Broadway Street and Sargent Street Water Pipeline Replacement

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The City of Gilroy is forecasting a public works project to replace aging water infrastructure on Broadway Street and Sargent Street in Gilroy, California. The scope of work involves the removal and abandonment of approximately 370 feet of six-inch pipeline on Broadway Street and the abandonment of a four-inch pipeline on Sargent Street. In their place, the project will install approximately 1,510 feet of new eight-inch ductile iron pipeline using open trench methods, with 1,300 feet located between Wayland Lane and Hanna Street and 210 feet located between Broadway Street and First Street. The project is managed by Utilities Director Heath McMahon and is classified as a ministerial action exempt from the California Environmental Quality Act (CEQA) because the pipeline replacements are under one mile in length. Environmental filings and associated fees were processed through the Santa Clara County Clerk-Recorder's Office in July 2025. While the project is currently listed as a forecast with a posted date of July 30, 2025, no formal contract value, specific performance period, or federal acquisition regulation clauses have been established. All work is to be performed within the public right-of-way in accordance with current construction codes and municipal standards.

General Info

Gilroy replaces aging water pipelines with new ductile iron lines along Broadway and Sargent Streets using open trench methods.

Agency

California → City of Gilroy

Place of Performance

Broadway Street from Wayland Lane to Hannah Street and Sargent Street from Broadway to First Str, Gilroy, CA, 95020

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → City of Gilroy
Contacts1 person available
OfficeN/A
Organization / Agency
California → City of Gilroy
Office AddressN/A
Contacts
Heath McMahonUtilities Director

Full Description

Show more
On Broadway Street, approximately 370 feet of existing six-inch water pipeline would be removed, and the rest abandoned. Approximately 1,300 feet of new eight-inch ductile iron pipeline would be installed in the public right-of-way between Wayland Lane and Hanna Street using open trench methods. On Sargent Street, the existing four-inch water pipeline would be abandoned in place, and approximately 210 feet of new eight-inch ductile iron pipeline would be installed in the public right-of-way between Broadway Street and First Street using open trench methods.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
Federal
Z2NZ-- 658-23-108 Correct Stormwater Drainage
Solicitation # 36C24626B0031
Solicitation 36C24626B0031 is a firm-fixed-price sealed bid invitation for Project 658-23-108, which entails correcting stormwater drainage at the Salem VA Medical Center in Salem, Virginia. The project is a 100% set-aside for certified Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 237110. The estimated magnitude of construction is between $10,000,000 and $20,000,000, with a performance period of 450 calendar days from the issuance of the Notice to Proceed. The scope of work includes general construction and utility work, specifically requiring the installation and 24/7 operation of a dewatering system and the use of flowable fill for backfilling in designated areas. The award will be made to an eligible SDVOSB that meets specific qualification criteria, including the completion of three projects of similar complexity and value within the last three years and a clean record regarding EPA and OSHA asbestos regulations. The prime contractor is required to perform at least 15% of the construction work. Bidders must be registered in the System for Award Management (SAM) and provide a bid guarantee of at least 20% of the bid price, capped at $3,000,000. Following several amendments, the final bid submission deadline is November 10, 2026, at 5:00 PM EST. Required submission documents include a signed SF 1442 offer page, an SF 24 bid bond, and a signed VAAR 852.219-75 Certificate of Compliance.
246-NETWORK Contracting Office 6 (36C246)

POSTED

about 5 hours ago

DEADLINE

in 21 days
View Details
NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project, solicitation number SRP-W-134-0290, is a construction contract for the City of Belmont in North Carolina with a project estimate of 16,690,000 dollars. The scope of work involves the construction of 16,435 linear feet of new 20-inch ductile iron force main and comprehensive upgrades to the Morgans Branch Pumping Station. Key infrastructure improvements include the installation of a new wet well, valve vault, and associated appurtenances, as well as the demolition of existing pumps and piping. The contractor is responsible for delivering a fully operational station featuring mechanical and electrical systems, including pumps, a generator, and odor control equipment, along with new gravity sewers and manholes. The contract is a small business set-aside and will be awarded to the responsible bidder submitting the lowest responsive bid. Bids must be submitted using the EJCDC C-410 form and include a bid bond, evidence of signing authority, and MWBE compliance documentation. Performance and payment bonds are required upon award. Project administration follows EJCDC standard general and supplementary conditions, with payments processed monthly via applications for payment reviewed by the Engineer. Final acceptance is contingent upon a substantial completion inspection, the resolution of a punch list, and a final inspection conducted by the Owner, Contractor, and Engineer.
Don Moorhead Construction, Inc.

POSTED

about 11 hours ago

DEADLINE

in 20 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS