Industrial Water Channel Sediment Removal

Active
CON-2018-46State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The contract awarded to C & J Excavation of Carlsborg, WA, totaling $78,759.67, covers the removal of approximately 6,600 cubic yards of sediment from an active industrial water channel in Port Angeles, Washington, relocating it to an adjacent abandoned channel area. This project includes grubbing and stockpiling contaminated sediment to be reused as a protective cap over uncontaminated materials, accompanied by pre- and post-relocation surveys to verify conditions. Work is mandated to comply with the 2018 Washington State Department of Transportation Standard Specifications, the City of Port Angeles Urban Services Standards, and APWA General Special Provisions, with completion required by October 1, 2018. The contract follows a lowest responsible and responsive bidder approach without formal Federal Acquisition Regulation clauses, relying instead on locally defined public works contract terms. Bid submissions were due August 28, 2018, with specific requirements including sealed paper bids with completed bid forms, non-collusion affidavits, and bid security. The evaluation focused on mandatory factors such as bidder responsibility, compliance with bonding and insurance, and prevailing wage laws, consistent with a Lowest Price Technically Acceptable methodology. Contract administration tasks, including invoice review and approval, fall to the Director of Public Works and Utilities or their designee, with payments due within 30 days of proper invoice receipt. Inspection and acceptance are conducted on-site by an engineer representing the City, with risk and expense for correction of deficiencies borne by the contractor, who also provides a one-year warranty on workmanship and materials. Insurance requirements are detailed, enforcing continuous coverage with defined minimums and insurer rating expectations. No special contract clauses regarding security clearances, key personnel, or organizational conflicts were identified, and all contract communications and submissions were handled through the City Engineer’s office at Port Angeles, with no electronic bidding options available.

General Info

C & J Excavation awarded $78,759.67 for sediment removal, relocation, surveys, and compliance by October 1, 2018.

Place of Performance

WA, USA

Set-Aside

NONE

Documents

3

Addendum 1 to CON-2018-46 Industrial Water Channel Sediment Removal Project

PDF, High priority: read this firstamendment
High

CON-2018-46 Industrial Water Channel Sediment Removal Contract

PDF, High priority: read this firstcontract-document
High

CON-2018-46 Instruction to Bidders and Bid Form for Industrial Water Channel Sediment Removal

PDF, High priority: read this first7 pages · rfb
High

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseSolicitation
Posted

Solicitation

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyWashington → Port Angeles
Contacts1 person available
OfficeN/A
Organization / AgencyWashington → Port Angeles
Office AddressN/A
Contacts

Full Description

Show more
Award to C & J Excavation, Carlsborg, WA for $78,759.67
Addendum #1 is issued.

Bids must be received no later than Tuesday, August 28, 2018 at 2:00 PM and will then be opened and read shortly after.

Engineer's estimate range - $40,000 to $60,000.

Similar Contracts

Same NAICS industry code

NAICS: 238910
New
Keystone Job Corps Building 14 Demo
Solicitation # keystone-job-corps-building-14-demo
The Keystone Job Corps is soliciting bids for the complete demolition of Building 14, the old security building, and its foundation at the Keystone Red Rock Job Corps Center in Drums, Pennsylvania. The scope of work includes the demolition of an old septic system, removal of debris, trees, and rocks, and the subsequent backfilling, grading, and seeding of the affected areas. Critical utility work is required, including capping the sewer line and disconnecting building power while ensuring uninterrupted power and communications for the guard shack and mountain pump house and tank. Additionally, the contractor must disconnect and replace the water shut-off valve with a straight pipe, a task that must be completed within a single day between 8:30 AM and 3:00 PM to minimize disruption to students. This small business set-aside project requires the contractor to provide all necessary permits, dumpsters for haul-off, and chain of responsibility letters for all waste. Due to the building's roadside location on Foothills Drive, the contractor is responsible for providing flaggers and traffic control to manage heavy equipment and local traffic. Bidders must be active and registered in SAM.gov and are required to submit bids with labor and materials listed separately. Compliance with the Davis-Bacon Act is mandatory, requiring the payment of prevailing wages and the submission of certified payroll.
Keystone Job Corps

POSTED

about 15 hours ago

DEADLINE

in 4 days
View Details
NAICS: 238910
New
Federal
Shirley Creek Campground Improvements
Solicitation # 127EAX26Q0114
Solicitation 127EAX26Q0114 is a Request for Quotation issued by the USDA Forest Service for campground improvements at Shirley Creek Campground within the Brownstown Ranger District of the Hoosier National Forest in Indiana. This total small business set-aside project requires a contractor to provide all labor, materials, tools, and supervision to develop individual campsites, overflow and day-use parking, and drive widening. The scope of work includes staking campsite spurs, stripping turf, earthwork, excavating to sub-grade, installing and compacting aggregate base and surface courses, and restoring disturbed areas with topsoil, seed, and mulch. All work must comply with 2022 Indiana Department of Transportation Standard Specifications, and the contractor is responsible for disposing of excess materials at designated on-site locations. The contract will be awarded as a firm-fixed-price agreement based on the lowest price technically acceptable criteria. Evaluation factors include a technical approach detailing the work plan, a construction schedule, and a record of three similar projects completed within the last three years. The performance period is 30 business days from the notice to proceed, with a scheduled window between October 12, 2026, and November 11, 2026. Quotations must be submitted as three separate PDF documents, including a signed SF1442, a priced Schedule of Items, and a technical proposal. Following amendments, the final deadline for electronic submission is October 20, 2026, at 5:00 PM Eastern Time.
Csa Southwest 7 Usda-Fs

POSTED

about 19 hours ago

DEADLINE

in 5 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS