Precast Envelope & Façade

Active
Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This subcontract for the General Services Administration involves the installation of the exterior skin for prime contractors at the St. Elizabeths West Campus in Washington, DC. The scope of work focuses on delivering a fully enclosed and weathered building envelope by installing a panelized precast envelope featuring in-laid brick, openings, flashings, sealants, doors, windows, and louvers. Due to the project location, work will be performed on a high-security federal campus that is also designated as a National Historic Landmark. This opportunity falls under NAICS code 238110 and is managed by the PBS Project Delivery Capital Construction Branch Northeast, with a response deadline of October 26, 2026.

General Info

GSA subcontract for exterior skin installation at St. Elizabeths West Campus, Washington DC.

NAICS

238110 - Poured Concrete Foundation and Structure Contractors

Place of Performance

Washington, DC, 20032, USA

Set-Aside

NONE

Documents

This scope was carved out of 47PB5126R0038 .

The full solicitation package (10 documents), including the RFP, is on the prime solicitation, not on this scope.

View the prime solicitation

Construction Services for the Gate 7 Parking Garage St. Elizabeths West Campus

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

Posted

subcontract

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyGeneral Services Administration → Pbs Project Delivery Capital Construction - Branch Northeast
ContactsNo contacts available
OfficeN/A
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
Installs the exterior skin for prime contractors on GSA/DHS facility projects at the St. Elizabeths West Campus. Installs panelized precast envelope with in-laid brick, openings, flashings, sealants, doors, windows, and louvers. Work is performed on a high-security federal campus and National Historic Landmark. Delivers a fully enclosed and weathered building envelope.

Similar Contracts

Same NAICS industry code

More opportunities from General Services Administration → Pbs Project Delivery Capital Construction - Branch Northeast

Same awarding agency

NAICS: 236220
New
Federal
Construction Services for the Gate 7 Parking Garage St. Elizabeths West Campus
Solicitation # 47PB5126R0038
The General Services Administration is seeking a qualified contractor for the construction of the Gate 7 Parking Garage at the St. Elizabeths West Campus in Washington, DC, to support the operational needs of the Department of Homeland Security. This firm-fixed-price project, estimated between 120 million and 160 million dollars, involves the design-bid-build construction of a multi-level parking garage featuring a classical architectural brick facade, a mechanically ventilated system, and associated surface parking. The comprehensive scope includes site development, utility relocations, structural framing, physical security elements such as vehicle barriers and gates, and extensive site improvements including landscaping and stormwater management. Because the project is located within a National Historic Landmark, the contractor must adhere to the Secretary of the Interior's Standards for Rehabilitation and the St. Elizabeths West Campus Preservation, Design and Development Guidelines. The procurement follows a two-phase acquisition process where the government evaluates demonstrated qualifications and historical performance in Phase 1 before proceeding to a best-value tradeoff evaluation in Phase 2. The performance period is approximately 595 to 655 calendar days, with liquidated damages set at 1,351.78 dollars per day. Key requirements include the submission of bid, performance, and payment bonds, as well as compliance with the Davis-Bacon Act and ABA Accessibility Standards. All personnel must pass security checks to work on the high-security federal campus. The contractor is responsible for providing all management, labor, and materials, including the delivery of final BIM and COBie asset data upon project closeout.
Commercial and Institutional Building Construction

POSTED

about 14 hours ago

DEADLINE

in 29 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement