The contract involves repairing and improving the damaged beachfront armoring at three locations—Heron Street, Egret Avenue, and Mallard Street—in Wilbur by the Sea, Volusia County, Florida, following damage caused by Hurricanes Ian and Nicole. The project scope includes demolition and removal of the existing structures, construction of new seawalls, grading, compaction, and the building of timber dune walkovers to restore public beach access. The work must be carefully coordinated due to limited space for materials and equipment, proximity to private properties, and the presence of a heavily trafficked road nearby.
This solicitation, titled "Heron Street, Egret Avenue, and Mallard Street Seawall Replacement Project," was posted on January 20, 2026, with a response deadline of February 19, 2026. It is managed by the Coastal agency under the jurisdiction of Volusia County. Key contacts for the project include Wes Fontaine, Construction Manager, and Inga Fegley, Senior Procurement Analyst. The project is based out of DeLand, Florida, and emphasizes careful logistical planning to accommodate site constraints while ensuring effective restoration and enhancement of beach access and shoreline protection.
General Info
Repair and replace seawalls at three Wilbur by the Sea locations post-Hurricanes Ian and Nicole.
XLSX, High priority: read this first1 page · bid-schedule
HighAI Summary for 2025-10-10 3 Birds Bid Schedule: This document is a bid schedule dated October 10, 2025, for the Replacement Seawall and Beach Access Stairs projects at three locations in Volusia County: Mallard Street Beach Access, Egret Ave Beach Access, and Heron Beach Access. It includes itemized bid tabulations with descriptions, quantities, and units for various construction tasks such as mobilization, demolition, sand fill, seawall construction, concrete work, aluminum guiderail installation, dune planting, as-built survey, and site restoration. The schedule is intended to support the bidding process by providing detailed cost breakdowns for each project component.
PDF
PDF, High priority: read this first14 pages · technical-specifications
HighAI Summary for 2025-10-10 Egret Avenue Post Hurricane Nicole Repairs Technical Specifications: This document dated 07/21/2025 provides detailed technical specifications for the Egret Avenue Post Hurricane Nicole Repairs project in Volusia County, Florida. It outlines the scope of work including demolition of damaged infrastructure and construction of replacement infrastructure such as a concrete sheet pile seawall, concrete walkway, wooden beach access stairs, dune plantings, and ancillary site improvements. The document includes requirements for permit compliance, pre-construction meetings, staking, inspection notifications, construction access, public safety, erosion control, and avoidance of protected species. It serves as a critical guide for contractors to ensure compliance with environmental and safety regulations and proper execution of the project.
PDF
PDF, High priority: read this first14 pages · technical-specifications
HighAI Summary for 2025-10-10 Heron Street Post Hurricane Nicole Repairs Technical Specifications: This document contains the Technical Specifications for the Heron Street Post Hurricane Nicole Repairs project in Volusia County, Florida, dated 07/21/2025. It details the scope of work including demolition and removal of damaged infrastructure and construction of replacement infrastructure such as a concrete sheet pile seawall, concrete walkway, wooden beach access stairs, dune plantings, and ancillary site improvements. The specifications include permit compliance requirements, pre-construction meeting protocols, staking and inspection notifications, construction access and staging areas, public safety measures, and erosion and water pollution control. The document emphasizes adherence to permits, safety, and environmental protection standards throughout the construction process.
PDF
PDF, High priority: read this first13 pages · technical-specifications
HighAI Summary for 2025-10-10 Mallard Street Post Hurricane Nicole Repairs Technical Specifications: This document dated 07/21/2025 provides detailed technical specifications for the Mallard Street Post Hurricane Nicole Repairs project in Volusia County, Florida. It outlines the scope of work including demolition of damaged infrastructure and construction of replacement infrastructure such as a concrete sheet pile seawall, concrete walkway, wooden beach access stairs, dune plantings, and ancillary site improvements. The document specifies permit compliance requirements, pre-construction meeting protocols, staking and inspection notifications, construction access, public safety measures, erosion control, and avoidance of protected species and benthic resources. It serves as a critical guide for contractors to ensure compliance with environmental and safety regulations and proper execution of the construction work.
PDF
PDF, High priority: read this first2 pages · geotechnical-report
HighAI Summary for Egret Avenue Beach Access Geotechnical Data Report: This document is a geotechnical data report prepared by Bechtol Engineering and Testing, Inc. for the Egret Avenue Beach Access project in Port Orange, Volusia County, Florida. Dated September 27, 2024, the report presents the results of a Standard Penetration Test boring to a depth of 40 feet to evaluate subsurface soil characteristics. It includes soil profiles, a boring location plan, and suggested soil parameters such as unit weight, friction angle, earth pressure coefficients, cohesion, and modulus of subgrade. The data is intended to assist in the design of a replacement boardwalk landing and sheet pile bulkhead. The report is signed and sealed by a licensed professional engineer.
PDF
PDF, High priority: read this first15 pages · drawings
HighAI Summary for EGRET AVENUE POST HURRICANE NICOLE REPAIRS Drawings: This document contains engineering drawings for the EGRET AVENUE POST HURRICANE NICOLE REPAIRS project in Volusia County, Florida. It includes a cover sheet, location map, staging area map, existing conditions, erosion control plan, demolition plan, site plan, grading plan, paving, drainage cross-sections, and detailed construction drawings for seawalls, beach access stairs, and other infrastructure. The drawings are dated 08/25/2025 and prepared by Coastal Tech with survey data from Sliger & Associates, Inc. The project involves demolition and replacement of damaged infrastructure including boardwalks, sidewalks, seawalls, and dune plantings. The work is to be performed within the Mallard Street right-of-way and complies with Florida Department of Environmental Protection permits and regulations.
PDF
PDF, High priority: read this first2 pages · insurance-requirements
HighAI Summary for Exhibit A - Insurance Requirements 26-B-38IF: This document outlines the insurance requirements for contract 26-B-38IF, specifying types and coverage limits. It includes Workers Compensation with Florida statutory coverage and waiver of subrogation, Commercial General Liability with specified occurrence and aggregate limits, Auto Liability with combined single limit, Excess Liability, Contractors Pollution Liability, and Builders Risk or Installation Floater insurance. The County of Volusia must be named as additional insured and certificate holder, with a 30-day cancellation notice required. The document ensures contractors maintain adequate insurance protections for the County.
PDF
PDF, High priority: read this firstconstruction-plans
HighAI Summary for Exhibit D - Construction Plans 26-B-38IF - Mallard Street Post Hurricane Nicole Repairs: This document contains the construction plans for the Mallard Street Post Hurricane Nicole Repairs project in Volusia County, Florida. It includes a sheet list table detailing various plans such as existing conditions, erosion control, demolition, site plan, grading, paving, drainage, seawall details, and miscellaneous details. General notes specify the scope of work including removal of damaged infrastructure and construction of replacement infrastructure like concrete sheet-pile seawall, concrete walkway, beach access stairs, and site improvements. The work is confined to the Mallard Street right of way and must comply with permits from the Florida Department of Environmental Protection and other regulatory requirements. The document references surveys and engineering details relevant to the project.
PDF
PDF, High priority: read this first41 pages · technical-specifications
HighAI Summary for Exhibit E - Technical Specifications 26-B-38IF for Heron Street Repairs: This document titled 'Technical Specifications' dated 07/21/2025 details the construction work for post-Hurricane Nicole repairs at Heron Street, Egret Avenue, and Mallard Street in Volusia County, Florida. It outlines demolition and removal of damaged infrastructure and construction of replacement infrastructure including a concrete sheet pile seawall, concrete walkway, wooden beach access stairs, dune plantings, and ancillary site improvements. The document specifies permit compliance requirements, pre-construction meeting protocols, staking, inspection notifications, construction access, public safety measures, erosion and water pollution control, and avoidance of protected species. It serves as a critical guide for contractors to ensure compliance with engineering, environmental, and safety standards during the project.
PDF
PDF, High priority: read this first4 pages · procedure
HighAI Summary for Exhibit F - Sales Tax Exemption Procedure 26-B-38IF: This document titled 'Sales Tax Exemption Procedure for Construction Management Projects' outlines the procedure for the County of Volusia to utilize a Consumer's Certificate of Exemption issued by the State of Florida Department of Revenue. It details the process for exempting the County from Florida sales and use tax on various purchases related to construction projects, specifically the Heron Street, Egret Street, and Mallard Avenue Seawall Replacement Project. The document includes definitions of key terms, a step-by-step flow of documents from requisition to direct payment, and responsibilities of both the County and the Prime Contractor. It ensures compliance with Florida Administrative Code Rule 12A-1.094 and provides instructions for submitting requisitions, processing purchase orders, and handling invoices to achieve sales tax savings.
XLSX
XLSX, High priority: read this first1 page · bid-price-sheet
HighAI Summary for Exhibit G - Bid Price Sheet 26-B-38IF: This document is a bid price sheet for the Heron Street, Egret Avenue, and Mallard Street Beach Access Seawall Replacement and Beach Access Stairs project. It lists itemized costs for various construction activities such as mobilization, demolition, sand fill, seawall construction, concrete work, aluminum guiderail installation, dune planting, as-built survey, and site restoration. Quantities and units are provided for each item, but all prices are currently zero. The total bid price will be determined based on the combined pricing submitted for the three locations. The document serves as a critical component for evaluating bids and awarding the contract based on the lowest responsive and responsible bidder.
PDF
PDF, High priority: read this firstgeotechnical-report
HighAI Summary for Exhibit H - Geotechnical Data for 26-B-38IF Heron, Egret, Mallard Streets: This document is a geotechnical report prepared by Bechtol Engineering and Testing, Inc. dated September 27, 2024. It provides geotechnical data for three beach access parcels in Port Orange, Volusia County, Florida: Heron Street, Egret Avenue, and Mallard Street. The report includes results from Standard Penetration Test (SPT) borings to a depth of 40 feet, soil profiles, and suggested soil parameters such as unit weight, friction angle, earth pressure coefficients, cohesion, and modulus of subgrade. The data is intended to support the design of replacement boardwalk landings and sheet pile bulkheads by others. The report is signed and sealed by a licensed Professional Engineer.
PDF
PDF, High priority: read this first11 pages · contract-provisions
HighAI Summary for Exhibit J - Federal Contract Provisions (FEMA) 26-B-38IF: This document titled 'Federal Contract Provisions' outlines the contractor's obligations to comply with federal requirements, specifically related to Equal Employment Opportunity and the Davis-Bacon Act for construction work under FEMA and other federal grant programs. It includes detailed clauses on nondiscrimination, affirmative action, compliance with Executive Order 11246, and enforcement measures. The provisions apply to contractors and subcontractors involved in federally assisted construction projects, emphasizing compliance, reporting, and potential sanctions for violations. The document is a critical part of the contract ensuring adherence to federal labor and employment standards.
PDF
PDF, High priority: read this first15 pages · drawings
HighAI Summary for Heron Street Post Hurricane Nicole Repairs Drawings: This document contains detailed engineering drawings for the Heron Street Post Hurricane Nicole Repairs project in Volusia County, Florida. Dated August 25, 2025, the drawings include site location maps, existing conditions, erosion control plans, demolition plans, grading plans, and detailed construction elements such as seawalls, walkways, and beach access stairs. The project involves removal of damaged infrastructure and construction of replacement infrastructure including concrete sheet-pile seawalls, concrete walkways, dune plantings, and ancillary site improvements. The document specifies compliance with Florida Department of Environmental Protection permits and includes notes on construction access, staging areas, and environmental considerations. The drawings are prepared by Coastal Tech and Sliger & Associates, Inc., with certification and engineering oversight noted.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for Heron Survey - Coastal Technology Corporation: A topographic survey document for Coastal Technology Corporation located in Volusia County, Florida. It includes technical survey notes, legal descriptions, elevation data (NAVD 88), and flood insurance rate map zones. The document references approval by the Volusia County Board of County Commissioners on June 29, 2017.
PDF
PDF, High priority: read this first100 pages · ifb
HighAI Summary for Invitation for Bid 26-B-38IF Heron Street, Egret Avenue, and Mallard Street Seawall Replacement Project: This Invitation for Bid (IFB) 26-B-38IF, released January 20, 2026, by the County of Volusia, solicits bids for the Heron Street, Egret Avenue, and Mallard Street Seawall Replacement Project. The project involves demolition, hauling, seawall construction, grading, compaction, and timber dune walkover construction at three beachfront locations damaged by Hurricanes Ian and Nicole. Bids must be submitted electronically by February 19, 2026, with a non-mandatory pre-bid meeting on January 29, 2026. The contract includes all permitting, labor, materials, equipment, and services necessary for completion. Estimated construction cost is $2,112,580.80, with substantial completion in 120 days and final completion in 150 days. The document includes general and special terms, insurance requirements, technical specifications, construction plans, and federal contract provisions.
XLS
XLS, High priority: read this first1 page · prime-subcontractor-form
HighAI Summary for ITB 26-B-38IF Prime-Subcontractor Form for Contract C-2067: This document is the Prime/Subcontractor Form associated with Invitation to Bid (ITB) No. 26-B-38IF and Contract No. C-2067. It requires bidders to list all subcontractors proposed to perform work on the project, including company names, addresses, dollar values, and percentages of work performed. The form emphasizes that failure to complete and return it may result in a non-responsive bid. It also notes that the prime contractor is responsible for ensuring subcontractors hold appropriate licenses and that any changes require prior approval from the County Project Manager. The form is used to determine local bid preference and includes various subcontractor disciplines anticipated for the project.
XLS
XLS, High priority: read this first1 page · prime-sub-form
HighAI Summary for ITB No. 25-B-##XX Prime/Subcontractor Form: This document is a Prime/Subcontractor Form associated with ITB No. 25-B-##XX, version dated January 15, 2025. It requires bidders to list all subcontractors proposed to perform work on the project, including company names, addresses, dollar values, and percentage of work performed. The form emphasizes that failure to complete and return it may result in a non-responsive bid. It also notes that the prime contractor is responsible for ensuring subcontractors hold appropriate licenses and that any changes require prior approval from the County Project Manager. The form is used to determine local bid preference and includes instructions for self-performing primes and subcontractor disciplines.
PDF
PDF, High priority: read this first14 pages · drawings
HighAI Summary for Mallard Street Post Hurricane Nicole Repairs Drawings: This document contains detailed construction drawings for the Mallard Street Post Hurricane Nicole Repairs project in Volusia County, Florida. It includes a sheet list with cover sheet, existing conditions, erosion control plan, demolition plan, site plan, grading plan, details for seawall and deadman, and other miscellaneous details. The work involves demolition and removal of damaged infrastructure and construction of replacement infrastructure such as a concrete sheet-pile seawall, concrete walkway, beach access stairs, dune plantings, and ancillary site improvements. The document also includes general notes on project scope, permits, and construction requirements, as well as technical specifications references and silt fence installation notes.
PDF
PDF, High priority: read this first48 pages · contract-document
HighAI Summary for Volusia County Construction Contract ITB No. 26-B-38IF: This document is a construction contract between the County of Volusia and a contractor for the Heron Street, Egret Avenue, and Mallard Street Seawall Replacement Project. It references ITB No. 26-B-38IF and includes detailed contract articles covering contract documents, contractor services, scope of work, compensation, personnel, insurance, dispute resolution, termination, liability, government compliance, and miscellaneous provisions. The contract incorporates multiple exhibits such as general conditions, special conditions, bid documents, bonds, construction plans, technical specifications, and federal provisions. It outlines permit responsibilities and the order of precedence for contract documents. The contract emphasizes contractor responsibilities for site conditions, permits, and compliance with contract terms.
PDF
PDF, Low priorityother
LowAI Summary for Exhibit I - Surveys for 26-B-38IF Heron Street, Egret Avenue, and Mallard Street: This document titled 'Exhibit I - Surveys for 26-B-38IF Heron Street, Egret Avenue, and Mallard Street' appears to be an exhibit related to surveys for specific locations. The content of the document is not provided or is empty, so no further details about the surveys or their purpose can be determined.
PDF
PDF, Low priority2 pages · geotechnical-report
LowAI Summary for Heron Street Beach Access Geotechnical Data Report G24130: This document is a geotechnical data report dated September 27, 2024, prepared by Bechtol Engineering and Testing, Inc. for the Heron Street Beach Access project in Port Orange, Volusia County, Florida. The report presents the results of subsurface soil testing, including one Standard Penetration Test boring to 40 feet depth, soil profiles, and suggested soil parameters for design use. It provides physical and strength characteristics of the soils to assist in the design of a replacement boardwalk landing and sheet pile bulkhead. The report includes soil classification, groundwater levels, penetration resistance, and engineering parameters such as cohesion, friction angle, and earth pressure coefficients.
PDF
PDF, Low priority2 pages · geotechnical-report
LowAI Summary for Mallard Street Beach Access Geotechnical Data Report G24131: This document is a geotechnical data report dated September 27, 2024, prepared by Bechtol Engineering and Testing, Inc. for the Mallard Street Beach Access project in Port Orange, Volusia County, Florida. The report presents the results of a Standard Penetration Test boring to a depth of 40 feet to evaluate subsurface soil characteristics for the design of a replacement boardwalk landing and sheet pile bulkhead. It includes soil profiles, soil parameters, and a boring location plan to assist design engineers. The report is signed and sealed by a professional engineer, Love B. Patel, P.E.
PDF
PDF, Low prioritysurvey-report
LowAI Summary for Topographic Survey for Coastal Technology Corporation, Volusia County FL: This document is a topographic survey prepared for Coastal Technology Corporation. It covers a portion of Section 12, Township 16 South, Range 33 East in Volusia County, Florida, specifically located at S Atlantic Ave, Port Orange, FL. The legal description references property boundaries per the Volusia County Property Appraiser, including part of Eort Ave (Pelican St) east of SR A1A Wilbur By The Sea Plat 1 MB 15 PCS 124-125. The survey provides detailed geographic and property boundary information relevant to this location.
During Hurricane's Ian and Nicole the existing beachfront armoring at the eastern end of Heron Street, Egret Avenue, and Mallard Street in Wilbur by the Sea were severely damaged or destroyed. These right-of-way's are controlled by Volusia County and its the intent of this project to repair and improve the armoring and public beach access at these locations. This project will require demolition and hauling of existing structures, construction of seawalls, grading, compaction and timber dune walkover construction. All three project locations have minimal space for materials and equipment and are bordered by private properties and a heavily traveled road.