hillside Water Reservoir by replacing the current 35-foot diameter, 100,000-gallon tank with a new 55-foot diameter tank capable of holding 250,000 gallons, while maintaining the same water level height. This substantial capacity increase necessitates expanding the existing utility easement to accommodate the larger footprint of the new structure. To ensure continuous water service during the transition, five temporary tanks, each with a 21,000-gallon capacity, will be installed on-site throughout construction. The project is part of ongoing infrastructure improvements in Morgan Hill, California, with all work localized to the 95037 zip code area. Project oversight is managed by David Gittleson, the Project Engineer, who serves as the primary point of contact for technical and operational inquiries, and Amberly Morgan, the Senior Environmental Planner, who handles environmental coordination. The project is forecasted for release in July 2026, with no formal solicitation number assigned yet, indicating it is in the pre-solicitation planning phase. The initiative reflects the city’s commitment to enhancing water storage capacity and reliability in alignment with regional infrastructure needs, while ensuring environmental and regulatory compliance during construction.

General Info

Morgan Hill to replace 100k-gallon reservoir with 250k-gallon tank, add five temporary tanks, expand easement, completion expected July 2026.

Agency

California → City of Morgan Hill

Place of Performance

Glen Ayre Drive, Morgan Hill, CA, 95037

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Get full access to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → City of Morgan Hill
Contacts2 people available
OfficeN/A
Organization / Agency
California → City of Morgan Hill
Office AddressN/A
Contacts
David GittlesonProject Engineer
Amberly MorganSr. Environmental Planner

Interested Companies (1)

ECORP Environmental ConsultingRocklin, CA

Full Description

Show more
The project will upgrade the existing tank (35-feet in diameter) with a capacity of 100,000 gallons. To increase the capacity to 250,000 gallons without affecting the water level height, the new tank will be designed to be approximately 55-feet in diameter. The new tank footprint will require an expansion of the existing utility easement. During construction, five 21,000 gallon temporary tanks will be placed onsite.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
26350 Lynchburg, VA - CSO 70 Sewer Improvements
Solicitation # 2027-027
Cleary Construction is soliciting quotations from certified Disadvantaged Business Enterprises for the City of Lynchburg CSO 70 Sewer Improvements project in Virginia, identified by solicitation number 2027-027. This opportunity is open to various small business set-asides, including SBA certified Veteran Owned, Service-Disabled Veteran Owned, Women-Owned, and HUBZone small businesses. Interested firms must submit their responses by December 4, 2026. The scope of work involves comprehensive sewer infrastructure improvements, including the open-cut installation of PVC and DIP sewer lines ranging from 6 to 30 inches in diameter. Key technical requirements include the installation of standard and doghouse manholes, interior drop assemblies, a CSO regulator fit out, and 24-inch diameter trenchless crossings with associated launch and receiving shafts. Additional project deliverables include the implementation and maintenance of a Stormwater Pollution Prevention Plan, geotechnical instrumentation and monitoring, and the maintenance of flows and bypass for all pipes and manholes during construction. General project requirements include clearing and grubbing of wooded areas, seeding, fine grading, and select tree removal. Due to the project location and nature, contractors must provide railroad insurance. The bid schedule further accounts for extra depth excavation and the abandonment of existing pipes and manholes. All inquiries and quotations should be directed to John Connelly at Cleary Construction.
Cleary Construction, Inc.

POSTED

about 5 hours ago

DEADLINE

in about 1 month
View Details
NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project, solicitation number SRP-W-134-0290, is a construction contract for the City of Belmont, North Carolina, with a project estimate of 16,690,000 dollars. The scope of work involves the installation of 16,435 linear feet of new 20-inch ductile iron force main and comprehensive upgrades to the Morgans Branch Pumping Station. Key deliverables include the construction of a new wet well and valve vault, the demolition of existing pumps and piping, and the delivery of a fully operating facility equipped with mechanical and electrical systems, a generator, odor control equipment, and stormwater facilities. The project also requires associated site work, including exploratory drilling, rock excavation, and grading. The contract is governed by EJCDC standard general and supplementary conditions, with technical specifications spanning divisions 00 through 44. Award will be granted to the responsible bidder submitting the lowest responsive bid, with evaluation based on qualifications, financial ability, and adherence to submission requirements. Bidders must provide a signed bid form, bid security, and mandatory MWBE documentation, including a Good Faith Efforts Form and Table A, to meet participation goals of 10.9 percent for EPA MBE and 10 percent for the State of North Carolina. Contract administration is managed by the City of Belmont with Willis Engineers serving as the project engineer. Payment is processed via Applications for Payment, with a 30-day payment term following the engineer's recommendation.
Don Moorhead Construction, Inc.

POSTED

about 5 hours ago

DEADLINE

in 11 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS