Market Intelligence Notice: Niagara Falls Air Reserve Station Taxiway A4 & Runway Extension Project - Use of Construction Management at Risk (CM@Risk) Utilizing Other Transaction Authority (OTA)

Closed
W912QR-CMRISK-NFARSTAXIWAYFederal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237310
New
North Hollywood Central Remediation Well Collector Line; IFB No. 8003R1
Solicitation # 8003R1
Kiewit Infrastructure West Co. is soliciting sub-quotes for the North Hollywood Central Remediation Well Collector Line project, an initiative for the City of Los Angeles Department of Water and Power located in California. The comprehensive scope of work includes underground construction such as tunneling, boring, jacking, and micro tunneling, as well as site preparation activities including land surveying, site clearing, shoring, and subgrade roadbed work. Additional requirements encompass environmental services like storm water pollution prevention, the installation of utilities, manholes, traffic signals, lighting, and landscaping, and the supply of materials such as ready mix and precast concrete. This solicitation is open to qualified Small Businesses, including SBA certified Women-Owned Small Businesses and Disadvantaged Business Enterprises. To be considered responsive, bidders must possess a valid California Contractor license, provide acceptable insurance, and be capable of providing bonding for 100 percent of their contract value, for which Kiewit will reimburse the premiums. Bidders must also demonstrate an ability to maintain labor harmony on the project. Interested parties must contact Lead Estimator Ken Johnston to receive an Invitation to Bid via the Building Connected system, with a final response deadline of November 18, 2025.
Kiewit Infrastructure West Co.

POSTED

about 5 hours ago

DEADLINE

in 19 days
NAICS: 237310
New
SLED
SB Minor B 03A4243 - Bicycle Railing Installation - Placer County
Solicitation # 03A4243
The California Department of Transportation is soliciting bids for contract 03A4243, which involves the installation of bicycle railings at the Maple Street Overcrossing on Route 80 in Auburn, Placer County. This is a Small Business Minor B set-aside project with an estimated cost of $253,000.00. The contract will be awarded to the lowest responsible bidder who is a certified small business at the time of bid opening and award. The project must be completed within 20 working days, and the scope includes the implementation of temporary traffic control systems and the installation of traffic stripe tape meeting specific retroreflectivity and durability standards. Bids must be submitted via email to [email hidden] by November 12, 2026, and any bid exceeding $484,000.00 will be rejected. While no specific DVBE goal is established, participation is encouraged. The successful bidder will be required to provide a payment bond if the bid exceeds $25,000, along with certificates of insurance, a Payee Data Record, and Postconsumer-Content Certification. All construction materials must comply with Build America Buy America standards under 2 CFR 184.6. Payment for contracts of 20 working days or less is made after contract acceptance, while longer contracts allow for progress payments via itemized invoices.
California Department of Transportation

POSTED

about 5 hours ago

DEADLINE

in 14 days
NAICS: 237310
New
SLED
SB Minor B-Install passageway for emergency vehicles-San Diego County
Solicitation # 11A4469
The California Department of Transportation is soliciting bids for contract 11A4469 to install a passageway for emergency vehicles in San Diego County. This is a Small Business Minor B set-aside, requiring bidders to be certified as a small business by the Department of General Services by 5:00 p.m. on the bid opening date. The scope of work includes traffic control, electrical system installation for detectors, environmental controls such as temporary water pollution and concrete washout facilities, and the installation of signage and pavement markings. The project is governed by 2025 Standard Specifications and Standard Plans, with specific requirements for Buy America compliance and strict quality standards for local materials, including pH and lead concentration limits. Bids must be submitted exclusively via email to [email hidden] by November 12, 2026, as hard copies will not be accepted. Any bid exceeding 484,000.00 dollars will be rejected per Public Contract Code 10105(b). The contract will be awarded to the lowest responsible bidder within 30 days of the bid opening. Successful awardees must provide payment bonds and insurance at the time of award and complete the Payee Data Record and Standard Agreement forms. Payment terms vary based on project duration, with progress payments available for contracts exceeding 20 working days, provided the work meets specifications and the value exceeds 5,000 dollars.
California Department of Transportation

POSTED

about 5 hours ago

DEADLINE

in 14 days

AI Contract Overview

Show more

The U.S. Army Corps of Engineers, Louisville District, is seeking market intelligence for a project to extend Runway 10-28 and associated taxiways at the Niagara Falls Air Reserve Station in New York. With an estimated acquisition magnitude of 50 million dollars, the scope includes reconstructing the Runway 28 overrun, extending Taxiway A4 and Runway 6-24, installing new airfield electrical and lighting systems, constructing a creek culvert over Cayuga Creek, and erecting a jet blast deflector fence. The project involves approximately 780,000 square feet of new airfield pavement and requires coordination with the FAA and other stakeholders. Key challenges include shallow bedrock, high groundwater, and the protection of the sensitive Devil Crayfish habitat. The government is evaluating a Construction Management at Risk strategy utilizing Other Transaction Authority under 10 U.S.C. section 2808a. This approach would be executed in two phases, starting with a preconstruction phase where the builder assists in finalizing the design from 35 percent to 100 percent, followed by a construction phase under a Guaranteed Maximum Price. Interested firms are requested to provide detailed responses via a specific survey form by September 25, 2026, addressing their experience with airfield pavement, environmental risk management, and collaborative delivery methods. This RFI is for informational purposes only and does not constitute a formal solicitation.

General Info

USACE seeks market intelligence for 50 million dollar runway extension in New York.

NAICS

237310 - Highway, Street, and Bridge Construction

Place of Performance

KY

Set-Aside

NONE

Documents

2

W912QR-CMRISK-NFARSTAXIWAY: NFARS Runway Extension Market Intelligence

PDF, Low prioritysources-sought
Low

QRCode+for+Market+Intelligence+NFARS.png

PNG

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseClosed
Posted

Sources Sought

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → W072 Endist Louisville
Contacts1 person available
OfficeLOUISVILLE, KY, 40202-2230, USA
Office AddressLOUISVILLE, KY, 40202-2230, USA
Contacts

Full Description

Show more

REQUEST FOR INFORMATION (RFI) / MARKET INTELLIGENCE NOTICE


Place of Performance: Niagara Falls Air Reserve Station (NFARS), New York


Notice: This is a Request for Information (RFI) for market intelligence and for informational purposes only. This announcement does not constitute a Solicitation or a Request for Proposal (RFP), and no solicitation is currently available. Participation in this RFI is strictly voluntary. The Government will not be obligated to award any agreement or contract because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal should formal solicitation be issued in the future.


NAICS Code: 237310 – Highway, Street and Bridge Construction.



(Note: While Other Transaction Authority is not subject to FAR-based small business regulations, this NAICS code is provided for market research to help the Government understand the size and demographics of the interested industrial base.)


Small Business Size Standard: $45 Million



PROJECT OVERVIEW


The U.S. Army Corps of Engineers (USACE), Louisville District, has a requirement for the design and construction to extend Runway 10-28 and associated taxiways at the Niagara Falls Air Reserve Station, New York.


The scope of work consists of furnishing all necessary equipment, materials, labor, supervision, quality control, and supplies to deliver fully functional airfield improvements. The primary project elements include:


a. Reconstructing the existing overrun/blast pad on Runway 28 end to full-strength airfield pavement.


b. Extending Runway 10-28 and extending Taxiway A4 to connect the 914th ARW apron to the new Runway 28 end.


c. Extending a 520-foot portion of Runway 6-24 and providing a warmup pad for two (2) KC-135R aircraft.


The potential total area of new airfield pavement is approximately 780,000 sq ft.


d. Modifying the Federal Aviation Administration (FAA) Medium-Intensity Approach Lighting System with Runway End Identification Lights (MALSR) approach lighting, which requires active coordination with FAA construction representatives during removal and re-installation.


e. Installing new airfield electrical and lighting systems, including runway edge lights, runway centerline lights, threshold lights, touchdown zone lights, airfield signage, and taxiway edge lights.


f. Constructing a new creek culvert to allow the new taxiway to traverse the Cayuga Creek.


g. Erecting a jet blast deflector fence on the Runway 28 end.


Estimated Acquisition Magnitude: $50,000,000.00


CRITICAL PROJECT CONSTRAINTS & CHALLENGES:


  • Geotechnical Constraints: The project site features variable and shallow bedrock (as shallow as 3 feet below grade) and a high groundwater table that heavily complicates subdrainage and stormwater design.
  • Sensitive Environmental Conditions: Work will occur near federal and state-regulated wetlands and Cayuga Creek. The site is a habitat for the Devil Crayfish, which is listed as a species of Greatest Conservation Needs. Multiple permits with State and Federal agencies will be required prior to construction.
  • Operational Constraints: A significant portion of the work will occur within the active runway Controlled Movement Area (CMA). Work requires compliance with an FAA-approved Construction Safety and Phasing Plan (CSPP), temporary displaced threshold markings, modifications to NAVAIDS, and FAA flight checks.
  • Security Constraints: Strict security constraints are in place, requiring Government escorts at all times during construction.
  • Airfield Pavement Quality Control: Onsite batch plant space (approx. 6 acres) has been identified. Review and final approval of concrete and asphalt mix designs reside with the USACE Transportation Service Center (TSC). The TSC will provide a mandatory, weeklong airfield pavement workshop prior to the start of construction, which the contractor’s key personnel must attend.
  • Stakeholder Coordination: The contract requires active coordination with the airport operator (Niagara Frontier Transportation Authority - NFTA), USACE, Air Force Reserve Command (AFRC), FAA, and Niagara Falls Air Reserve Station (NFARS).


PLANNED ACQUISITION STRATEGIES UNDER EVALUATION: Construction Management at Risk (CM@Risk) via Other Transaction Authority (OTA).


The Louisville District is evaluating a Construction Management at Risk (CM@Risk) strategy utilizing an Other Transaction (OT) Agreement under the authority of 10 U.S.C. § 2808a. This authority is intended for military construction projects that involve testing and experimentation associated with new and emergent construction technologies to achieve potential benefits such as enhanced mission resilience, improved installation support, or cost and schedule reduction.


Currently, the Government has advanced the design to 35% and has the capability to progress to a full design. Therefore, the Government is utilizing this RFI to assess industry capability, interest, and the advantages of utilizing Construction Management at Risk (CM@Risk) utilizing an Other Transaction (OT) Agreement under the authority of 10 U.S.C. § 2808a.



The CM@Risk Course of Action (10 U.S.C. § 2808a):


This Course of Action utilizes the 10 U.S.C. § 2808a OT authority to execute a construction project where the design is at 35% completion.


Phase 1 Preconstruction: The builder is hired during Phase 1 to act as an expert consultant, helping the Designer of Record (DOR) push the design from 35% to 100% using real-time market data and MII (MCACES 2nd Generation) cost comparisons.


Phase 2 Construction: Once the design hits 100% and the MII estimate validates the open-book pricing, the agreement transitions to Phase 2, where the builder goes "At-Risk" to construct the facility under a Guaranteed Maximum Price (GMP). The DOR retains design liability, but the contractor drives constructability and assumes responsibility for layout, schedule, and trade coordination.



The CM@Risk Pricing Structure:


Preconstruction Services Fee: A small, fixed-price or time-and-materials amount paid to the contractor strictly to fund their time spent helping the Architect Engineer (A/E) finalize the 35% design into a 100% design.


The Target Fee: The contractor’s transparent profit margin for managing the actual construction, bid competitively upfront.


The GMP: The absolute ceiling for the construction phase (Validated Direct Costs + Target Fee + Shared Contingency).



PHASED EXECUTION PLAN


Phase 1: Preconstruction Services Agreement (CM@Risk Advisory)


  • Solicitation (White Papers): The Solicitation would likely include the 35% design. The Deliverable is anticipated to be a concise 5-10 page White Paper. Evaluation Criteria will likely include Corporate capability and experience with collaborative project delivery methods ( including CM@Risk, Progressive Design-Build (PDB) and/or Design-Build to Budget (DBtB)) under an OT framework; preconstruction approach (how the firm plans to collaborate with the Government's A/E to close the remaining 65% design gap, identify value-engineering opportunities, and mitigate supply-chain risks); proposed Target Fee (for construction) and Preconstruction Services Fee.
  • The Pitch Meeting (Oral Presentations): A 90-minute pitch where the contractor must bring their Project Manager, Site Superintendent, and their Preconstruction Manager. The Government team assesses how well the contractor's team will integrate with the A/E during the critical final design push. The OT is initially awarded and funded only for the Preconstruction Services Fee.
  • Design Finalization (Bridging the 65% Gap): The contractor’s Preconstruction team sits with the Government and the DOR. Because the design is not locked, they can actively change it. They perform value engineering, finalize equipment selections, and ensure the drawings are 100% constructible.
  • Open Book Pricing vs. MII: As the design reaches 100%, the contractor conducts open-book market outreach. The Government and contractor review actual sub-bids together. USACE cost estimators finalize the Independent Government Estimate (IGE) using the MII software to validate costs and establish the GMP base.

Phase 2: Construction Execution Agreement (Going "At-Risk")


  • Execution: The Agreements Officer (AO) executes a bilateral modification to the OT Agreement, incorporating the GMP and funding the physical construction.
  • Risk Allocation: Under CM@Risk, the contractor is now "At-Risk." While the DOR retains design liability, the contractor collaborates to identify constructability conflicts during Phase 1. During Phase 2, while the DOR still owns fundamental engineering failures, the contractor loses the ability to claim "defective design" for constructability issues, material delays, or coordination errors, because they were explicitly paid to help finalize those exact decisions using market and MII data during Phase 1.

INFORMATION REQUESTED (INDUSTRY QUESTIONNAIRE)


Interested parties are requested to respond to the following questions to help shape the final acquisition strategy:


Company Profile:


Q1. Firm Name


Q2. Address


Q3. Point of Contact (Name, Title)


Q4. Phone Number


Q5. Email Address


Q6. Unique Entity ID


Q7. CAGE code


Q8. Socioeconomic Status (Other Than Small, Small, 8(a), SDVOSB, etc.)


Q9. Participating Role (Prime Contractor, Subcontractor, Design Firm, Other)


Other Transaction Authority (OTA) & Statutory Compliance:


Q10. Innovative Technologies: The authority for this OTA (10 U.S.C. § 2808a) is focused on prototyping with new or emergent construction technologies. Describe any innovative materials, methods, or technologies your firm could propose for a project of this scale that could lead to cost savings, schedule acceleration, or enhanced facility performance and resilience.


Q11. OTA Experience: Describe your firm's previous experience (if any) executing prototype projects under an OTA.


Q12. Barriers to Innovation: What commercial or Government-imposed barriers currently make it difficult to propose or implement innovative construction technologies on traditional military construction projects? How could the flexibility of an OTA help overcome these barriers?


Q13. Custom Commercial Terms & Dispute Resolution: To optimize the flexibilities of the Other Transaction Authority (OTA) framework, what specific commercial terms (e.g., tailored dispute resolution/rapid escalation mechanisms, commercial milestone payment structures, or shared intellectual property rights for innovative methods) would your firm recommend the Government adopt to minimize risk and incentivize your participation?


Q14. What project characteristics make CM@Risk-OTA particularly advantageous or disadvantageous for this requirement?


CM@Risk & Design-Assist Involvement:


Q15. Design Entry Point Suitability (35% vs. 65% vs. 95% Entry): The Government is seeking industry feedback on the optimal design completion stage for onboarding the CM@Risk builder. In your experience, which design entry point—35% (bridging a 65% gap to construction-ready), 65% (bridging a 35% gap), or 95% (bridging a 5% gap)—provides the best value for integrating meaningful constructability, value engineering, and long-lead supply chain mitigation?


Q16. Design Maturity & Early-Builder Benefits: Given the scale of this project ($50M), what are the primary benefits of bringing on a CM@Risk builder during the preconstruction phase (e.g., at 35% or 65% design), and how can the Government maximize those benefits?


Q17. Collaborative Framework: What collaborative mechanisms do you recommend the Government implement to rapidly close the design gap and transition to a validated GMP?


Q18. CM@Risk Experience: Describe your experience executing Construction Management at Risk (CM@Risk) or other highly collaborative delivery methods, particularly where you served as an advisor before going "at-risk".


Guaranteed Maximum Price (GMP), Risk Allocation & Compensation:


Q19. Preconstruction Compensation: What specific compensation structures (e.g., fixed stipends, time-and-materials) would best compensate your firm for the pre-construction effort and design-assist phase?


Q20. Open Book Pricing: How do you approach "open-book" pricing and transparency during Phase 1 to build trust and ensure the Government is receiving fair market value before locking in the GMP?


Q21. For airfield and taxiway projects where full paving mobilization is bound by concrete mix designs, test section approvals, and strict QA/QC testing protocols, what novel or standard early work packages (e.g., batch plant mobilization, subgrade prep, haul routes) and long-lead material procurements (e.g., airfield lighting, specialized aggregates) would your firm recommend authorizing immediately upon GMP establishment to optimize schedule performance while mix approvals are pending?


Q22. Phase 1 Off-Ramp Risk: If the Government and the contractor cannot reach an agreement on the final GMP, what specific off-ramp conditions are critical to your firm?


Q23. Risk allocation: Under a CM@Risk model where the Government retains the Designer of Record, how does your firm view the proposed risk allocation regarding constructability and design-defect claims? What risk-sharing or shared-contingency structures do you recommend to optimize pricing?


Airfield Pavement & Environmental/Geotechnical Expertise:


Q24. Technical Airfield Experience: Describe your specific experience with large-scale airfield pavement projects (minimum 500,000 SF) on active FAA-regulated or military airfields, including the management of onsite concrete/asphalt batch plants and compliance with FAA Construction Safety and Phasing Plans (CSPP).


Q25. For each project example provided in response to Question 24, please clearly specify your firm’s specific role and level of responsibility (e.g., Prime Contractor, Joint Venture Managing Partner, Non-Managing JV Partner, Construction Manager, Subcontractor, or Specialized Trade Contractor). Please also indicate the percentage of the total contract value performed directly by your firm.


Q26. Environmental & Geotechnical Risk Management: This project involves highly sensitive environmental conditions (wetlands, Cayuga Creek, Devil Crayfish) and challenging geotechnical constraints (variable bedrock as shallow as 3 feet, high groundwater). Describe your experience managing extensive subdrainage installation and bedrock excavation under high groundwater conditions.


Q27. How would your firm mitigate risks associated with working in/near state and federal wetlands and protecting sensitive species (like the Devil Crayfish) without causing project delays?


Q28. What is the greatest supply chain, scheduling, or technical risks you foresee for a project of this type at Niagara Falls Air Reserve Station, and how would this CM@Risk delivery method help mitigate them?


Teaming & Subcontractor Integration:


Q29. Subcontractor Onboarding: Under a CM@Risk model starting at a 35% design, how and when do you plan to on-board your critical subcontractors (e.g., electrical, paving, earthwork, structural steel)?


Q30. Subcontract Competition: Will you compete with these subcontracts openly during Phase 1 to build the open-book GMP, or do you prefer bringing in established partners from day one?


Feedback on the Acquisition Strategy & Alternatives:


Q31. Strategy Incentives: Does the proposed CM@Risk-OTA strategy incentivize your firm to participate? Why or why not?


Q32. Two-Phase Selection Process & Proposal Burden: Does the proposed two-phase selection framework (Phase 1: Concise 5-10 page White Paper; Phase 2: 90-minute Pitch Meeting/Oral Presentation) provide an efficient mechanism for your firm to demonstrate its qualifications and CM@Risk capabilities without creating an undue proposal cost burden? What specific submission requirements, page limits, or response timelines would encourage robust competition from top-tier firms?


Q33. Alternative Approaches: Are there alternative acquisition strategies, phasing approaches, or commercial practices the Government has not considered that would yield a better airfield facility, faster delivery, or lower cost?


Q34. Differentiating Evaluation Criteria: To differentiate high-performing CM@Risk collaborative builders from traditional low-bid general contractors, what evaluation criteria (e.g., past collaborative-delivery/CM@Risk performance, key personnel/superintendent experience, trade-partner/subcontractor open-book engagement strategy, or proposed General Conditions fees) should carry the greatest weight in the Government's evaluation?


Bonding Capability:


Q35. Maximum Bonding: Specify your maximum bonding (Single and Aggregate) as a Sole Prime Contractor and/or as a Joint Venture.


Q36. Phased Bonding Approach: Given the distinct phases of the CM@Risk OTA structure, would a phased bonding approach - where your firm is only required to bond the value of the Phase 1 preconstruction services initially, with full construction Performance and Payment bonds deferred until the bilateral execution of Phase 2 (GMP) - effectively mitigate risk and bonding capacity constraints for your firm? Please describe any alternative commercial security structures you recommend.



SUBMISSION INSTRUCTIONS


Submission Requirement: The only authorized transmission method of responses is via filling out the survey form. No other transmission method will be accepted. Please limit your capability statement to the space provided within the form. The Market Intelligence Response Form can be accessed at  https://forms.osi.apps.mil/r/xpuL4AqhEr  or via the QR Code provided in the attachment.


Please submit your responses by 25 September 2026 at 1000 Eastern Time.


The questionnaire is the Government's primary mechanism for obtaining detailed market intelligence and addresses industry capability, experience, technical capabilities, construction considerations, and recommended OTA and commercial practices.


The Government welcomes candid industry feedback and recommendations regarding commercial practices, agreement terms, project phasing, risk sharing, governance, pricing approaches, and other considerations that could improve successful execution of this project under 10 U.S.C. § 2808a.


Interested firms are encouraged to add themselves to the Interested Vendors List associated with this announcement on SAM.gov to receive future updates.


Note: Do not submit proprietary trade secrets, protected technologies, or classified information in your response.  All feedback received will be handled as public market research to shape the Government's final acquisition approach.


More opportunities from Department Of Defense → W072 Endist Louisville

Same awarding agency

NAICS: 237110
New
Federal
Design-Bid-Build - Rough River Lake Axtel Wastewater Treatment Plant (WWTP)
Solicitation # W912QR27BA003
Solicitation W912QR27BA003 is a Design-Bid-Build project for the demolition and construction of the Axtel Wastewater Treatment Plant (WWTP) at Rough River Lake in McDaniels, Kentucky. The scope of work requires the contractor to remove the existing WWTP and fencing and install a new Aerobic Treatment Unit (ATU) and Drip Field System. This unrestricted procurement is estimated to have a construction magnitude between 1 million and 5 million dollars, with the award based on the lowest evaluated price. A 10 percent price evaluation preference will be applied to eligible HUBZone small business concerns. The contract is a Firm-Fixed-Price agreement under NAICS code 237110, with a total project duration of 400 calendar days from the Notice to Proceed. Performance is scheduled from December 18, 2026, to January 22, 2028, with a requirement to commence work within 10 calendar days of the notice. Key requirements include the submission of a Construction Quality Control (CQC) plan within 30 days of the notice to proceed, adherence to Davis-Bacon Act wage rates, and the provision of a Site Safety Health Officer. Liquidated damages for delays are set at 500 dollars per calendar day. Proposals must be submitted electronically via the PIEE Solicitation Module by the December 3, 2026, deadline.
Water and Sewer Line and Related Structures Construction

POSTED

3 days ago

DEADLINE

in about 1 month
View Details

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS