Trancas Creek Bridge Replacement Project

Forecast
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The Trancas Creek Crossing Permanent Waterline (Phase II) project, managed by Caltrans District 7 and Los Angeles County Waterworks District No. 29, is located in Malibu, California, along the Pacific Coast Highway between Guernsey Avenue and Trancas Canyon Road. The scope of work involves the installation of approximately 400 linear feet of permanent 18-inch steel waterline and the removal of approximately 420 linear feet of temporary 16-inch High-Density Polyethylene bypass watermain. This project is integrated into the broader State Route 1 Trancas Creek Bridge Replacement project and adheres to the Environmental Reevaluation and Mitigated Negative Declaration adopted by Caltrans. The project is compliant with the established Environmental Commitment Record and Mitigation Monitoring program, and a Notice of Determination dated September 3, 2025, confirms that no further environmental documentation under CEQA is required. The work falls under NAICS code 237110 for heavy and civil engineering construction.

General Info

Caltrans and LACWWD installing 400ft steel waterline and removing bypass main in Malibu.

Agency

California → Caltrans, District 7 - Los Angeles

Place of Performance

PC H & Trancas Canyon Rd, Malibu, CA, 90265

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseForecast
Posted

forecast

Prepare for this forecast

Research the agency, track this forecast, and prepare your capture plan before the solicitation opens.

Organization & Contact Information

Show more
AgencyCalifornia → Caltrans, District 7 - Los Angeles
Contacts2 people available
OfficeN/A
Organization / Agency
California → Caltrans, District 7 - Los Angeles
Office AddressN/A
Contacts
Eduardo MaguinoCivil Engineer
Jack HustedSr. Civil Engineer

Full Description

Show more
The project consists of installing approximately 400-linear-feet of permanent 18-inch steel waterline and removing approximately 420-linear-feet of temporary 16-inch High-Density Polyethylene bypass watermain. The project and related recommended actions are within the scope of the project in the Environmental Reevaluation/Addendum to the Mitigated Negative Declaration/Finding of No Significant Impact (MND) prepared and adopted by Caltrans as lead agency for their State Route 1 Trancas Creek Bridge Replacement project previously reviewed and considered by the Los Angeles County Board of Supervisors on June 9, 2020. The proposed Trancas Creek Crossing Permanent Waterline (Phase II) project is within the assumptions for construction and operation analyzed in the Addendum to the MND, which described the installation and proposed removal of the temporary bypass pipe.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project for the City of Belmont, North Carolina, involves the construction of 16,435 linear feet of new 20-inch ductile iron force main and significant upgrades to the Morgans Branch Pumping Station. The scope of work includes installing a new wet well and valve vault with associated appurtenances, as well as the demolition of existing pumps and piping. The project has an estimated value of 16,690,000 dollars and a performance period of 560 calendar days following the issuance of a Notice to Proceed. The contract is administered using EJCDC standard forms and will be awarded to the responsible bidder submitting the lowest responsive bid. Key requirements for bidders include the submission of bid security, evidence of authority to sign, and specific M/WBE compliance documentation, including a Good Faith Efforts Form and Table A. Participation goals are set at 10.9 percent for MBE and 10.4 percent for WBE per EPA guidelines, with a combined state goal of 10 percent. The contractor must provide performance and payment bonds, maintain insurance from providers with an A.M. Best rating of A-VII or better, and adhere to OSHA fall protection and various technical standards, including AWS D1.2 for welding and NEMA MG1 for motors. Payment will be processed in equal monthly amounts via EJCDC C-620 applications, with a 200,000 dollar contingency allowance available for authorized additional work.
Don Moorhead Construction, Inc.

POSTED

about 7 hours ago

DEADLINE

in about 18 hours
View Details
NAICS: 237110
New
Jefferson St. Pump Station Replacement
Solicitation # ITB-2026141
The City of Winchester is soliciting bids for the Jefferson Street Pump Station Replacement project in Virginia under solicitation ITB-2026141. The scope of work includes the construction of a new pump station featuring a precast concrete building, controls, and a standby generator, as well as site electrical work, yard piping, security fencing, grading, and paving. Additionally, the project requires the relocation of an existing fuel tank and the demolition of existing facilities. All work must be completed within 610 calendar days following the Notice to Proceed, with adherence to VDOT 2020 Road and Bridge Specifications and the City of Winchester Standards Manual. WG Construction is seeking MBE/WBE subcontractor participation for paving, material supply, site development, fencing, MEP, roofing, and carpentry. Bids are due by 2:00 pm on November 12, 2026, via the City's e-Procurement Portal. The contract will be awarded to the lowest responsive and responsible bidder based on qualifications, compliance, and pricing. Requirements include a 5 percent bid guarantee, performance and payment bonds equal to 100 percent of the contract amount, and compliance with Davis-Bacon wage determinations and OSHA safety standards. Bidders must provide a minimum of three similar project references and confirm they are not on any government debarment lists.
WG Construction Co., Inc.

POSTED

about 7 hours ago

DEADLINE

in about 18 hours
View Details

Prepare for this forecast

Research this forecast and prepare for the solicitation

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS