The Air Force is seeking a small business contractor to install and integrate two government-owned Ingersoll Rand compressors, dryers, and glycol coolers into Building 269 at Hill Air Force Base, Utah. The work involves providing labor, tools, and standard materials such as piping, wiring, and epoxy to connect the equipment to the facility’s 460V electrical system and compressed air loop. All major equipment is Government Furnished Property, and the contractor must comply with Davis-Bacon prevailing wage requirements. Access to critical facility drawings is restricted as Controlled Unclassified Information and requires verified SAM.gov credentials. The solicitation has a strict timeline with key deadlines including a site visit RSVP due on July 20, 2026, a pre-quote site visit scheduled for July 23, and a contractor Q&A deadline of July 27. Quotes must be submitted by August 4, 2026, and the installation must be completed no later than August 17, 2026, to maintain the manufacturer’s warranty. This is a Total Small Business Set-Aside under NAICS code 238220, with the contract managed by the Department of Defense through the FA8224 AFSC OL H PZIM office in Hill AFB, Utah. Primary point of contact is Willie Little, with Joshua Akinwande as secondary.
General Info
Agency
NAICS
Place of Performance
Hill Air Force Base, UT, 84056, USASet-Aside
Timeline
Response Deadline
Organization & Contact Information
Full Description
The Air Force is soliciting a 100% Small Business Set-Aside for a contractor to install and integrate a Government-furnished compressor and cooling system at Hill AFB, Utah.
Key Project Details:
-
The Work: The contractor will provide the labor, tools, and standard materials (piping, wiring, epoxy) to physically install two government-owned Ingersoll Rand compressors, dryers, and glycol coolers into Building 269 and connect them to the base's 460V power and air loop.
-
The Constraints: All primary machinery is Government Furnished Property (GFP). Facility drawings are Controlled Unclassified Information (CUI) requiring vetted SAM.gov access. Davis-Bacon prevailing wages apply.
-
Critical Deadlines:
-
Site Visit RSVP Deadline: 20 July 2026
-
Pre-Quote Site Visit: 23 July 2026
-
Contractor Q&A Deadline: 27 July 2026
-
Quotes Due: 04 August 2026
-
Mandatory Completion: On or before 17 August 2026 (Strict deadline to preserve the manufacturer's warranty).
-