This Solicitation opportunity from Department Of Defense was posted on March 9, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

Military Construction Project (MILCON) P732 Design-Bid-Build, Electrical Distribution System Upgrades (Gosport Substation Only) at Norfolk Naval Shipyard (NNSY) in Portsmouth, Virginia.

Closed
N6247026R0015Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237130
New
SLED
Broadband Implementation Project - FFA
Solicitation # 2001063
The Broadband Implementation Project - FFA, solicitation number 2001063, is a comprehensive infrastructure initiative for the City of San Luis Obispo, California. The project involves the installation of aerial and underground fiber optics, including directional boring for conduit, deep bore casing, and the installation of 288 CT fiber cable. The scope of work encompasses the placement of various sized vaults, copper clad ground rods, pole risers, down guys, anchors, and new wooden poles, as well as cut and kick operations for existing poles. Additional requirements include potholing, tree trimming, public notification, and strict compliance with CPUC grant reporting and archaeological monitoring. The project is structured with a base bid and five additive alternates covering specific street segments, with award decisions based on a total project bid hierarchy capped at 2,400,000 dollars. Contractors must adhere to stringent technical and regulatory standards, including CPUC General Order 95, Caltrans 2024 specifications, and the City of San Luis Obispo 2025 Engineering Standards. Key requirements include the submission of OTDR bi-directional testing results prior to acceptance and the employment of directional drilling personnel with at least two years of experience. Bidders must provide a bid guaranty of 10 percent of the bid amount and, upon award, provide performance and payment bonds equal to 100 percent of the contract price. Compliance with California Labor Code is mandatory, requiring registration with the Department of Industrial Relations and adherence to prevailing wage laws. Sealed bids are due by 11:00 a.m. on November 19, 2026, to the Public Works Administration Office in San Luis Obispo.
City of San Luis Obispo

POSTED

about 13 hours ago

DEADLINE

in 30 days
NAICS: 237130
New
SLED
24-17.11
Solicitation # 24-17.11
The City of Piqua, Ohio, is soliciting bids for Project No. 24-17.11, which involves the construction of the Washington Road 69kV Transmission Line. The scope of work includes the furnishing and installation of approximately 2.0 miles of 69kV transmission line terminating at a new 69kV/13.8kV substation. Key technical requirements include a 12.47kV distribution underbuild from Pole P1 through Pole P18, the installation of all-dielectric self-supporting fiber optic cable along the entire line, and the use of both contractor-furnished materials and owner-furnished self-supporting steel poles. The project has an engineer's estimate of $1,900,000 and requires adherence to the National Electrical Safety Code and various ASTM standards for ductile iron poles and fiberglass crossarms. Bidders must provide evidence of financial and performance experience and are required to submit a bid bond of at least 10% of the total bid amount. The successful contractor must post a combined performance and payment bond for 100% of the contract value. Compliance with State of Ohio Prevailing Wage laws, the Americans with Disabilities Act, and Drug-Free Workplace certifications is mandatory. Bids must be submitted via Bid Express, email, or sealed hard copy by October 29, 2026. All equipment must be delivered FOB Destination to the City of Piqua, and any bids specifying FOB Factory will be rejected.
City of Piqua

POSTED

1 day ago

DEADLINE

in 9 days
NAICS: 237130
New
SLED
24-17.10
Solicitation # 24-17.10
The City of Piqua, Ohio, is soliciting bids for project 24-17.10, which involves the electrical construction of the Piqua 69kV The Site Substation. With an engineer's estimate of $1,310,000, the scope of work includes furnishing and installing major equipment such as liquid-filled step-down transformers, circuit breakers, and switches, as well as the construction of 69kV incoming, switch, metering, and bus support structures. The contractor is responsible for comprehensive site work, including minor clearing, excavation, structural fill, grounding for all equipment, and the installation of above-ground conduits. The project also requires assistance with the start-up and commissioning of all mechanical, electrical, and electronic systems. Bidders must adhere to strict compliance standards, including State of Ohio Prevailing Wage laws, the Americans with Disabilities Act, and Drug-Free Workplace certifications. A bid bond of no less than 10 percent is required, and the successful contractor must provide performance and payment bonds equal to the full contract price. Award selection will be based on a comparison of relative merits and the lowest and best bid. Technical execution must follow NESC, NEC, IEEE, and ANSI standards, with specific quality controls for concrete foundations and equipment shipment integrity. Performance penalties of $500 per calendar day apply for deliveries exceeding the designated completion date.
City of Piqua

POSTED

1 day ago

DEADLINE

in 9 days
NAICS: 237130
New
Federal
USFK C4I Communication Tower and Facility Maintenance CY27
Solicitation # W91QVN26QXXXX
This firm-fixed price non-personnel services contract, solicitation number W91QVN26QXXXX, provides communication tower and facility maintenance for the 41st Signal Battalion C4I mission support in South Korea. The scope of work includes physical and visual inspections of metal surfaces for structural integrity, maintenance of bonding, grounding, and lightning protection systems, LED replacement for beacon and side marker lights, and interior and exterior repairs for C4I communication shelters. Performance is required across multiple sites, including Papyongsan, Yongsan TCF, Osan Bucket, Highpoint, and CP Walker AFN FM. The base period of performance is 12 months from the date of award, with funding provided by the Republic of Korea Ministry of National Defense (ROK MND). Award will be made on an all-or-none basis to the responsible offeror submitting the lowest price that is technically acceptable. Technical acceptability is evaluated on a pass/fail basis, requiring a complete technical package and compliance with the Performance Work Statement. All price proposals must be submitted in Korean Won. The contractor must provide key personnel, including an Information and Communication Engineer and a CQCSM/Safety Manager with specific education and experience requirements. Mandatory qualifications include an Information and Communication Construction License and an Electrical Construction License. The contractor is also required to adhere to strict security protocols, including AT/OPSEC compliance for foreign performance and the safeguarding of Controlled Unclassified Information.
0411 Aq Hq Contract Augmented

POSTED

1 day ago

DEADLINE

in 28 days
NAICS: 237130
New
SLED
Refurbishment Of Existing On Load Tap Changer At Adobe Creek Substation - AC21
Solicitation # RFQ199445
The City of Palo Alto Utilities Department is soliciting quotes under RFQ199445 for the refurbishment of an existing on-load tap changer (OLTC) at the Adobe Creek Electric Substation (AC-21). The project specifically requires the replacement of the TLH-21 LTC on an Allis Chalmers 15MVA transformer with a certified re-manufactured component. The scope of work includes draining and processing transformer oil, filling the LTC tank with 760 gallons of new oil, re-sealing the barrier board and pass-through studs, and replacing valves and gaskets on six radiators along with the 60KV SMD fuse holder. Comprehensive preliminary and post-work testing, including Power Factor, TTR, and DGA/oil quality testing, is mandatory. The City has standardized its requirements for the Allis Chalmers TLH-21 and will not accept alternate materials or equivalent products. Eligible bidders must hold a valid California Class A license and be registered with the DIR. The contract will be awarded to the lowest responsive and responsible bidder based on the lowest Base Bid. As a public works project, it is subject to California prevailing wage laws and requires the contractor to provide performance and payment surety bonds totaling at least 100 percent of the contract value. Additionally, contractors must meet strict insurance requirements, including general liability and worker's compensation, and comply with the City's Environmental Purchasing Policy. Bids must be submitted electronically via the OpenGov portal by November 3, 2026.
Utilities

POSTED

1 day ago

DEADLINE

in 14 days

AI Contract Overview

Show more

This contract concerns a Military Construction Project (MILCON) P732 for design-bid-build services focused on electrical distribution system upgrades exclusively at the Gosport Substation located within the Norfolk Naval Shipyard (NNSY) in Portsmouth, Virginia. The project is solicited by the Department of Defense through the Naval Facilities Engineering Systems Command Atlantic (Navfacsyscom Atlantic) and falls under the NAICS code 237130, which pertains to power and communication line and related structures construction. Interested parties must review the full solicitation document and request detailed specifications directly via email from the designated contract specialist. The solicitation, identified by number N6247026R0015, was posted on December 31, 2025, with a response deadline set for March 2, 2026. There is no set-aside status applied to this procurement, meaning it is open to all qualified bidders. Primary and secondary points of contact are provided to assist with inquiries, ensuring clear communication for prospective contractors. The project is based in Portsmouth, Virginia, with the administrative office located in Norfolk, Virginia. This solicitation requires careful examination of the complete documentation and adherence to outlined requirements for submission within the designated timeframe.

General Info

Design-bid-build MILCON for electrical upgrades at Gosport Substation, Norfolk Naval Shipyard.

NAICS

237130 - Power and Communication Line and Related Structures Construction

Place of Performance

Portsmouth, VA, USA

Set-Aside

NONE

Documents

26

Amendment 0004 to Solicitation N6247026R0015

PDF, High priority: read this first13 pages · amendment
High

Amendment 0005 to Contract N40085-22-D-0047 for Electrical Distribution System Upgrades

PDF, High priority: read this first137 pages · amendment
High

Amendment 0005 to Task Order N6247024F4169 Electrical Distribution System Upgrades

PDF, High priority: read this first128 pages · amendment
High

Amendment ECN0002 for FY26 P-732 Electrical Distribution System Upgrades

PDF, High priority: read this first128 pages · amendment
High

Amendment N6247026R00150005 to Solicitation N6247026R0015

PDF, High priority: read this first15 pages · amendment
High

Attachment C - Past Performance Questionnaire

DOCX, High priority: read this first5 pages · past-performance
High

Attachment D Historical Small Business Utilization N62470-26-R-0015

PDF, High priority: read this first6 pages · supporting-document
High

Attachment G - Price Proposal Form Amendment 0005

PDF, High priority: read this first4 pages · price-proposal
High

Attachment G - Price Proposal Form for P-732 Electrical Distribution System Upgrades

DOCX, High priority: read this first4 pages · price-schedule
High

Attachment I - P732 EPA Bid Form

PDF, High priority: read this first1 page · bid-form
High

Davis-Bacon Act Wage Determination VA20250161

PDF, High priority: read this first8 pages · wage-determination
High

Davis-Bacon Act Wage Determination VA20250209 for Portsmouth County, VA

PDF, High priority: read this first6 pages · wage-determination
High

Pre-Proposal Inquiries for Solicitation N62470-26-R-0015 Electrical Distribution System Upgrades

XLSX, High priority: read this first6 pages · pre-proposal-inquiries
High

RFP N62470-26-R-0015 Small Business Participation Commitment Document

PDF, High priority: read this first3 pages · small-business-participation-commitment-document
High

Small Business Subcontracting Plan N62470-26-R-0015

PDF, High priority: read this first13 pages · subcontracting-plan
High

Solicitation N6247026R0015 for Electrical Distribution System Upgrades at Norfolk Naval Shipyard

PDF, High priority: read this first56 pages · ifb
High

Justification and Approval for SCADA Products Procurement N62470-25-R-0006

PDF, Low priority3 pages · justification-and-authorization
Low

Justification and Approval for Use of Other Than Full and Open Competition - SEL Devices for Norfolk Naval Shipyard

PDF, Low priority4 pages · justification-and-authorization
Low

PIEE Vendor Access Instructions Guide

PDF, Low priority7 pages · other
Low

Pre-Proposal Inquiry Submission Form for Solicitation N62470-26-R-0015

XLSX, Low priority1 page · pre-proposal-inquiry-log
Low

Amendment+0001.zip

ZIP

Amendment+0001.zip

ZIP

Amendment+0002.zip

ZIP

Amendment+0003.zip

ZIP

Attachment+B+-+Construction+Experience+Project+Data.docx

DOCX

Drawings.zip

ZIP

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

9 updates
PhaseClosed
Posted

Solicitation

Notice updated

The notice description changed.

Notice updated

The notice description changed.

Notice updated

Notice details unchanged. Attachments may have changed.

Notice updated

The notice description changed.

Notice updated

The notice description changed.

Notice updated

Response deadline changed from Mar 2, 2026 to Mar 18, 2026. The notice description changed.

Notice updated

The notice description changed.

Notice updated

Response deadline changed from Mar 18, 2026 to Apr 2, 2026. The notice description changed.

Notice updated

The point of contact changed.

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Start your free trial to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → Navfacsyscom Atlantic
Contacts2 people available
OfficeNORFOLK, VA, 23508-1278, USA
Office AddressNORFOLK, VA, 23508-1278, USA
Contacts

Full Description

Show more

READ THE ATTACHED SOLICITATION DOCUMENT IN ITS ENTIRETY.



YOU WILL NEED TO REQUEST THE SPECIFICATIONS VIA EMAIL AND SEND ALL PPIs TO THE CONTRACT SPECIALIST LISTED BELOW:


Daniel Rocha; daniel.r.rocha2.civ@us.navy.mil



Military Construction Project (MILCON) P732 Design-Bid-Build, Electrical Distribution System Upgrades (Gosport Substation Only) at Norfolk Naval Shipyard (NNSY) in Portsmouth, Virginia.



AMENDMENT 0001


1. Revise the Solicitation
2. Add Site Visit Information
3. Add Award Fee Information and Award Fee CLIN
4. Answer PPIs

 


The Following Attachments were added:
Attachment N - Award Fee Plan
Attachment O - SECNAV 5512
Attachment P - BLANK DBIDS or VISITOR REQUEST
Attachment Q - Approved Identity Proofing Documents
Attachment R - Criteria for Denying Access to Navy Installations



AMENDMENT 0002


1. Revise the Solicitation
2. Answer PPIs



AMENDMENT 0003


1. Add revised Specification "01 30 00.00 22" attachment
2. Answer PPIs
3. Add Site Visit Sign-in Roster


AMENDMENT 0004


1. Revise the solicitation
2. Remove Project Labor Agreement Requirement (PLA)
3. Extend the proposal due date to 18 March 2026


AMENDMENT 0005


1. Extend the proposal due date
2. Revise the solicitation section 00 70 00 - Conditions of the Contract
3. Answer PPIs
4. Revise Clause 52.211-12 Liquidated Damages-Construction.
5. Revise Clause 52.211-10 Commencement, Prosecution, and Completion of Work.
6. Revise Factor 3 - Schedule
7. Revise Attachment G - Price Proposal Form
8. Revise Specifications
9. Revise Drawings


THE PPI PERIOD IS NOT EXTENDED WITH THE SOLICITATION DUE DATE.

More opportunities from Department Of Defense → Navfacsyscom Atlantic

Same awarding agency

NAICS: 236220
New
Federal
Navy Child Development Centers (CDC) Industrialized Construction (IC) Projects via Other Transaction Authority (10 U.S.C. § 2808a)
Solicitation # N6247027R0003
The Department of the Navy, through Navfacsyscom Atlantic, is seeking commercial vendors to provide Industrialized Construction solutions for the modernization of 11 Child Development Centers. This effort is being conducted via Other Transaction Authority under 10 U.S.C. 2808a to leverage advanced manufacturing methods such as volumetric modularity hybrid or Kit of Parts. The primary objectives are to reduce overall design and construction costs by at least 20 percent and accelerate delivery timelines by 30 percent or more compared to traditional construction methods. Proposed structures must be capable of being designed, reviewed, and approved within a 9 to 12 month timeframe while meeting or exceeding DoD Unified Facility Criteria and Whole Building Design Guide standards. The acquisition process consists of two phases, beginning with a white paper submission due by November 6, 2026. Vendors must demonstrate relevant experience by detailing at least three completed industrial construction commercial projects from the last 10 years valued at $25 million each, or three institutional projects exceeding 25,000 square feet. The government will use these white papers to short-list vendors for a second phase involving a Request for Project Proposal, where full proposals will be evaluated for best value based on expanded technical approaches, detailed price and schedule estimates, and data rights. Successful awardees must comply with the Buy American Act, Davis Bacon Act, Miller Act, and Cybersecurity Maturity Model Certification.
Commercial and Institutional Building Construction

POSTED

5 days ago

DEADLINE

in 17 days
View Details

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS