This Solicitation opportunity from Iowa was posted on March 11, 2025. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
2025 Pavement Markings Program
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The contract involves the application of pavement markings across various streets in the City, including edge lines, centerlines, barrier lines, double yellow lines, turn lane lines at intersections, crosswalks, and symbols. The work is divided into two phases: the first application, focusing on lane lines, symbols, and crosswalks, must commence on or after April 2, 2025, and be finished by July 15, 2025, with a 45-day completion window once started. The second application, which includes only lane lines, is scheduled to begin on or after September 15, 2025, and conclude by November 15, 2025, with a 20-day completion period. Both phases are mandatory to complete within their respective deadlines, regardless of remaining work days, with liquidated damages of $500 per day for delays past the deadlines. Bidders are required to submit their proposals through the eBidding system by the response deadline of March 25, 2025. The contract is valued at approximately $500, and the project is managed by the Iowa-based organization, with primary contact Pat Lynch available via email and phone for inquiries. The project emphasizes timely execution and adherence to specified schedules to ensure the pavement markings are completed efficiently across the designated city streets.
General Info
Agency
Place of Performance
IA, USASet-Aside
Timeline
Submission Closed
Organization & Contact Information
Full Description
All work on this contract shall be completed in two applications. The first application shall start on or after April 2, 2025 and be completed by July 15, 2025. The second application shall start on or after September 15, 2025 and be completed by November 15, 2025. The first application includes all lane lines, symbols and crosswalks. The second application will only include the lane lines. Once started, the contractor shall have 45 working days to complete the first application and 20 working days for the second application. Both applications must be completed by the completion dates listed above, regardless of remaining working days. The beginning and completion dates will be included in and made part of the contract between the successful bidder and the City. Liquidated damages in the amount of Five Hundred Dollars and no/100 ($500.00) per calendar day shall be charged for every day past the completion date.
Vendors must log in to the eBidding system in order to submit a bid.
Earlier notices in this NAICS code
Posted before this notice, open and closed
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS