19CG5026R0010 - Front Perimeter Wall Repair
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
The U.S. Embassy in Kinshasa is seeking a contractor to repair a collapsed section of the front perimeter wall at the 103 Roi Baudouin residence compound, which gave way under the weight of a fallen tree and heavy rainfall. The repair work will extend beyond the immediate collapse area to include additional unstable segments, with the total wall length to be confirmed during an on-site walkthrough. The contractor is responsible for replacing damaged electrical wiring and lighting, reinstalling concertina wire, backfilling the entrance parking area, and replacing pavers to restore the site to its original condition. All materials must be approved by the Contracting Officer Representative before any installation begins, and the contractor must provide all labor, equipment, and materials needed to complete the work. The project must be finished within 60 days of award, and all proposals must be submitted in English by the deadline of August 3, 2026. The solicitation, identified as 19CG5026R0010 under NAICS code 238190, is managed by the Department of State through the U.S. Embassy in Kinshasa, with inquiries directed to Vernetta Wheeler and Annie N’tula.
General Info
Agency
NAICS
Place of Performance
Kinshasa, CD-KN, CODSet-Aside
Documents
(1)AI Contract Breakdown
Uniform Contract FormatWhat is UCF?
Uniform Contract Format (UCF) uses AI to break down any contract into standardized sections—scope, pricing, deliverables, and evaluation criteria.
Timeline
Response Deadline
Organization & Contact Information
Full Description
Overview of the project:
The U.S. Embassy has a project requirement to repair a section of the 103 Roi Baudouin residence Compound front perimeter wall that collapsed due to a big tree roof and a heavy rain. In addition to the collapsed portion, several addition feet will need to be rebuilt due to be unstable after the collapse. The wall is estimated to be 22m long, with the exact length needed to be repaired to be revealed during the walkthrough stage of the project solicitation.
The contractor will also make sure to replace the damaged electrical wire as well as lights, to replace the concertina wire, backfill the entrance parking and then replace the pavers.
The selected contractor will supply all labor, materials and equipment required to successfully complete this project. All material will be inspected and approved by the Contracting Officer Representative (COR) before installation can start.
The project must be completed in 60 days, and the offer must be submitted in English.