This Solicitation opportunity from Pennsylvania was posted on January 5, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
The contract entails the demolition and removal of approximately 98 linear feet of an existing stone retaining wall and the subsequent construction of a precast modular block gravity retaining wall. Additionally, it includes the reconstruction of about 25 linear feet of the existing stone retaining wall. The work is scoped within Delaware County, Pennsylvania, under the Township of Haverford jurisdiction, and is managed by the Delaware County agency in cooperation with PennDOT. The solicitation, posted in June 2026, seeks qualified contractors with demonstrated financial stability, technical expertise, and compliance with labor and safety standards, including prevailing wage laws and OSHA training requirements. The project emphasizes the use of apprenticeship programs and mandates that contractors provide adequate craft labor personnel certified in OSHA 10-hour training, with a prime contractor representative holding OSHA 30-hour certification.
This construction contract features strict compliance provisions addressing nondiscrimination, contractor integrity, the Americans with Disabilities Act, and contractor responsibility requirements, as detailed in exhibits serving as required Commonwealth contract provisions. There is no formal FAR clause numbering; instead, these provisions include administrative placeholders for signatures and dates to ensure adherence to ethical business conduct and equal opportunity standards. The award process utilizes a Lowest Price Technically Acceptable (LPTA) methodology, requiring responsible contractors to meet all certification, experience, and regulatory compliance standards. Payments are processed via ACH through PennDOT's administrative channels, and inspection as well as acceptance occur on-site, adhering to specific PennDOT publications and Pennsylvania regulatory codes. No packaging, marking, or security clearance stipulations apply, and bid submissions are managed through the PENNBID electronic platform with no formal evaluation weighting beyond responsibility and price compliance. The contract includes provisions for organizational conflict of interest disclosures and requires notification within seven days of any material changes affecting contractor eligibility.
General Info
Demolition and reconstruction of retaining walls in Delaware County with strict safety and compliance requirements.
PDF, High priority: read this firstspecial-provisions
HighAI Summary for 01001 Special Provisions Addendum No. 1: This document is Addendum No. 1 to Section 01001 Special Provisions for a project involving installation of electrical conduits, wires, and solar panels on the PV racking system at the Haverford Township building. It outlines general requirements including qualifications for bidders, storage and site restrictions, pedestrian accommodations and safety measures, disposal of materials, nuisance ordinance compliance, public utilities coordination, dust control procedures, and consequences for failure to perform work according to specifications. The document also references compliance with the Public Works Employment Verification Act (Act 127 of 2012). It serves as a critical guide for contractors preparing bids and executing the contract work in full compliance with the stipulated conditions.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for 01340 Shop Drawings, Product Data and Samples Addendum No. 1 - Nondiscrimination Clause: This document is Addendum No. 1 to the 01340 Shop Drawings, Product Data and Samples contract section. It details the Nondiscrimination/Sexual Harassment Clause applicable to the grantee, subgrantees, contractors, and subcontractors. The clause mandates non-discrimination in hiring and employment practices based on race, gender, creed, color, sexual orientation, gender identity or expression, and compliance with the Pennsylvania Human Relations Act and federal laws. It requires written policies on nondiscrimination and sexual harassment, posting of the clause, compliance with EEO-1 reporting, and ongoing obligations throughout the grant term. Violations may result in contract termination, forfeiture of funds, and debarment actions by the Commonwealth.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Addendum No 1 2025-07-30 - Haverford Township Purchasing System Ordinance: This document is Addendum No 1 dated July 30, 2025, amending the purchasing system regulations for Haverford Township. It establishes the purchasing system framework, roles of the Finance Director, Township Manager, and department heads, and outlines competitive bidding rules. Key provisions include the establishment of a responsible bidders list, disqualification criteria, invitation to bid procedures, and responsible contractor bidding requirements for public works projects valued at $250,000 or more. The amendment emphasizes contractor qualifications, past performance, compliance with apprenticeship training programs, and prevailing wage requirements. It supplements existing contractor qualification standards to ensure responsible, qualified firms perform public construction and maintenance contracts.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Addendum No. 1 for Darby Creek Trail Extension Contract REC-34: Addendum No. 1 issued on November 10, 2025, for the Haverford Township Darby Creek Trail Extension and Burmont and Glendale Roads Realignment Contract No. REC-34. This addendum provides supplemental data amending the contract documents, including revisions to the Table of Contents, Form of Bid, and Construction Specifications (Section 01025). It also includes updates to contract drawings with detailed changes to pedestrian trail profiles and bridge details. Bidders are instructed to consider these amendments in their proposals and acknowledge them accordingly.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Addendum No. 1 for Darby Creek Trail Southern Extension - Phase III Contract REC-35: Addendum No. 1 issued on November 13, 2025, for the Darby Creek Trail Southern Extension - Phase III Contract No. REC-35. This amendment revises contract documents including the Table of Contents, Form of Bid, Special Conditions, and Construction Specifications. Key updates include corrections to project naming, bid item modifications and renumbering, insurance requirements including Contractors Pollution Liability Insurance, and detailed changes to measurement and payment items. A new section on Concrete (03301) is added. Contract drawings are updated to reflect work restrictions within waterways until after June 1, 2026, and other site plan revisions. Bidders must consider these changes in their proposals and acknowledge them accordingly.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Addendum No. 1 for Haverford Township Fuel Tank Replacement Contract MY-8: Addendum No. 1 issued May 19, 2026, for the Haverford Township Public Works Complex Fuel Tank Replacement Contract No. MY-8. This amendment revises contract documents including the Form of Bid and Form of Agreement to update liquidated damages to $850.00 per day and project duration to 220 days. Construction specifications are updated with revised special provisions and a change from fiberglass to steel storage tanks. Contract drawings are revised to reflect these changes, including updates to site plans and tank details. Bidders must acknowledge this addendum in their proposals and consider these modifications in their bids.
PDF
PDF, High priority: read this firstwage-determination
HighAI Summary for Addendum No 1 - Prevailing Wages for Public Works Complex Fuel Tank Replacement: Addendum No 1 dated around 2026 provides prevailing wage rates for the Public Works Complex Fuel Tank Replacement project in Haverford Township, Delaware County. It includes detailed hourly rates, fringe benefits, and total compensation for various labor classifications such as Boilermakers, Carpenters, Electricians, and Laborers. The document is issued by the Bureau of Labor Law Compliance and covers effective dates primarily in 2024-2026. It supports compliance with wage requirements for the project awarded by Pennoni Associates.
PDF
PDF, High priority: read this firstwage-determination
HighAI Summary for Addendum No 2 2025-08-04 Prevailing Wages for Township Building Solar Project: This document is Addendum No 2 dated August 4, 2025, providing prevailing wage rates for the Township Building Solar project in Haverford Township, Montgomery County. It includes detailed hourly rates, fringe benefits, and total compensation for various labor classifications such as Asbestos & Insulation Workers, Boilermakers, Bricklayers, Carpenters, Electricians, and others. The wage rates are effective from various dates primarily in 2024 and 2025, with some extending to 2026. The document is issued by the Bureau of Labor Law Compliance and is associated with project serial number 25-06750. It serves as a critical reference for compliance with labor wage standards on this building project.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Addendum No. 2 for Darby Creek Trail Extension Contract REC-34: This document is Addendum No. 2 issued on November 14, 2025, for the Darby Creek Trail Extension Burmont and Glendale Roads Realignment project, Contract No. REC-34. It provides supplemental data amending the contract documents, specifically modifications to the Form of Bid section. Key changes include the removal and replacement of certain asphalt mixture design items with a plain cement concrete base course and an updated superpave asphalt mixture design for the wearing course. Revised bid pages C-4 and C-5 are enclosed. The addendum also includes informational bid sheets with item descriptions and quantities for various construction tasks related to the project.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Addendum No. 2 for Haverford Township Fuel Tank Replacement MY-8: Addendum No. 2 issued May 21, 2026, for the Haverford Township Public Works Complex Fuel Tank Replacement Contract No. MY-8. This document amends the contract documents by revising Section 01025 - Measurement and Payment, removing certain electrical components from the contract scope, and providing revised contract drawings (E1003, E1004, E1005). It details measurement and payment criteria, defect assessment, and non-payment conditions for rejected work. The addendum includes specific changes to payment items such as removal and replacement of the fueling system and rock excavation, outlining the scope and payment methods for these items.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Addendum No. 3 for Darby Creek Trail Extension Contract REC-34: Addendum No. 3 dated November 19, 2025, for the Darby Creek Trail Extension Burmont and Glendale Roads Realignment Contract No. REC-34. This document provides supplemental data amending the contract documents, including revisions to the Form of Bid such as quantity adjustments for Plain Cement Concrete Base Course and additions of new bid items like Relocate Mailbox and Remove Post Mounted Signs Types B and F. Revised bid pages C-4, C-8, C-9, and C-10 are enclosed. Bidders must consider these changes in their proposals and acknowledge the addendum accordingly.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Addendum No. 4 for Haverford Township Darby Creek Trail Extension Contract REC-34: Addendum No. 4 issued on November 21, 2025, for the Haverford Township Darby Creek Trail Extension and Burmont and Glendale Roads Realignment Contract No. REC-34. This addendum provides supplemental data amending the contract documents, specifically revising Section C - Form of Bid, Page C-2. The revision removes certain items from the list of electronic copies required to be uploaded with the bid and clarifies which items are intended to inform contractors of bidding requirements, funding, and permit guidelines. Bidders must consider this amendment in their proposal preparation and acknowledge it accordingly.
PDF
PDF, High priority: read this firstifb
HighAI Summary for Brookline Park Phase 4 Sagamore Road Parking Contract REC-33: This document is an Invitation for Bids (IFB) for the Brookline Park - Phase 4 Sagamore Road Parking project under Contract No. REC-33 for Haverford Township, Delaware County, Pennsylvania. Dated May 2026, it includes advertisement, instructions to bidders, forms of bid and bonds, general and special conditions, construction specifications, form of agreement, contract bonds, and related documents. The project involves site grading, ADA-compliant sidewalks, ADA-accessible parking spaces, stormwater installation, and restoration work. Bids are to be submitted electronically via the PennBID Program by May 27, 2026, with a required bid bond of 10%. The document emphasizes compliance with responsible contractor requirements, prevailing wage rates, and non-discrimination laws. It also outlines submission procedures, bid security, and the owner's rights regarding bid acceptance.
PDF
PDF, High priority: read this firstcontract-document
HighAI Summary for Contract Drawings - Electrical Conduits Installation Pricing: This document titled 'Contract Drawings' includes detailed pricing information for the installation of electrical conduits and wires for solar panels on the PV racking system. It features a pricing section with unit prices and total costs, highlighting the lowest bid and selected items. The document serves as a contract-related pricing schedule for the base bid, dated as per the original filename, and is critical for understanding cost allocations in the contract.
PDF
PDF, High priority: read this first1 page · specifications
HighAI Summary for Contract Drawing SS-51: Sanitary Sewer Lining - Various Areas: Technical drawing and specifications document for sanitary sewer lining projects in Haverford Township, PA. It includes a location plan, work summary, construction notes, general notes, and utility coordination requirements. The document specifies requirements for bypass pumping, traffic control, and compliance with PA Act 287 regarding underground utility line protection.
PDF
PDF, High priority: read this firstrfb
HighAI Summary for Contract MY-8 Public Works Complex Fuel Tank Replacement: This document is the solicitation package for Contract No. MY-8 issued by Haverford Township, Delaware County, Pennsylvania, for the Public Works Complex Fuel Tank Replacement project. Dated May 2026, it includes the advertisement, instructions to bidders, forms of bid and bonds, general and special conditions, construction specifications, and contract drawings. The solicitation invites sealed bids via the PennBID Program until May 27, 2026, with a pre-bid meeting scheduled for May 12, 2026. The project scope involves removal and replacement of vehicle fueling systems with new tanks, dispensers, piping, wiring, and controls. The document outlines bidder responsibilities, submission requirements, bid guaranty, and contract conditions, making it a primary solicitation for construction services.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for Contract No. SS-52 Merion Golf Course Sewer Lining Contract Drawings: Technical specifications and general notes for the Merion Golf Course sewer lining project. The document details access restrictions on private property, requirements for 10-inch PVC pipe lining, bypass pumping protocols, and the mandatory use of Duradek ground protection matting to protect the site.
PDF
PDF, High priority: read this firstwage-determination
HighAI Summary for Contract Prevailing Wage Rates REC-34 for Burmont/Glendale Road Intersection Improvement: This document is a prevailing wage determination for the project REC-34 involving intersection improvements at Burmont/Glendale Road (SR 1006) and Burmont Road (SR 2007) in Haverford Township, Delaware County. The contract award date is 12/8/2025, with the determination date on 10/20/2025. It includes detailed hourly wage rates and fringe benefits for various labor classifications such as carpenters, electricians, laborers, and others, effective from various dates primarily in 2024 and 2025. The document is issued by the Bureau of Labor Law Compliance and is critical for contractors to comply with wage requirements on this highway construction project.
PDF
PDF, High priority: read this firstrfb
HighAI Summary for Contract RP-2A Paving Modifications Various Locations: This document is the solicitation package for Contract RP-2A issued by Haverford Township, Delaware County, Pennsylvania, for paving modifications at various locations. It includes the advertisement, instructions to bidders, forms of bid and bonds, general and special conditions, construction specifications, and contract drawings. The solicitation requires sealed bids to be submitted via the PennBID Program by July 3, 2025. Key contents include bidder responsibilities, bid submission instructions, bid guaranty requirements, and compliance with the Township's Responsible Contractor Bidding Requirements. The document also outlines contract terms, insurance, wage rates, and project scope involving pavement reconstruction, base repair, and mill/overlay work.
PDF
PDF, High priority: read this firstspecial-provisions
HighAI Summary for Contract Section G No. MY-8 - Special Provisions for Fueling System Replacement: This document, titled Contract Section G No. MY-8, outlines the special provisions for a project involving the removal of an existing fueling system and installation of a new system at the Township's Public Works Complex, 1 Hilltop Road, Havertown, PA. It includes the scope of work, bidder qualifications, project location, working hours, and a detailed anticipated schedule for contract award, shop drawings submission, tank ordering, and installation. The document also covers coordination requirements with the Township, installation procedures, contractor safety obligations, and existing site conditions. The provisions emphasize compliance with PaDEP certifications, OSHA standards, and manufacturer instructions, with a focus on soil testing and potential remediation. The document is critical for bidders to prepare responsive proposals and understand project execution requirements.
PDF
PDF, High priority: read this firstcontract-document
HighAI Summary for Contract Sections G No. Rec-34 - Special Provisions for Burmont/Glendale Road Intersection Improvement: This contract document, titled Contract Sections G No. Rec-34, outlines the special provisions for a construction project improving the intersection at Burmont/Glendale Road (SR 1006 and SR 2007). It includes installation of a 10-foot-wide bituminous trail and a prefabricated pedestrian bridge. The document details work within the park and roadway, emphasizing safety, environmental compliance, and access restrictions. It mandates contractor prequalification by PennDOT, adherence to erosion control and permit conditions, and specifies responsible contractor bidding requirements for projects valued at $250,000 or more. Funding is provided by the PennDOT Multimodal Transportation Fund, with nondiscrimination and contractor integrity provisions included. The document is critical for understanding project scope, contractor qualifications, and compliance requirements.
PDF
PDF, High priority: read this firstcontract-document
HighAI Summary for Contract Sections K-R No. REC 34 - Public Works Employment and Nondiscrimination Clauses: This document titled 'Contract Sections K-R No. REC 34' includes key contract clauses related to public works employment verification and nondiscrimination/sexual harassment. It affirms compliance with the Public Works Employment Verification Act through the federal E-Verify Program and outlines contractor obligations for verifying employment eligibility. The nondiscrimination clause prohibits discrimination based on race, gender, creed, color, sexual orientation, gender identity or expression, and mandates a written policy on nondiscrimination and sexual harassment. It also requires compliance with federal and state laws, filing of EEO-1 reports, and allows contract termination for violations. Additionally, the document includes provisions on the establishment of a purchasing system by the Township Manager and department heads' responsibilities for purchases.
PDF
PDF, High priority: read this firstrfp
HighAI Summary for Darby Creek Trail Extension Contract No. REC-34 Solicitation: This document is the solicitation package for the Darby Creek Trail Extension and Burmont and Glendale Roads Realignment, Contract No. REC-34, issued by Haverford Township, Delaware County, Pennsylvania. It includes advertisement, instructions to bidders, forms of bid and bonds, general and special conditions, construction specifications, and contract drawings. The solicitation invites sealed bids via the PennBID Program until November 25, 2025, for construction work including intersection improvements, trail installation, and pedestrian bridge furnishing. The document outlines bidder responsibilities, submission requirements, bonding, wage rates, and compliance with PennDOT and local ordinances. A pre-bid meeting is scheduled for November 4, 2025.
PDF
PDF, High priority: read this first4 pages · specifications
HighAI Summary for Fire Tower Parking Lot Retaining Wall - Contract Drawings: Technical drawing set (Sheets 1-4) dated 6/4/2026 prepared by Pennoni Associates Inc. for the Fire Tower Parking Lot Retaining Wall project in Haverford Township, PA. The document includes project notes, a site plan, and retaining wall notes, specifying that all dimensions must be verified by the contractor.
PDF
PDF, High priority: read this first115 pages · ifb
HighAI Summary for Fire Tower Parking Lot Retaining Wall Contract No MY-9: This document is the Invitation for Bids (IFB) for the Fire Tower Parking Lot Retaining Wall project, Contract No. MY-9, issued by Haverford Township, Delaware County, Pennsylvania. Dated July 2026 and prepared by Pennoni Associates Inc., it includes advertisement, instructions to bidders, forms of bid and bonds, general and special conditions, construction specifications, and contract drawings. The project involves demolition and removal of an existing stone retaining wall and construction of a precast modular block gravity retaining wall. Bids are to be submitted electronically via the PennBID program by July 7, 2026, with a required bid bond or certified check of at least 10% of the bid amount. The document outlines bidder responsibilities, submission procedures, bid guaranty requirements, and conditions for bid acceptance and contract award.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Haverford Township Merion Golf Course Sewer Lining Addendum No. 1: Issued October 27, 2026, for Contract No. SS-52, this addendum modifies the special conditions and contract information for the Merion Golf Course Sewer Lining project. Key changes include updating Owner Protective Coverages to include Merion Golf Club, introducing a mandatory $3,000,000 Pollution Liability Insurance requirement for sewage handling, and adding a new sanitary sewer inspection video to the contract information list. The document also includes detailed specifications for contract security bonds and insurance requirements.
PDF
PDF, High priority: read this firstifb
HighAI Summary for Merion Golf Course Sewer Lining Contract No. SS-52: An invitation for bid (IFB) issued by Haverford Township, Delaware County, PA, for the lining of approximately 1,250 linear feet of 10-inch vitrified clay sanitary sewer mains at the Merion Golf Club. The document, dated July 2026, includes the advertisement, instructions to bidders, general and special conditions, and construction specifications. Bids are due by October 30, 2026, via the PennBID program.
PDF
PDF, High priority: read this firstplan-set
HighAI Summary for Pavement Modifications Plan Set - Haverford Township: This document is a plan set for pavement modifications at various locations in Haverford, Pennsylvania, prepared by Pennon Associates and dated May 21, 2025. It includes detailed notes on work standards, traffic management, paving specifications, and sequencing requirements. The plan mandates compliance with PENNDOT standards, specifies work hours, traffic lane maintenance, signage, and flagger requirements. It outlines paving thickness, drainage, and restoration responsibilities, as well as coordination with property owners and township representatives. The document also provides technical details on taper lengths, channelizing device spacing, and asphalt mixture design, ensuring proper execution and safety during construction.
XLSX
XLSX, High priority: read this firstpricing-section
HighAI Summary for Pricing Section BT-04IJ: This document is the Pricing Section BT-04IJ for a construction-related procurement. It includes detailed pricing data for various bid items such as bituminous leveling course, overlays, variable depth mill, base repair allocation, and miscellaneous excavation/backfill across multiple areas. The sheet compares unit prices and total costs from different vendors, highlighting the lowest prices and selected items. The document is essential for evaluating bids and determining contract awards based on cost.
XLSX
XLSX, High priority: read this firstpricing-section
HighAI Summary for Pricing Section BT-39AH: This document is the Pricing Section BT-39AH for a procurement, containing detailed bid pricing information from multiple vendors. It includes a legend explaining color codes for lowest price and selected items, and a detailed table listing various bid items such as installation, grading, and excavation with unit prices and total costs from different contractors. The document is structured to compare vendor pricing for contract evaluation purposes.
XLSX
XLSX, High priority: read this firstpricing-section
HighAI Summary for Pricing Section BT-59EX 1764083273.5707476: This document is a pricing section spreadsheet for contract BT-59EX, containing detailed unit prices and total costs for various construction items and services. It includes multiple bidders' pricing for items such as temporary controls, grading modification, site clearing, installation of bituminous trail, prefabricated bridge, restoration, excavation, concrete base course, asphalt mixture, drainage, and other construction-related tasks. The spreadsheet lists quantities, units of measure, item numbers, and cost breakdowns for each bidder, facilitating cost comparison and evaluation for the procurement process.
PDF
PDF, High priority: read this firstaddendum
HighAI Summary for Public Works Employment Verification Form Addendum No. 1: This document is an addendum titled 'Public Works Employment Verification Form' related to a public works contract. It affirms compliance with the Public Works Employment Verification Act through the federal E-Verify Program, ensuring all employees hired after January 1, 2013, are authorized to work in the U.S. It requires contractors and subcontractors to verify employment eligibility within five business days of hire and maintain documentation for audits. The form must be signed by an authorized company representative, attesting to the truthfulness of the information, with legal sanctions for false submissions.
PDF
PDF, High priority: read this firstifb
HighAI Summary for Sanitary Sewer Lining Various Areas Contract SS-51: This document is the Invitation for Bids (IFB) for the Sanitary Sewer Lining project in various areas of Haverford Township, Delaware County, Pennsylvania, Contract No. SS-51. Dated July 2026, it includes advertisement, instructions to bidders, forms of bid and bonds, general and special conditions, construction specifications, and contract drawings. Bids are to be submitted electronically via the PennBID program by August 3, 2026, with a required bid bond of 10%. The project involves lining vitrified clay sanitary sewers in residential areas. The document outlines bidder responsibilities, submission procedures, addenda acknowledgment, and bid guaranty requirements, emphasizing compliance with the Township's Responsible Contractor Bidding Requirements.
PDF
PDF, Low prioritybid-tabulation
LowAI Summary for BID TAB (HAVTT13250): The document is a bid tabulation file identified as HAVTT13250, used to record and compare bids received for a procurement action.
PDF
PDF, Low prioritycontract-drawing
LowAI Summary for Contract Drawing REC-33 Brookline Park Phase 4 Sagamore Road Parking: This document is a contract drawing for the Brookline Park Phase 4 Sagamore Road Parking project under contract number REC-33 for the Township of Haverford. It includes legends for existing and proposed features, scale information, and general notes on grade adjustments and precast concrete grade adjustment rings. The document is produced by Pennoni Associates Inc. and provides technical details relevant to the construction and adjustment of grades for the project site.
PDF
PDF, Low prioritycontract-document
LowAI Summary for Contract General Conditions: This document titled 'Contract General Conditions' appears to be a contract-related document containing general symbols and notes. It includes references to a project (HAWT20062) dated 07/08/2025 and mentions components related to the IQ Gateway Commercial solar energy system. The content primarily consists of general sheet notes and symbols, without detailed technical specifications or solicitation instructions.
AI Contract Breakdown
Uniform Contract Format
Sign up to view the full breakdown with detailed analysis of each section.
Timeline
1 update
PhaseAwarded
Posted
Solicitation
Notice updated
Solicitation number changed from Township of Haverford, Delaware County to 216089. The notice description changed.
Awarded
Contract was awarded
Submission Closed
Find active opportunities like this
Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.
Ref. #: Township of Haverford, Delaware County TOWNSHIP OF HAVERFORD
1014 Darby Road
Havertown, PA 19083 Sealed bids will be received by Haverford Township via the PennBID Program (https://pennbid.bonfirehub.com) until 10:00 o'clock PM , prevailing time, on the 2nd day of February 2026 , at which time and place they will be publicly read for: HAVERFORD COMMUNITY RECREATION AND ENVIRONMENTAL CENTER DECK REPLACEMENT
CONTRACT NO. REC-36 All documents and solicitation details are available at no cost at PennBID (https://pennbid.procureware.com/). Each bid must be accompanied by a certified check or bid bond payable to the Owner in an amount of not less than ten percent (10%) of the bid or bids. Only bonds from companies licensed to do business in the State where the Owner is located will be accepted and the bond shall so state same. Bids must be submitted unconditionally. No bidder may withdraw bid within SIXTY (60) days after the scheduled closing time for receipt of bids. The Owner reserves the right to waive any informalities or to reject any or all bids. This project is subject to the Township’s “Responsible Contractor Bidding Requirements.” These requirements can be found on the Township website at https://ecode360.com/14964254. The project involves the removal and replacement of a 1,620 square-foot elevated exterior wood deck attached to the building. A Pre-Bid meeting will be held on Friday, January 16th, 2026, at 10:00 AM, at the parking lot of the CREC, 9000 Parkview Dr, Haverford, PA 19041
More opportunities from Pennsylvania → Delaware County