This Solicitation opportunity from Government of Canada was posted on December 21, 2023. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
Anchor blocks installation– Ile d’entrée – Magdalen Islands Region
Closed
30005185CanadaSubmission Closed
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
General Info
Agency
Government of Canada → Fisheries and Oceans CanadaView Agency
NAICS
N/A
Place of Performance
*Gaspésie–Îles-de-la-Madeleine, CANSet-Aside
NONE
Documents
(0)AI Contract Breakdown
Uniform Contract FormatNo contract breakdown available.
Cannot generate Contract Breakdown because no documents were found from this contract's source.
Timeline
PhaseClosed
Submission Closed
Organization & Contact Information
Show more
AgencyGovernment of Canada → Fisheries and Oceans Canada
Contacts1 person available
OfficeN/A
Office AddressN/A
Contacts
Full Description
Show more
SCOPE OF WORK
The work is in Ile d’Entrée harbor and includes, but without being limited to:
1. Demolition and disposal of part of items shown on plans.
2. Excavation and recovery of stones in existing rock embankments
3. Construction and installation of gangway blocks cribworks (timbers or plastic pieces and hardware supplied by DFO);
4. Installation of anchor blocks supplied by DFO; .
5. Supply and installation of lamp post base, electrical conduits and pulling cable;
6. Installation of new section of armor rock protection
7. It is to consider that Department of Fisheries and Oceans (DFO) already acquired stones for actual project that will be available on January 15th 2024
.1 Armor rock stones;
.2 Filter stones;
.3 20mm stones
.4 Mg 20
8. Material supplied by DFO will be shipped by DFO onsite.
9. Contractor will be in charge of users security onsite.
FAMILIARIZATION WITH SITE
Before submitting a bid, bidders can visit the site and its surroundings, at their own expense, to review and verify the form, nature, and extent of the work, materials needed for the completion of the work, the means of access to the site, severity, exposure, and uncertainty of weather, soil conditions, any accommodations they may require, and in general shall obtain all necessary information as to risks, contingencies, and other circumstances which may influence or affect their bid. No allowance shall be made subsequently in this connection on account or error or negligence to properly observe and determine the conditions that will apply.
CONSTRUCTION TIME
The Contractor must perform and complete all Work by June 30, 2024.
Note: If the contractor requires the use of a boat to complete the work noted above, Marine Liability Insurance will be required. The contractor’s insurance policy must be submitted to the Contracting Officer prior to the commencement of work.