Coastal Storm Risk Management (CSRM) At Surf City, North Carolina - Industry Day
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
The Coastal Storm Risk Management project in Surf City, North Carolina, involves a comprehensive beach nourishment effort requiring the placement of 6,500,000 cubic yards of dune and berm fill across approximately 33,300 linear feet of beach. The scope of work includes dredging from an offshore borrow area near the south end of Topsail Island, transporting and shaping beach fill, conducting pre and post construction surveys, extending 40 existing walkover structures, and stabilizing 46 to 56 acres of new dunes. Contractors must utilize ocean certified hopper or pipeline dredges to complete the project. An Industry Day meeting is scheduled for September 15, 2026, at 11:00 AM EST via Microsoft Teams to discuss the requirements. Interested parties must RSVP to Rosalind Shoemaker and Jenifer Garland by 3:00 PM ET on September 11, 2026, and may request individual breakout sessions following the general meeting. This opportunity is managed by the Department of Defense under the W074 Endist Wilmington office.
General Info
Agency
NAICS
Place of Performance
NC, USASet-Aside
Documents
(0)AI Contract Breakdown
Uniform Contract FormatNo contract breakdown available.
Cannot generate Contract Breakdown because no documents were found from this contract's source.
Timeline
Response Deadline
Organization & Contact Information
Full Description
Special Notice: W912PM27BA001
Title: Industry Day for FY26/FY 27 Coastal Storm Risk Management Surf City, North Carolina
The Industry Day Meeting for the Coastal Storm Risk Management (CSRM) Surf City will occur on 15 September 2026 at 11:00 AM EST via Teams. The work consists of furnishing plant, labor, materials, and equipment to perform dredging, transporting, placing and shaping beach fill and performing all pre and post construction beach surveys. Approximately 1 borrow areas is available for the project and located offshore of Topsail Island Beaches at the south end of the island. The Surf City Coastal Storm Risk Management Project consists of placing 6,500,000 CY of Dune and Berm beach fill along approximately 33,300 LF of Surf City Beach. This project shall use either an ocean certified hopper and/or an ocean certified pipeline dredge. The project also consists of extending approximately 40 existing walkover structures in Surf City and the stabilization of approximately 46 to 56 acres of new dune.
In addition, breakout sessions will be provided with individual contractors following the group industry day meeting. Please indicate with your RSVP if you would like to request a breakout meeting.
Please RSVP no later than 3PM ET 11 September 2026 to both Ros Shoemaker and Jenifer Garland at Rosalind.m.shoemaker@usace.army.mil and jenifer.m.garland@usace.army.mil if you plan to attend the Industry Day and/or request a breakout session. A Teams calendar invite will be sent out to all RSVP’s.