The proposed project would include the repair and reconstruction of an eroded embankment and damaged culverts and headwall by the San Diego Unified Port District (District) along the Bayshore Bikeway adjacent to Pond 10A in the South San Diego Bay. The proposed project would be implemented as a hazard-abating effort to quickly address the failing infrastructure and increasing concerns towards public safety along the bike path due to the deteriorated state of the embankment adjacent to the damaged culverts where the bike path crosses a tidal channel. The proposed project is also a preventative effort for any further deterioration resulting from the additional anticipated extreme high tides (including King Tides) and storm surges anticipated to occur in the coming months.
In October 2026, separation of two (2) of the five (5) culvert joints was observed and reported. Consequently, the District is mobilizing to implement emergency repairs to quickly address the failing infrastructure. Work to complete the proposed project would primarily consist of five (5) components, and would specifically include the following:
1. Culvert slip line. Insertion of HDPE (high-density polyethylene geomembrane) liner (or similar) into the existing 42-inch RCP (reinforced concrete pipe) at the observed joint separation points. The annular space would be sealed and grouted, and the liner would be sized to keep the existing hydraulic opening and muted tidal exchange as close to that which is existing to the greatest extent feasible.
2. Headwall tiebacks. Installation of approximately six (6) corrosion-resistant tiebacks between the culvert openings using stainless steel (or similar corrosion-resistant material) housed in PVC (polyvinyl chloride) sleeves (or similar), anchored to each headwall with a corrosion-resistant anchoring system. Other methods to install the tiebacks which would require no excavation are also being explored.
3. Headwall bracing. Installation of corrosion-resistant bracing or angle irons to secure the southern headwall separated by cracks along its face.
4. Void filling and embankment repair. Filling of voids and fissures behind and around the southern headwall with grout, slurry or engineered fill, and rebuilding and compacting of the embankment.
5. Rock slope protection. Placement of new ¼- to ½-ton rock slope protection (RSP) in the scour area and at the southern end of the headwall on a bedding layer or geotextile. This would prevent further scour and ensure stabilization of the headwall. Any bike path pavement, shoulders, striping, fencing, and signs disturbed during the proposed work would be stabilized following its completion.
Prior to construction of the components described above, excavation of the area directly above the culverts would be conducted for investigative purposes to assess the full extent of the two (2) visibly damaged culverts, as well as assess the condition of the remaining three (3) culverts. The project site would be accessed from CA-75 and the staging area would be within the surrounding area adjacent to the west of the bike path to ensure minimal impact to public access. Access to the project site via the bike path and proposed work in tidal areas would be scheduled for during low tides. Construction of the proposed project may require intermittent partial closures of the bike path as necessary for specific work activities. Intermittent closures would last no more than a few hours at a time, and signs, traffic control, and flagger(s) would be present to warn and direct the public throughout the project site and maintain public access and use of the bike path during construction. Construction of the proposed project is anticipated to occur in Fall 2026 and would take approximately 15 days to complete, subject to tidal conditions.
Additionally, in August 2026, the District was notified of erosion along the southern edge of the bike path adjacent to Pond 10A due to overtopping and flooding during high tides. Continuous overtopping and the subsequent erosion has created approximately 8- to 12-inch drop-offs from the bike path to the surrounding ground and are beginning to undercut the bike path; these drop-offs were observed along an approximately 300-foot stretch of the southern edge of the bike path and pose a significant safety issue to users of the bike path. To prevent any further erosion and address the increasing concerns towards public safety, the District is proposing an approximately 4-foot-wide tapered shoulder made of asphalt along the stretch of bike path facing extensive erosion as a temporary solution for the upcoming El Niño season. The tapered shoulder would connect the existing height of the bike path to the surrounding ground, and would not extend past the existing fence that borders the bike path and wildlife refuge. This work is anticipated to occur concurrently with the culvert repairs, or shortly after in coming months.
Due to its nature and limited scope, construction of the proposed project would generate a minor amount of vehicle trips and would require limited use of equipment. Therefore, impacts related to air quality, greenhouse gas emissions, and transportation and traffic are not anticipated to occur. Furthermore, the District would be responsible for complying with all applicable federal, state, and local laws regarding construction demolition debris, hazards and hazardous materials, and stormwater.