This Solicitation opportunity from General Services Administration was posted on April 29, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
Binghamton New York First Floor Buildout Solicitation
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The General Services Administration (GSA) is soliciting proposals for the construction services required to complete the build-out of the first floor at the Binghamton Federal Building and U.S. Courthouse in Binghamton, New York. This project involves renovating approximately 3,015 square feet into a Sensitive Compartmented Information Facility (SCIF), including comprehensive interior work such as demolition, abatement, installation of walls, ceilings, doors, cabinetry, flooring, plumbing, electrical, IT infrastructure, fire protection, and mechanical systems. The construction documents have been prepared by N.K. Bhandari Architecture & Engineering, P.C. Key project elements include strict adherence to security protocols, coordination with GSA building management and security teams, and special conditions regarding site conduct and scheduling. Contractor qualifications are stringent: firms must have at least eight years of relevant experience with projects of similar size and complexity, including at least one SCIF construction project performed as the General Contractor, and three past performance projects each valued at a minimum of $1.5 million. The Project Manager and Superintendent must each have a minimum of eight years of experience, with a stipulation that the company owner cannot serve as the Project Manager. Amendments to the solicitation have extended the proposal due date to May 11, 2026, at 6 PM Eastern and have provided additional clarifications and responses to requests for information. A mandatory site visit is scheduled for April 14, 2026. All offerors must have an active System for Award Management (SAM) registration and comply with required certifications and representations when submitting proposals. This opportunity is set aside exclusively for small businesses under NAICS code 236220.
General Info
Agency
Contract Value
$2,252,566.5NAICS
Place of Performance
Binghamton, NY, 13901, USASet-Aside
Awardee
Award Issued Date
Timeline
Submission Closed
Organization & Contact Information
Full Description
Amendment 4:
The purpose of this amendment is to extend the due date for proposals to 5/11/2026 at 6PM Eastern.
Amendment 3:
The purpose of this amendment is to provide responses to RFIs.
As a result of this amendment:
1. REPLACE pages 2 and 3 only of Specification Section 000100 – Table of Contents with the attached. Section 081113 is not required. Section listed “224217” is a typo and should be changed to “224216”.
2. REPLACE page 1 only of Specification Section 011000 with the attached, which changes paragraph 1.1.B.1 - revised to read “Binghamton Federal Building & Courthouse 1 st Floor Build-Out”.
3. REPLACE Drawing Sheet AE600 with the attached revised Drawing Sheet AE600 with “Door Hardware Schedule” information included.
4. REPLACE Drawing Sheet AE-601 with the attached revised Drawing Sheet AE601, clarifying a typo on the Room Finish Schedule – “PNT4” should be “PNT2”.
The following Attachments are incorporated: 1. Specification Section 000100 – Table of Contents (pages 2 & 3) 2. Specification Section 011000 - Summary (page 1) 3. Drawing Sheet AE600 4. Drawing Sheet AE-601 5. 47PC5326R0002 RFI Responses Binghamton 1st Floor Build-out
The due date for proposals is extended to May 4, 2026 at 4:00 PM Eastern.
Amendment 2:
The purpose of this amendment is to extend the due date for proposals to 5/1/2026.
This will allow time to provide responses to questions received. An additional amendment will be forthcoming with the responses to questions received.
Amendment 1:
The purpose of the amendment is to include the SF1442 and the site visit sign in sheet.
Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see FAR 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for
Award Management. Offerors shall also submit with their proposal, the completed provisions identified in Section IV
of the solicitation.
_________________
The General Services Administration (GSA), Public Buildings Service, Upstate Service District, intends to procure construction services for the build-out of the 1st Floor at the Binghamton Federal Building and U.S. Courthouse, located at 15 Henry Street, Binghamton, New York 13901.
Site Visit is scheduled for Tuesday, April 14, 2026.
This project involves the furnishing of all materials, equipment, labor, and supervision to complete the work described in the contract documents, including drawings and specifications developed by N.K. Bhandari Architecture & Engineering, P.C.
The total renovated space is approximately 3,015 Sq. Ft. and will be constructed as a Sensitive Compartmented Information Facility (SCIF). Base interior work includes, but is not limited to: demolition, abatement, new walls, hard ceiling, doors, casework, woodwork, flooring, plumbing, electrical, IT, fire protection, and mechanical work.
Qualification Requirements
Interested contractors must meet the following minimum qualifications:
- Experience: Minimum 8 years of successful experience in comparable projects (size, complexity, and scope).
- Past Performance:
- All three required past performance projects must have a minimum award value of $1,500,000.
- At least one of the three required past performance projects must be SCIF construction, performed as the General Contractor.
- Key Personnel Experience: The Project Manager and Superintendent must each have a minimum of 8 years of experience in their respective positions.
- Prohibition: The Company owner may not serve as the Project Manager.
Special Requirements
The contractor must adhere to the following special conditions:
- Security: All personnel must meet HSPD-12 security requirements and any additional customer agency requirements.
- Site Conduct: Cell phones and transmittal devices are prohibited on the project site.
- Scheduling: Loud or disruptive work must be performed off-hours at no additional cost to the Government.
- Coordination: The Contractor is responsible for coordinating all building shut-offs and roof penetrations with GSA Building Management and the Security Division Access Control (SDAC).