The UPRR Valley Subdivision MP 239.83 Bridge Repair Project, identified by solicitation number 5A52CR00258, involves the repair of pier 6 at Milepost 239.83 in California. The scope of work includes installing steel sheet-pile forms around the existing 8-foot-by-22-foot pier to a depth of 10 feet below the scour line, dewatering the area, and filling the scour hole with approximately 11.5 cubic yards of controlled low-strength material in 3-foot layers. This process will result in 0.0007 acre of new fill. Additionally, the project requires the removal of two abandoned piers and associated sheet-pile cofferdams from the Cottonwood Creek channel, which will be cut 3 feet below the ground line. The removal of these abandoned structures and the associated staging and work areas will result in total temporary impacts of 0.097 acre, including 0.018 acre and 32 cubic yards of impact specifically from the pier located below the ordinary high water mark. Upon completion of construction, all debris will be removed, and temporary work areas will be restored to their pre-project contours. The project has been granted a Notice of Exemption from CEQA review by the Central Valley Regional Water Quality Control Board under section 15301, as the work constitutes maintenance and repair of an existing private structure with negligible expansion of use.

General Info

Repair of pier 6 and removal of abandoned piers at UPRR Valley Subdivision.

Agency

California → Regional Water Quality Control Board, Region 5 - Redding

Place of Performance

CA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Regional Water Quality Control Board, Region 5 - Redding
Contacts3 people available
OfficeN/A
Organization / Agency
California → Regional Water Quality Control Board, Region 5 - Redding
Office AddressN/A
Contacts
Lynn CosterSenior Environmental Scientist
Stephen CheneySenior Director Design & Environmental
Samuel BohannonSenior Regulatory Project Manager

Full Description

Show more
The proposed project will repair pier #6 of the existing bridge at Milepost 239.83 on the Valley Subdivision. An excavator equipped with a vibratory sheet driver will install steel sheet-pile forms a minimum of 6 inches from the perimeter of the existing 8-foot-by-22-foot pier to a minimum depth of 10 feet below the scour line, containing a 9-foot-by-23-foot area. If any standing water remains in depressions adjacent to the pier, a pump will dewater the area contained by the sheet pile, and the contained area will be excavated to create a void. Controlled low-strength material (CLSM) will be pumped into the scour hole in 3-foot-deep layers and allowed to cure before the next layer is poured. CLSM poured between the existing pier and the sheet-pile form will result in 0.0007 acre of new fill. When poured to a depth of 10 feet below the scour line, a volume of approximately 11.5 cubic yards of CLSM will be required. Additionally, two existing abandoned piers and associated sheet-pile cofferdams from a previous bridge, each approximately 12-feet by 24-feet, will be removed from the Cottonwood Creek channel. The structures will be cut 3 feet below the ground line. One of the two abandoned pier structures is below the ordinary high water mark of Cottonwood Creek, and its removal will result in 0.018 acre and 32 cubic yards of temporary impacts. With the staging and work area for the Project, the combined total of temporary impacts will be 0.097 acre. Following construction activities, debris will be removed, temporary work and staging areas will be restored to pre-project contours as necessary, and best management practices will be removed.

Similar Contracts

Same NAICS industry code

NAICS: 237310
New
North Hollywood Central Remediation Well Collector Line; IFB No. 8003R1
Solicitation # 8003R1
Kiewit Infrastructure West Co. is soliciting sub-quotes for the North Hollywood Central Remediation Well Collector Line project, an initiative for the City of Los Angeles Department of Water and Power located in California. The comprehensive scope of work includes underground utilities such as tunneling, boring, jacking, and micro tunneling, as well as site work involving land surveying, site clearing, shoring, and subsurface investigation. Additional requirements encompass surface improvements like asphalt paving, landscaping, and the installation of traffic signs, signals, and lighting, along with environmental support services including storm water pollution prevention. Required materials include ready mix supply, precast concrete, and aggregate. This solicitation is open to qualified Small Business, Women-Owned Small Business, and Disadvantaged Business Enterprise subcontractors and suppliers. To be considered, responsive bidders must possess a valid California Contractor's license, provide acceptable insurance, and be capable of providing bonding for 100 percent of their contract value, with bond premiums reimbursed by Kiewit. Bidders must also demonstrate an ability to maintain labor harmony on the project. Interested firms must be issued an Invitation to Bid through the Building Connected electronic system, with a response deadline of November 18, 2025. Primary contact for this effort is Lead Estimator Ken Johnston.
Kiewit Infrastructure West Co.

POSTED

about 3 hours ago

DEADLINE

in 21 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS