Remodeling of GYM at the U.S. Embassy Marine House
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
The project involves the remodeling and expansion of the Gym/Fitness room at the U.S. Embassy Marine House in Vienna, increasing the existing area from 55m2 to 62m2 by demolishing the bathroom and a wall cabinet. The general contractor will be responsible for both construction work and electrical installation. Key demolition tasks include removal of partition walls, doors, wall coverings, existing bathroom fixtures including tiles, sanitary equipment, plumbing, PVC flooring, and ceiling lights. The refurbishment phase covers plastering, leveling, cleaning, priming, and painting walls and ceilings, as well as grinding and leveling the floor with the installation of new PVC flooring in the renovated area. Six new ceiling lights will be delivered, installed, wired, and integrated into the existing electrical system, followed by final cleaning. The project must be conducted without disturbing ongoing facility operations or the presence of residents, while adhering strictly to USG security regulations and clearance procedures for personnel, vehicles, and materials. Safety and protective measures are mandatory throughout the work. The construction is scheduled to take place over an indicative period of five weeks in the fall of 2026. The solicitation is managed by the U.S. Embassy Vienna’s Department of State office, with contact points provided for project inquiries.
General Info
Agency
NAICS
Place of Performance
Vienna, AT-9, AUTSet-Aside
Documents
(0)AI Contract Breakdown
Uniform Contract FormatNo contract breakdown available.
Cannot generate Contract Breakdown because no documents were found from this contract's source.
Timeline
Response Deadline
Organization & Contact Information
Full Description
This project is for the remodeling of the Gym/Fitness room at the U.S. Embassy Marine House, located in 1190 Vienna.
The old room structures and surfaces need improvement and renovation. The existing GYM will be expanded from 55m2 to 62m2, and the bathroom and a wall-cabinet will be demolished for this purpose.
Scope of work: General Contractor for Construction work and Electrical Installation
Demolition
- Temporary plasterboard dust wall with door.
- Demolition of partition walls (10cm), incl. wall coverings, 2 wooden doors+ doorframes and 1 wooden cabinet, electrical installation and equipment, incl. removal and disposal.
- Demolition, removal and disposal of the existing wall- and floor tiles and in the bathroom, existing sanitary items and equipment in the bathroom, including pipes, and the
PVC flooring incl. glue. - Removal of 4 existing ceiling lights.
Refurbishment
- Walls and ceiling: plaster, level, clean, prime, paint to cover, incl. 16m2 floor covering material.
- Floor: Clean, grind and level the floor; New PVC flooring in the demolition area.
- Delivery and assembly of 6 new ceiling lights in new position, Including switch, wiring, and integration into the existing system.
- Final cleaning
Special requirements
- The work will be carried out while the facility remains in operation and in the presence of the residents, who should not be disturbed during the construction work
- USG Security regulations
- Clearance process for employees, cars, material on site
- Safety and protective measures
Execution periods
Indicative construction schedule: 5 weeks in fall 2026