The Plano Independent School District has issued a request for proposals to select a Construction Manager at Risk through a one-step process for the renovation and compliance upgrades of its three-story administration building located at 2700 W. 15th St., Plano, Texas. The project, with an estimated construction budget of 5.8 million dollars, involves significant mechanical, structural, and interior improvements, including replacing two chillers, roof replacement, skylight removal, and various interior upgrades such as new paint, flooring, LED lighting, door hardware, signage, restroom enhancements, and entry security film. The design phase is scheduled from January 19 to March 29, 2024, with bid solicitations beginning in April and the final approval of the Guaranteed Maximum Price expected by May 21, 2024. Construction is planned to commence in early June 2024, with work to be completed in 4-5 phases, culminating in substantial completion by March 14, 2025, while portions of the building remain occupied. The project’s procurement process includes a virtual open house scheduled for February 13, 2024, and the contract approval is anticipated by the Plano ISD Board of Trustees in March 2024. The selected construction manager will oversee phased construction activities, ensuring compliance with project specifications and schedules. The contract details, including response deadlines and contact information, are publicly available, emphasizing transparency and adherence to procurement policies. This project aligns with the district’s ongoing efforts to modernize and secure its administrative facilities, ensuring functional and safety improvements within the designated budget and timeline.
General Info
Place of Performance
TX, USASet-Aside
Timeline
Submission Closed
Organization & Contact Information
Full Description
The Plano ISD Administration Building is three-stories, and work will include the replacement of two chillers, roof replacement, and removal of an existing large skylight. Interior work will include new paint, new flooring on a portion of the 3rd floor, new LED lighting, new door hardware, new room signage, and restroom upgrades, entry resistant film.
The estimated construction budget is $5.8M
Location –2700 W. 15th St. Plano, TX 75075
RECOMMENDATION TO BOARD OF CM@R APPROVAL: March 19, 2024 Proposed Construction Schedule:
Design and Documentation: 01/19/24 – 03/29/24 Issue for sub bids: 04/02/24 Sub bids due: 04/23/2024 School board approval of GMP: 05/21/2024 Construction start: 06/03/2024 Construction to be completed in 4-5 phases while portions of the building are occupied Substantial Completion of final phase: March 14, 2025 VIRTUAL OPENING ZOOM CREDENTIALS:
Veronica Couzynse is inviting you to a scheduled Zoom meeting.
Topic: Veronica Couzynse's Zoom VIRTUAL Opening CMAR Admin Building Systems & Compliance Time: Feb 13, 2024 02:00 PM Central Time (US and Canada)
Join Zoom Meeting https://planoisd.zoom.us/j/3804467644?pwd=S09iMHgvR1NyNkx2S2ZqTnYzek5wQT09&omn=98935047748
Meeting ID: +1 (555) 000-0000 Passcode: 9S5Att
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS