This Solicitation opportunity from Department Of Defense was posted on March 18, 2021. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

Simplified Acquisition of Base Engineering Requirements (SABER)

Closed
FA820121R0007Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 236220
New
Construction of the Recharge Master Plan Update Basin Improvements Project Montclair Basin Improvements
Solicitation # construction-recharge-master-plan-update-basin-improvements-project-montclair-basin-improvements-2
The Construction of the Recharge Master Plan Update Basin Improvements Project Montclair Basin Improvements is a solicitation issued by RT Contractor Corp for the Inland Empire Utilities Agency. This project, located in California with a specific performance area in Riverside or Los Angeles, focuses on basin improvements under NAICS code 236220. The solicitation was posted on October 19, 2026, with a response deadline of November 4, 2026. This opportunity is specifically set aside for Disadvantaged Business Enterprises (DBE) as defined by the Department of Transportation. To secure project financing, the Inland Empire Utilities Agency requires strict adherence to expanded DBE Good Faith Effort (GFE) guidelines. Bidders must provide proof of utilizing SBA and MBDA services and demonstrate that solicitations were posted in an online publication for 30 consecutive days and in a newspaper for at least one day prior to the bid opening. Failure to include this documentation within the bid package will result in the proposal being deemed non-responsive. While outreach documentation may be submitted up to three business days after the closing date, all other mandatory GFE requirements must be met by the opening date to ensure compliance.
RT CONTRACTOR CORP

POSTED

about 4 hours ago

DEADLINE

in 15 days
NAICS: 236220
New
P084 NEXT GENERATION TORPEDO INTEGRATION LAB & P1016 Consolidated RDT&E Systems Facility – Newport, RI
Solicitation # p084-next-generation-torpedo-integration-lab-p1016-consolidated-rdte-systems-facility-newport-ri
J&J Contractors, Inc. is soliciting bids for the construction of the Next Generation Torpedo Integration Lab and the P1016 Consolidated RDT&E Systems Facility in Newport, Rhode Island. The project involves the development of a 12,920 square foot multi-story steel frame laboratory and office facility, as well as an optional 17,978 square foot laboratory facility. Construction features include shallow foundations, metal standing seam roofs, and exterior walls composed of masonry and metal panels. The scope of work encompasses comprehensive site preparations, including landscaping, parking, exterior lighting, and the installation of underground stormwater retention and utility systems. Additionally, the project requires the demolition of Building 1272T, a 548 square meter engineering facility. Pricing is requested across a wide array of trades, including demolition, abatement, concrete, masonry, structural and miscellaneous metals, millwork, roofing, drywall, flooring, painting, elevator installation, fire protection, plumbing, mechanical, electrical, sitework, and crane services. This is a small business set-aside solicitation subject to Davis Bacon Wage Rates and is exempt from sales tax. Interested parties must contact the primary point of contact to receive bid invitations and documents via Building Connected. The response deadline for this solicitation is November 30, 2026.
J&J CONTRACTORS, INC.

POSTED

about 4 hours ago

DEADLINE

in about 1 month
NAICS: 236220
New
CITY OF GREENFIELD WASTEWATER TREATMENT PLANT UPGRADE PROJECT
Solicitation # city-greenfield-wastewater-treatment-plant-upgrade-project
The City of Greenfield Wastewater Treatment Plant Upgrade Project involves the construction of a new 2.0 million gallons per day facility located on the northeast end of Walnut Avenue in Greenfield, California. The project scope is divided into four distinct phases: site preparation involving soil stabilization and utility relocation; construction of the plant including a packaged Membrane Bioreactor treatment plant, headworks, UV disinfection, and SCADA systems; decommissioning and demolition of existing facilities; and the completion of finish facilities including the Walnut Avenue extension. The total duration for the project is 915 calendar days, with a critical requirement to maintain existing plant services and regulatory compliance throughout the first two phases. Managed by C. Overaa & Co., the solicitation is open to various small and disadvantaged business enterprises, including DBE, SDVOSB, and WOSB. A significant local hiring goal requires that 50 percent of the total construction workforce be residents of Monterey, San Benito, or Santa Cruz counties. Subcontractors must utilize the Textura electronic system for invoicing and payments and are required to accept the standard Overaa agreement without modification. Key milestones include a mandatory pre-bid meeting on October 5, 2026, with bid submission deadlines listed as either October 28 or November 10, 2026.
C. Overaa & Co.

POSTED

about 4 hours ago

DEADLINE

in 21 days
NAICS: 236220
New
P1102 Weapons Magazine and Ordnance Operations Facility, Naval Submarine Base New London, Groton, Connecticut
Solicitation # p1102-weapons-magazine-ordnance-operations-facility-naval-submarine-base-new-london-groton
This solicitation issued by J & J Contractors, Inc. seeks pricing for the P1102 Weapons Magazine and Ordnance Operations Facility project at the Naval Submarine Base New London in Groton, Connecticut. The project has a duration of 1828 calendar days and involves the construction of six Containerized Long Weapons Storage units, two Box G magazines, and one Box H earth-covered high-explosive magazine. The scope includes comprehensive site work such as clearing, rock excavation, grading, and wetland mitigation, as well as the construction of an Ordnance Operations building, a Truck Inspection area, and a Sentry building. Demolition of 18 existing magazines and buildings 524 and 393 is also required. Technical requirements encompass a wide range of trades including demolition, abatement, concrete, structural steel, roofing, electrical, plumbing, and mechanical systems. Specialized construction features include rigid inclusions, load transfer mats, grounding and lightning protection, and intrusion detection systems. The project also involves installing primary and secondary electrical distribution, telecommunications infrastructure, access roads, and landscaping. This opportunity is set aside for various small business categories, and interested parties must contact the primary point of contact by the October 31, 2026, deadline to receive bid documents.
J & J Contractors, Inc

POSTED

about 4 hours ago

DEADLINE

in 11 days

General Info

Contract Value

$1,018,525.77

NAICS

236220 - Commercial and Institutional Building Construction

Place of Performance

Hill AFB, UT, 84056, USA

Set-Aside

8A

Award Issued Date

Documents

31

Asbestos+and+LBP+Report_Bldg+100+Bay+N_O_P++Modify+Exterior_+Install+Comm+Room.pdf

PDF

Attachment+01+-+SABER+Basic+SOW.pdf

PDF

Attachment+02+-+SABER+TEP+Matrix.xlsx

XLSX

Attachment+03+-+Architectural+Compatibility+Plan+%28ACP%29.pdf

PDF

Attachment+04+-+Base+Facility+Design+Standard+19+OCT+2020.pdf

PDF

Attachment+05+-+Hill+AFB+Construction+and+Demolition+Waste+Diversion+Report.pdf

PDF

Attachment+06-+Bona+Fide+Office+Requirements.pdf

PDF

Attachment+07-+Wage+Determination+-+Box+Elder+County+-+1+Jan+2021.pdf

PDF

Attachment+08-++Wage+Determination+-+Daggett-Duchesne-Rich-Summit+Counties+-+1+Jan+2021.pdf

PDF

Attachment+09-+Wage+Determination+-+Morgan-Weber+Counties+-+1+Jan+2021.pdf

PDF

Attachment+10-+Wage+Determination+-+Sublette+County+WY+-+1+Jan+2021.pdf

PDF

Attachment+11-+Wage+Determination+-+Davis+County+-+1+Jan+2021.pdf

PDF

Attachment+12+-+Wage+Determination+-+Salt+Lake+County+-+1+Jan+2021.pdf

PDF

Attachment+13+-+Seed+Project+SOW+-+Bldg.+100.pdf

PDF

Attachment+14+-+Seed+Project+Pricing+Matrix.xlsx

ZIP

Attachment+15+-+SABER+Section+L.pdf

PDF

Attachment+15+-+SABER+Section+L_Revision+1.pdf

PDF

Attachment+16+-+SABER+Section+M.pdf

PDF

Bldg.+100+Existing+Steam+Pipe+Sizes.pdf

PDF

Bldg.+100-Landscape+Symbols.pdf

PDF

Bldg.+100+Utilities+%282%29.JPG

JPG

Bldg+100+Utilities.png

PNG

Government+Responses+SABER+Question+Comment+Matrix+31121.xlsx

XLSX

Government+Responses+SABER+Question+Comment+Matrix.xlsx

XLSX

Government+Responses+to+Follow+up+Questions_03162021.xlsx

XLSX

HAZMAT+Info+to+Provide+to+Hill+AFB.xlsx

XLSX

SABER+Consolidation+DF.pdf

PDF

SABER+Question-Comment+Matrix.xlsx

XLSX

SABER+Site+Visit+Attendees.xlsx

XLSX

Solicitation+Amendment+-+FA8201-21-R-0007-0001.pdf

PDF

Solicitation+-+FA820121R0007.pdf

PDF

AI Contract Breakdown

Uniform Contract Format

Contract not broken down yet

CLEATUS splits the solicitation into Uniform Contract Format (UCF) sections: scope, pricing, deliverables, and evaluation criteria.

Timeline

11 updates
PhaseClosed
Posted

Presolicitation

Notice updated

The notice description changed.

Notice updated

The notice description changed.

Notice updated

Notice type changed from Presolicitation to Special Notice. The notice title changed. The notice description changed. The point of contact changed.

Notice updated

Notice type changed from Special Notice to Solicitation. Response deadline added: Mar 9, 2021. The notice title changed. The notice description changed. The point of contact changed.

Notice updated

Response deadline changed from Mar 9, 2021 to Mar 19, 2021. The notice description changed.

Notice updated

The notice description changed.

Notice updated

The notice description changed.

Notice updated

The notice description changed.

Notice updated

The notice description changed.

Notice updated

The notice description changed.

Notice updated

The notice description changed.

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Start your free trial to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → FA8201 Afsc Ol H Pzio
Contacts2 people available
OfficeHILL AFB, UT, 84056-5805, USA
Office AddressHILL AFB, UT, 84056-5805, USA

Full Description

Show more
UPDATE: MARCH 18, 2021 For offerors that are hand delivering their proposals, please input the following coordinates into Google Maps for an exact location of our building. Drop-off Coordinates 41.1267078, -112.022215 We have recently discovered that our building address 6038 Aspen Ave. Bldg 1289NE takes you to the incorrect location when input into Google Maps. If you have any issues finding the location, please call the POCs on this posting. UPDATE: MARCH 17, 2021 This update is to provide a single question and answer that was left off the latest Q&A Matrix. The question and answer is as follows: Q: Would the Government like us to correct the feed for the sprinkler heads with continuous 1 pipe and remove the fittings and pipe? A: Yes. There should be approximately 5-6 feet of piping involved to accomplish this task. UPDATE: MARCH 16, 2021 This update is to provide the following information and clarifications: If you are a Prime contractor planning to submit a proposal for this requirement, please email the POCs listed on this posting to inform them of the method of delivery (shipping or hand-delivery), the day it will be delivered, and the approximate time. This information will help us ensure that someone is available to receive your proposal. If you have already shipped or delivered any portion of your proposal, please let us know when and how it was delivered. City Light and Power (CLP) will need to be involved because of the high voltage power lines running through that vault. The Prime may hire CLP to do all work associated with their power lines OR they can hire an independent contractor to perform all work CLP determines needs to be done and have CLP perform the inspections and connections and pay CLP for these services. This information can be found in the Basic SOW, Section 35.2, page 32 of 66. The government is aware that utilities may be in the way of the - proposed location of the steam vaults. Final location will be determined once a complete evaluation of the area has been accomplished by the Civil Engineering Red Stakes Office, City Light & Power, American Water and the Communication Squadron. Once an evaluation of the area is complete, all attempts will be made to prevent the relocation of these utilities. IAW the Seed Project SOW 4.5 a) - The contractor shall demo steam/condensate piping and all associated components to facilitate new piping in vault. In regards to this, the connection will be outside, not inside the building. The final responses from the Government to follow-up questions is attached and titled "Government Responses to Follow-Up Questions_03162021" UPDATE: MARCH 11, 2021 This update is to provide the official amendment to the solicitation and the revised Attachment 15: Section L. The documents included as part of this update are the following: Official amendment to the Solicitation - FA8201-21-R-0007-0001 Revised Section L - Attachment 15 Section L - Revision 1 UPDATE: MARCH 11, 2021 This update is to provide offeror-requested documents and to provide a complete version of the Q&A matrix. Previous responses to the Q&A may have been updated or further clarified, therefore a complete review of the matrix may be necessary. The documents included as part of this update are the following: Government Responses SABER Question Comment Matrix Bldg 100 Exisiting Steam Pipe Sizes Bldg 100 Utilities Bldg 100 Utilities Bldg 100 Landscape Symbols UPDATE: MARCH 8, 2021 This update is to provide offeror-requested documents and extend the proposal due date to March 19, 2021. The Government responses to the questions are nearly complete; however there are still a few unanswered questions in the attachment. The Government intends to have all questions answered NLT, March 12, 2021. An official modification to the solicitation will be posted later this week. The documents included as part of this update are the following: Government responses to Questions and Comments Asbestos and Lead Based Paint Report Site Visit Attendee Sheet HAZMAT Information ORIGINAL POSTING NOTICE: This is the official Request for Proposal (RFP) for the Simplified Acquisition of Base Engineering Requirements (SABER) construction services at Hill AFB, UT. DESCRIPTION: The purpose of this solicitation is to establish the SABER contract which is an Indefinite-Delivery, Indefinite-Quantity (IDIQ), covering a broad range of maintenance, repair and minor construction work on various real property facilities managed by the 75th Civil Engineering Group (CEG) at Hill Air Force Base (HAFB). In addition to Hill AFB, project locations may also include, but are not limited to, Little Mountain, Utah; Utah Test and Training Range (UTTR); and Wyoming. Task Orders (TO) shall be issued under this contract to define specific project requirements. The SABER contract is set aside for 8(a) Small Business. Attached to this posting is the Solicitation and all accompanying attachments. Please review all attachments for additional information regarding SABER requirements. All current and future information concerning this effort will be posted under this solicitation number. RESPONSES: All proposals are due no later than March 9, 2021 at 4:00 PM MST. A site visit for the Seed Project will be held on Feb 17, 2021 at Hill AFB, UT. Offerors are required to attend the site visit in order to propose on the contract. Offerors are required to RSVP for the site visit no later than Feb 8, 2021 by 4:00 PM MST. Only those offerors that RSVP will be allowed to attend the site visit. Due to current COVID-19 restrictions, the Government will limit the number of personnel from each company to 10 individuals. This includes any subcontractors a company may bring. Additional information regarding the site visit, such as directions and instructions for COVID-19 precautions, will be sent to offerors after the RSVP date. At this time, the Government plans to schedule specific times throughout the day of the site visit for each company. This will be done to keep group numbers at or below 15. Also attached to this posting is a Question and Comment Matrix. Please utilize this attachment when submitting questions and comments. All questions are due no later than February 23, 2021 at 4:00 PM MST. However, the Government encourages offerors to submit questions as soon as possible, in order to ensure the Government has adequate time to respond. Government responses to questions will be attached to this posting on approximately March 2, 2021. If questions are proprietary in nature, please indicate on the Question and Comment Matrix. Questions shall be submitted via email to the POCs listed on this posting. Due to beta.sam.gov not allowing Microsoft Access Database attachments, please contact the Government POCs and a copy of the Past Performance Information (PPI) Tool will be emailed to your company. The PPI Tool is required to submit your Past Performance Information. Government Points of Contact Brad Conroy, Contract Specialist, Email: bradley.conroy@us.af.mil Brady Smith, Contracting Officer, Email: brady.smith@us.af.mil

More opportunities from Department Of Defense → FA8201 Afsc Ol H Pzio

Same awarding agency

NAICS: 238990
New
Federal
Hill AFB Painting ID/IQ Sources Sought
Solicitation # FA8201-27-R-Painting-HAFB
The Department of Defense is conducting market research to establish an Indefinite-Delivery/Indefinite-Quantity (IDIQ) contract for a broad range of maintenance, repair, and minor construction painting projects. The work will be performed at Hill Air Force Base, Little Mountain, and the Utah Test and Training Range. The anticipated contract structure includes a five-year base ordering period with a six-month option to extend, with an estimated maximum contract value of 5,500,000 dollars. The government is specifically interested in identifying qualified 8(a) Small Business concerns under NAICS code 238990. The scope of work requires the contractor to provide all labor, materials, and supervision for interior and exterior painting, including the application of primer and latex paints, wall covering removal and installation, and the application of stenciling and safety markings. All work must adhere to Federal Standard 595B for colors and specific architectural compatibility standards for Hill Air Force Base. Key personnel requirements include a Project Manager, Project Superintendent, and Quality Control/Safety personnel. Contractors must comply with rigorous safety and security protocols, including explosive safety briefings, hazardous material handling for lead paint, and strict base access requirements for personnel. Interested offerors must be registered in SAM.gov and submit a capability statement in PDF format, limited to ten pages, by 2:30 PM MST on 29 October 2026. Submissions must be sent via email with the subject line Painting Sources Sought, FA8201-27-R-Painting-HAFB and include company information, socioeconomic status, and a description of the ability to provide emergency response personnel within two hours of notification.
All Other Specialty Trade Contractors

POSTED

4 days ago

DEADLINE

in 9 days
View Details
NAICS: 812332
New
Federal
Industrial Laundering - Hill AFB
Solicitation # FA8201-NAF-Laundry
Hill Air Force Base and AFSC OL_H/PZIOA are conducting market research via a Request for Information to identify capable vendors for consolidated laundry, dry cleaning, industrial uniform, shop towel, and first aid replenishment services in support of the 75th Force Support Squadron. The scope of work includes the laundering of hospitality linens, work uniforms, and industrial protective clothing, as well as the provision of floor mats, mops, and ambient air freshener services. Performance is required at multiple locations across Hill AFB, including Air Force Inns Lodging, Auto Hobby, The Landing Club, and the Hubbard Memorial Golf Course. The government anticipates a Firm-Fixed Price contract structure with a 12-month base period, four one-year options, and a potential six-month extension. This is a Nonappropriated Fund procurement executed under DAFMAN 64-119, meaning standard FAR-based small business set-aside programs do not apply, although the anticipated NAICS code is 812332. The contractor must adhere to Service Contract Labor Standards for Davis County, Utah, and maintain a comprehensive Quality Control Program. Deliveries are FOB Destination with a standard 48-hour turnaround. Interested firms must submit a technical capabilities statement of no more than five pages by 1400 MST on 21 October 2026. The formal Request for Proposal is expected to be released on or about 27 October 2026.
Industrial Launderers

POSTED

6 days ago

DEADLINE

in 1 day
View Details

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS