53rd Ave Widening Project, from Crow Creek bridge to Middle Rd
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The project involves expanding approximately 5,000 linear feet of 14.5-foot-wide Portland Cement Concrete pavement on 53rd Avenue between Devils Glen Road and Middle Road, upgrading the existing two-lane corridor to a four-lane roadway. The scope includes constructing new sidewalks to enhance pedestrian connectivity, reconstructing storm sewer intakes, adjusting manholes, and performing pavement striping, sodding, erosion control, and traffic management to facilitate the road reconstruction. The work must adhere strictly to the plans and specifications provided by the City's engineering team. Construction is scheduled to begin no earlier than July 14th, 2025, weather permitting, with a maximum allowable work gap of five days after commencement. The project must be completed by October 30th, 2025, with liquidated damages of $500 per day applicable for delays beyond the deadline or the allowable work gap. Bidders are required to submit their pricing exclusively through the designated online platform, with no manual or electronic responses accepted. The contract is managed by the City of Bettendorf, Iowa, and the primary contact for inquiries is Brian Fries.
General Info
Documents
8AI Contract Breakdown
Uniform Contract FormatContract not broken down yet
CLEATUS splits the solicitation into Uniform Contract Format (UCF) sections: scope, pricing, deliverables, and evaluation criteria.
Timeline
Submission Closed
Organization & Contact Information
Full Description
The bidder to whom the Contract is awarded shall commence work no later than the date to begin work set forth in a Notice to Proceed from the City or its authorized representative, to the Contractor. All work shall be done in strict compliance with the plans and specifications prepared by the Engineer of the Engineering Division of the Public Works Department of Bettendorf, Iowa.
All work on this contract shall commence on or after July 14th, 2025, as weather permits. No more than a 5-calendar day work gap will be allowed for this contract after work begins on the project. Liquidated damages in the amount of Five Hundred Dollars and no/100 ($500.00) per calendar day shall be charged for every day after any 5-calendar day work gap. All work on this contract shall be completed by October 30th, 2025. The beginning and completion dates will be included in and made part of the contract between the successful bidder and the City. Liquidated damages in the amount of Five Hundred Dollars and no/100 ($500.00) per calendar day shall be charged for every day past the completion date.
Responders are to submit pricing via this online bidding platform. No manual, faxed, or emailed bid responses will be accepted.
Earlier notices in this NAICS code
Posted before this notice, open and closed
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS