This Award Notice opportunity from Department Of The Interior was posted on April 16, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
Solicitation 140P6326B0002 is a firm-fixed-price construction contract issued by the Department of the Interior, National Park Service, for the rehabilitation of the Cedar Pass Lodge Cabin road at Badlands National Park in Interior, South Dakota. The project scope includes repairing the roadway subgrade, base, and surfacing, improving drainage, and constructing an earthen berm to mitigate flooding. This effort is set aside 100% for small businesses under NAICS code 237310. The contractor is required to adhere to strict paleontological and archaeological protection protocols and follow specific work hour restrictions to minimize visitor disturbance, particularly around cabin areas.
The total period of performance is 120 calendar days, anticipated to begin on August 17, 2026. The work is divided into two phases: Phase 1 occurs in Fall 2026, focusing on ditch, berm, and grading work, while Phase 2 is scheduled for Spring 2027 to complete remaining tasks if winter delays occur. Contractors must submit a comprehensive bid package electronically, including a completed SF-1442, a bid guarantee, and a limitations on subcontracting report. Invoicing is mandated through the U.S. Department of the Treasury's Invoice Processing Platform. Compliance with South Dakota Heavy and Highway prevailing wage rates and various FAR construction clauses is required.
HighAI Summary for 140P6326B0002 Amendment 0001: Amendment 0001 to solicitation 140P6326B0002, issued on February 24, 2026, by the National Park Service (NPS). The primary purpose of this amendment is to extend the solicitation close date to April 08, 2026, to allow the Government additional time to provide answers to questions resulting from a site visit.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for 140P6326B0002 Amendment 0002: Amendment 0002 to solicitation 140P6326B0002 for the Badlands NP Rehab Cedar Road project, dated February 24, 2026. This amendment corrects the bid closing date to April 8, 2026, at 12:00 PM mountain time and incorporates questions and answers from the site visit into the solicitation specifications.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for 140P6326B0002 Amendment 0003: Amendment 0003 to solicitation 140P6326B0002, dated February 24, 2026. The purpose of this amendment is to incorporate the final set of questions and answers into the solicitation. No changes were made to the offer submission deadline.
PDF
PDF, High priority: read this firstifb
HighAI Summary for 140P6326B0002 - Badlands National Park Roadway Replacement: Invitation for Bids (IFB) issued on 02/24/2026 for a firm fixed price construction contract at Badlands National Park, Cedar Road Lodge. The project involves replacing granular surfaced roadway, minor grading, excavation, and construction of an earthen berm. Bids are due by 1300 local time on 03/24/2026. Performance is required within 120 calendar days of the Notice to Proceed, with an anticipated start date of August 17, 2026.
XLSX
XLSX, High priority: read this firstspecifications
HighAI Summary for Attachment 6 - Limitations on Subcontracting Report Template: A reporting template (v1, December 15, 2016) used to track and calculate the limitations on subcontracting. It includes specific formats for both standard contracts and Indefinite Delivery Vehicles (IDVs), requiring data on payments to similarly situated and non-similarly situated subcontractors to determine compliance percentages.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for B08 Solicitation Attach 2 - Badlands National Park Drawings: Technical drawings and specifications for a project at Badlands National Park, Interior, South Dakota (PIMS No. 239351). The document includes a contractor staging area plan, drainage channel plans, profiles, cross sections, and berm cross sections, dated May 2025. It contains specific technical notes regarding erosion control blankets and soil waste site locations.
DOCX
DOCX, High priority: read this firstamendment
HighAI Summary for B08 Solicitation Attachment 3: Period of Performance Addendum: This document serves as an amendment to the Period of Performance narrative in the specifications. It establishes a total work duration of 120 calendar days, divided into Phase 1 (Fall 2026) and Phase 2 (Spring 2027), with specific constraints regarding work hours and dates around cabin areas to minimize visitor disturbance.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for BADL 239351 - Rehabilitate Cedar Pass Lodge Cabin Road Submittal List: A detailed submittal list for project BADL 239351, 'Rehabilitate Cedar Pass Lodge Cabin Road'. The document specifies required documentation, including safety plans, insurance, construction schedules, quality control plans, and material test reports, mapped to specific specification sections and paragraph numbers.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for Badlands National Park - Cedar Pass Lodge Cabin Road Project Specifications: Project specifications dated May 16, 2025, for the rehabilitation of the Cedar Pass Lodge Cabin road at Badlands National Park (PMIS 239351). The scope includes repairing roadway subgrade, base, and surfacing, improving drainage, and constructing an earthen berm to mitigate flooding. Key requirements include a 120-calendar day period of performance, strict adherence to paleontological and archaeological protection protocols, and coordination with the COR for utility protection and ground disturbance oversight.
DOCX
DOCX, High priority: read this firstq-and-a
HighAI Summary for BADL Cedar Project - Amendment 3 Q&A: Question and Answer document dated April 3, 2026, associated with Amendment 3 of the BADL Cedar Project. It provides clarifications on electronic file availability, soil waste stockpile removal, corrections to drawing sheet references (C14 to C15), aggregate reuse specifications, and water valve locations.
PDF
PDF, High priority: read this firstq-and-a
HighAI Summary for BADL Cedar Road Repair - Question and Answers (Amendment 2): A Question and Answer document dated March 25, 2026, associated with Amendment 2 for the BADL Cedar Road Repair project. It provides clarifications on onsite water availability, work windows (8AM-4:30PM), utility verification responsibilities, borrow sources, archaeological monitoring, and permit requirements.
DOCX
DOCX, High priority: read this first2 pages · presolicitation
HighAI Summary for Invitation for Bid 140P6326B0002 for Cedar Lodge Road Repair: This pre-solicitation notice from the National Park Service Contracting Operations announces an upcoming Invitation for Bid (IFB) for construction services to repair Cedar Lodge Road at Badlands National Park, South Dakota. The project involves roadway resurfacing, grading, excavation, and berm construction with a firm-fixed price contract expected to be awarded in Spring 2026. The work is planned in two phases spanning Fall 2026 and Spring 2027, with specific calendar days and start/end dates outlined. The acquisition is set aside for 100% small business, with applicable wage rate requirements. The formal solicitation with specifications is anticipated to be issued around February 24, 2026, with responses due approximately 30 days later. Registration in SAM and a UEI number are required for award eligibility. Contact information for the contracting officer is provided.
PDF
PDF, High priority: read this firstwage-determination
HighAI Summary for SD20260001 Wage Determination - South Dakota Heavy and Highway: General Decision Number SD20260001 dated 01/30/2026 for Heavy and Highway construction projects statewide in South Dakota. The document specifies prevailing wage rates and fringes for various labor classifications, including Electricians, Ironworkers, Laborers, Painters, Power Equipment Operators, and Truck Drivers. It also includes notices regarding Executive Orders 13706 and 13658 concerning paid sick leave and minimum wage requirements.
DOCX
DOCX, High priority: read this first2 pages · sources-sought
HighAI Summary for Sources Sought for Rehab Cedar Lodge Road, Badlands National Park: This sources sought notice, reference number 140P6326B0002, issued by the National Park Service, seeks market information from vendors for a potential project to rehabilitate the Cedar Pass Lodge Cabin area roadway in Badlands National Park, Interior, SD. The project includes replacement of granular surfaced roadway, grading, excavation, and construction of an earthen berm, to be completed within 120 calendar days from the start date. The notice clarifies this is not a solicitation but a market survey to inform acquisition strategy. Interested firms must submit capability statements, size status, bonding capability, and contact information by 12:00 Noon MT, February 4, 2026, via email. The NAICS code is 237310 with a small business size standard of $45 million.
This is an IFB (invitation for bids) for construction services to rehab Badlands National Park Cedar Lodge Road. The purpose of amendment 1 is to extend the close date to April 08, 2026. This will allow the Government to finish answering questions received from the site visit.
More opportunities from Department Of The Interior → Mwr NEKOTA(63000)