Titan II Battery Energy Storage System and Imperial Irrigation District R-Line Upgrades Project

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

Titan II, LLC is seeking to modify an existing conditional use permit to install a 40-megawatt battery energy storage system and a corresponding gen-tie line that will connect to the Imperial Irrigation District’s existing 92 kV R-Line. Simultaneously, the project includes comprehensive upgrades to a 34-mile segment of the R-Line between the Dixieland and Anza substations, involving the replacement of aging wooden transmission poles with steel monopoles of similar height to improve system reliability, increase capacity, and mitigate vulnerabilities from severe weather. The majority of the upgrades will occur within the current right-of-way, but expansion will be necessary in select areas where the existing corridor is too narrow, requiring coordination with the Bureau of Land Management for a right-of-way grant on federally managed lands and temporary construction access. As a federal action, the transmission line upgrades are subject to environmental review under the National Environmental Policy Act, necessitating submission of a Standard Form 299 and a Plan of Development to BLM. The project comprises two interdependent components: the conditional use permit modification for the battery storage system and the broader infrastructure improvements to the R-Line, both aimed at enhancing grid resilience and supporting future energy needs in Imperial County.

General Info

Titan II, LLC to upgrade 34-mile R-Line with steel poles and add 40MW battery storage, requiring federal environmental review.

Agency

California → Imperial County

NAICS

237130 - Power and Communication Line and Related Structures ConstructionView NAICS

Place of Performance

Various; see Attachment A, CA, 92004

Set-Aside

NONE

Documents

(4)

Notice of Preparation for Titan II Battery Energy Storage System EIR

PDFpresolicitation

Attachment A Supplemental Information for NOC - Project Location and Parcel Details

PDFsupplemental-information

Initial Study and Notice of Preparation for Titan II Battery Energy Storage System and IID R-Line Upgrades Project

PDFinitial-study

Notice of Completion for Titan II Battery Energy Storage System Project

PDFnotice-of-completion

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Imperial County
Contacts3 people available
OfficeN/A
Organization / Agency
California → Imperial County
Office AddressN/A
Contacts
Sharyn HidalgoProject Manager
Jurg HeubergerProject Manager

Interested Companies (1)

Show more
HDR
Denver, Colorado

Full Description

Show more
The project applicant, Titan II, LLC, is currently requesting to modify a previously- approved conditional use permit (CUP) (CUP #17-0006) to add a 40 megawatt battery energy storage system (BESS) and gen-tie line to interconnect with the existing Imperial Irrigation District’s (IID) R-Line on APN 018-170-067 (CUP #22-0003). The proposed project would also include replacing and upgrading equipment along an approximately 34-mile segment of the existing IID 92 kV R-Line, between the Dixieland Substation and Anza Substation. The R-Line upgrades are planned in order to address long-term integrity of the system as well as capacity and maintenance issues associated with the existing R-Line, which among others, is susceptible to further deterioration and damage from high wind events and/or storms. Generally, the R-Line upgrades would involve replacing existing wooden transmission poles that are approximately 50 to 80 feet in height with steel monopoles. The new steel pole structures would be of similar height, ranging from approximately 50 to 80 feet. The transmission line route traverses private land as well as federal land under the jurisdiction of Bureau of Land Management (BLM). The majority of the proposed transmission line upgrades would be located within the existing transmission line alignment and right-of-way (ROW); however, in a few areas, the existing ROW is very limited/narrow and will need to be expanded to accommodate the improvements. Accordingly, the project applicant is seeking an ROW grant from BLM to authorize expansion of the existing ROW on BLM-managed lands, as well as temporary access required to support construction activities. In order to process the requested authorization, the project applicant would be required to submit a Standard Form 299 (SF 299) Application and an associated Plan of Development to BLM. Review and approval of the ROW application constitutes a federal action; therefore, the proposed R -Line upgrades would be subject to environmental review in accordance with the National Environmental Policy Act and applicable BLM implementing regulations and guidance. The proposed project consists of the following components: 1) Modification to CUP #17-0006 to add the BESS and gen-tie line to interconnect with the R-Line (CUP #22-0003), and 2) Upgrades to the IID’s R-Line.

Similar Contracts

Same NAICS industry code

NAICS: 237130
New
Kittrell Job Corps Center-12 Strand Fiber Optic Replacement- Bldg 2, Bldg 3, Bldg 4
Solicitation # kittrell-job-corps-center-12-strand-fiber-optic-replacement-bldg-2-bldg-3-bldg-4
Covenant Learning Solutions, operator of the Kittrell Job Corps Center in North Carolina, is soliciting sealed bids for the replacement of 12-strand aerial fiber optic cables and associated connectors between Buildings 2, 3, and 4. The contractor is responsible for providing all labor, materials, equipment, and supervision to install outdoor-rated fiber optic cable along existing aerial pathways and terminate them into existing network switches. A critical requirement of this project is that the existing network service must remain fully operational without interruption until the owner authorizes the final switch-over. The contractor must also provide a construction timeline for approval during a pre-construction meeting and adhere to standard work hours of 8:00 AM to 3:00 PM, Monday through Friday. The project requires strict adherence to industry standards, local codes, and manufacturer specifications regarding cable support and bend radius. Acceptance is contingent upon successful Optical Loss Testing, OTDR testing, continuity testing, and polarity verification, as well as the submission of a complete closeout package with as-built documentation. Bidders must hold a valid North Carolina General Contractor license and maintain all necessary Builder's Risk and Liability insurance. Proposals must be submitted via email to Rachelle Judkins by September 30, 2026, and must include a completed Mandatory Bid Document. Payment will be issued as a single lump sum upon project completion, provided all required purchasing documentation is submitted.
Covenant Learning Solutions operator of Kittrell Job Corps Center

POSTED

about 9 hours ago

DEADLINE

in 7 days
View Details
NAICS: 237130
New
Federal
Sources Sought for the Recapitalization of the Navy’s High Voltage (230kV) Transmission Loop and all Ancillary Equipment at Naval Submarine Base Kings Bay, GA
Solicitation # N69450-26-R-PW20
This sources sought notice seeks to identify qualified offerors for the wholesale recapitalization and cybersecurity hardening of the 230kV high voltage transmission loop and all ancillary equipment at Naval Submarine Base Kings Bay, Georgia. The project is envisioned as a design-build effort with an estimated magnitude between $100 million and $250 million and an anticipated period of performance of approximately 900 calendar days. Key technical requirements include the relocation of the high power loop and crossing tower, replacement of conductors, installation of smart motor-operated disconnects and vacuum/SF6 circuit breakers, and the modernization of substation digital protective relays. All telemetry and relay configurations must comply with NERC CIP standards and DoD Unified Facilities Criteria 4-010-06 for Industrial Control Systems. Due to the critical nature of the nuclear deterrent mission and the requirement for seamless integration with the Georgia Power Company (GPC) macro-grid, the government is considering this procurement under other than full and open competition. Potential sources must demonstrate significant financial capability, including a single project bonding capacity of $200 million, and possess specialized experience in 230kV live cutovers and cryptographic SCADA telemetry interconnection. Security requirements are stringent, requiring U.S. citizenship and at least Tier 3/Secret clearance for key personnel, including project managers and cybersecurity leads, to access restricted areas such as nuclear-support zones and the Defensive Ordnance Support Facility. Responses are due by 2:00 PM EDT on October 6, 2026, under NAICS codes 237130 or 221122.
Navfacsyscom Southeast

POSTED

1 day ago

DEADLINE

in 14 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS