Vernon Backup Generating Facility

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

GIC Vernon LLC is applying to the California Energy Commission for a Small Power Plant Exemption for the Vernon Backup Generating Facility in Vernon, California. This 99 MW emergency power system is designed to support the Goodman Energy Park data center, consisting of two buildings located at 3163 and 3049 East Vernon Avenue. The facility will be constructed on an 11.55-acre site and will feature 40 diesel generators, including 38 3-MW units for critical loads and two 1-MW house generators for life-safety and building systems. The system is electrically isolated from the regional grid and will only operate when electricity from Vernon Public Utility is unavailable. The project includes a new Soto switching station and an onsite project substation, with generators arranged in two separate yards tied to their respective data center buildings. Regulatory compliance requires adherence to the California Environmental Quality Act, National Pollutants Discharge Elimination System permit requirements under the Clean Water Act, and permits from the South Coast Air Quality Management District. Project management is led by Elizabeth Huber and Kaycee Chang. The current phase involves a Draft Environmental Impact Report under solicitation 25-SPPE-01 to determine if the project qualifies for an exemption from CEC certification.

General Info

99 MW diesel backup power system for Goodman Energy Park data center, emergency use only, no grid export.

Agency

California → Energy Commission

Place of Performance

Vernon Avenue and Soto Street, Vernon, CA, 90058

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Get full access to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Energy Commission
Contacts2 people available
OfficeN/A
Organization / Agency
California → Energy Commission
Office AddressN/A
Contacts
Elizabeth HuberProject Manager
Ward MaceRegional Director

Full Description

Show more
GIC Vernon LLC is applying to the California Energy Commission (CEC) for a Small Power Plant Exemption (SPPE) for the Vernon Backup Generating Facility (VBGF), a 99 MW emergency only power system that will support the Goodman Energy Park (GEP) data center in the City of Vernon. The GEP consists of two data center buildings located near Vernon Avenue and Soto Street, with addresses at 3163 and 3049 East Vernon Avenue. The project includes forty (40) diesel generators with thirty eight (38) 3 MW units dedicated to data center critical loads, and two 1 MW house generators that supply office, building, and life safety systems during outages. The backup system is designed to operate only when electricity from Vernon Public Utility is unavailable. It will not connect to the regional transmission grid or export power. Instead, the generators are arranged in two separate generation yards, each directly tied to its respective data center building

Similar Contracts

Same NAICS industry code

NAICS: 221112
Federal
SPE60427R0400 - MISO 2027
Solicitation # SPE60427R0400
Solicitation SPE60427R0400 is a request for proposal issued by DLA Energy for a Firm Fixed-Price Requirements Type contract to supply electricity, including ancillary and incidental services, to various Department of War and Federal Civilian facilities within the Midcontinent Independent System Operator (MISO) market area. The scope covers four specific locations: the Army Corps of Engineers, Scott Air Force Base, the US Department of Agriculture-National Center for Agriculture Utilization Research, and the Illinois Air National Guard. The contract features a 24-month delivery period starting from the May 2027 meter read date through the May 2029 meter read date, with a total estimated quantity of 240,033,144 kWh across four contract line item numbers. The award will be based on the best value, considering price and non-price factors. Past performance is the most critical non-price factor, followed by technical capability and risk, and finally small business participation. Price is weighted approximately equal to the combined non-price factors. Proposals must be submitted through the PIEE Solicitation module, and pricing will be handled via a reverse auction at a later date. Offerors must maintain active SAM registration and provide a Unique Entity Identifier and CAGE code. The contract incorporates standard commercial terms under FAR 52.212-4 and includes specific requirements for HUBZone and small business preferences, as well as Buy American and domestic commodity certifications.
DLA Energy

POSTED

14 days ago

DEADLINE

in 27 days
View Details
NAICS: 221112
SLED
Northtown Backup Generating Facility
Solicitation # 25-SPPE-02
The Northtown Backup Generating Facility is a 97.3 megawatt diesel-fired emergency power system designed to provide uninterrupted backup power exclusively to the Northtown Data Center in San José, California, without any connection to the transmission or distribution grid. Located on a 28.5-acre site at the southwest corner of West Trimble Road and Orchard Parkway on APNs 101-02-018 and 101-02-021, the facility will consist of 42 diesel generators—40 rated at 3 megawatts each and two smaller units at 1.75 megawatts—arranged in two generation yards adjacent to the data center buildings. Of the 3-megawatt units, eight are designated as redundant to ensure reliability. The two smaller generators will support office loads, building systems, and life safety services. The facility will include a new 115-kilovolt to 34.5-kilovolt, 110-megavolt-ampere electrical substation with a two-bay, two-transformer design, allowing one transformer to be taken offline without loss of service, effectively providing 105 megavolt-amperes of redundancy. On-site diesel fuel storage capacity is 234,000 gallons, and the generators will operate using renewable diesel fuel to minimize emissions and comply with sustainability mandates. The project is subject to comprehensive environmental review under the California Environmental Quality Act and requires permits from the Bay Area Air Quality Management District, the City of San José, the California Department of Fish and Wildlife, and the Federal Aviation Administration for structure height compliance. It must also participate in San José Clean Energy’s Total Green program to ensure 100 percent carbon-free electricity use. The California Energy Commission is the lead agency overseeing the project and has determined it qualifies for an exemption under Public Resources Code §25541. All generators must meet Tier 4 emissions standards with controls for nitrogen oxides and diesel particulate matter. Environmental mitigation measures include noise reduction, wildfire risk management, and protection of biological and cultural resources, with preconstruction surveys mandated. The project is currently in the environmental review phase, with a public comment period scheduled from July 21 to August 20, 2026. No procurement or contract pricing details are available, and while the project is not governed by federal acquisition regulations, compliance with state and local environmental, zoning, and safety codes
Energy Commission

POSTED

4 months ago

DEADLINE

N/A
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS